Topic: POCO considering charging customers for new transformer.

User: cwgreenelectric, Location: Washington County Florida

Asked on: Tuesday, August 6, 2024 at 9:26 am EDT
Answered on: Thursday, March 6, 2025 at 12:47 am EST

Question: What are your thoughts?I recently had a service call to check out dimming lights in a residence that recently had an addition ( converted a carport to a room).During my survey I found a new 18kw electric tankless water heater. Every time it came on the voltage feeding the house dropped 30 volts. This was measured at the top of the meter. I had the customer contact the poco for repair. Customer indicated 2 weeks later that the problem was fixed.A few days later I ran into a manager from the poco and asked what they found. She told me that they are tired of having to change transformers and service drops because customers are installing these high wattage electric appliances without first checking with them about service requirements and are likely going to start charging customers for the upgrades.The house was mid 70s and probably 1 of 3 houses on the transformer. House had original 200a service and well within the 200a load calculation. Currently there are 5 houses on the service transformer.How can the poco justify charging customers for upgrades to their system when the home is still well under load of the original service supply equipment?

This is a complex situation with valid arguments on both sides. Here's a breakdown of the factors involved and my thoughts

Poco's Perspective (Likely Justification):
Transformer Capacity & Distribution

While the house's load calculation might be under 200A, the
transformer is likely overloaded specifically because of the tankless water heater's high, intermittent draw. Transformers are designed for relatively even loading across their life. A sudden, massive surge of power from a tankless heater, especially on a system with several other homes, can cause voltage drops, overheating, and premature failure of the transformer. Even if the overall calculated load could be supported, the instantaneous load exceeds the transformer's capacity.

Cumulative Impact

The POCO is likely seeing a pattern. One house might not be an issue, but when multiple houses on the same transformer add these high-demand appliances, the cumulative impact stresses the system.

Planning & Scalability

The original system was designed for the loads expected in the 1970s. Modern appliances, especially tankless water heaters and EVs, have fundamentally changed residential power consumption patterns. POCOs need to plan for future growth and upgrade their infrastructure accordingly. However, they can't predict every homeowner's individual decision to install a high-demand appliance.


Customer Responsibility

The POCO's argument is that customers have a responsibility to understand the impact of their appliances on the grid and to consult with the utility before installing equipment that could strain the system. This isn't necessarily about exceeding the calculated load of their panel, but about the nature of the load and its impact on the distribution network.

Cost Allocation

The POCO is passing the costs to those who are causing the infrastructure upgrades. The few who add high current appliances are requiring the POCO to spend money that otherwise would not need to be spent.

Customer's Perspective (Potential Arguments)



Code Compliance

If the home's electrical system (panel, wiring, etc.) is code-compliant and the load calculation remains within the 200A service rating, the customer might argue they've done everything required and shouldn't be penalized.

Fairness

The customer might argue that if the POCO is responsible for providing adequate service to all customers, they should proactively upgrade their infrastructure to meet modern demands, rather than charging individual customers.


Lack of Communication

If the POCO didn't clearly communicate the potential for these charges or provide guidelines on acceptable appliance upgrades, the customer might feel blindsided.

Home improvement is a right

Customers might argue that it is their right to upgrade their home as they see fit within the bounds of the law. As long as local electrical codes are followed the customer is within their rights to improve their home.

My Thoughts and Recommendations



Communication is Key

The POCO should have clearly communicated the potential for these charges before the customer installed the tankless water heater. This is crucial for transparency and customer satisfaction.

Load Calculation vs. Actual Demand

This highlights the difference between a theoretical load calculation and the
actual demand placed on the transformer. Code-compliant load calculations are important, but they don't always perfectly reflect real-world usage patterns, especially with modern appliances.

Grid Modernization

Ultimately, the POCO does have a responsibility to modernize the grid to accommodate changing energy demands. However, they also need to manage costs and incentivize responsible energy consumption.

Tiered Approach

A possible solution could be a tiered approach to upgrades:


Basic upgrades

The POCO covers basic upgrades needed to meet general grid demand (e.g., replacing aging equipment).

Customer-driven upgrades

Customers who install high-demand appliances contribute to the cost of specific upgrades that directly benefit them and are triggered by their choices.


Incentives for Energy Efficiency

The POCO should also consider incentivizing energy-efficient alternatives to tankless water heaters, such as heat pump water heaters.

Transparency

The POCO needs to be transparent about how they calculate the required upgrades and the associated costs.

In the specific scenario you presented

It's a gray area. If the customer's installation was code-compliant and they were unaware of the potential impact on the transformer, it's understandable that they would feel unfairly targeted.However, the POCO's position is also reasonable. They're trying to manage a system that's being stressed by new technologies and want to avoid widespread transformer failures.

Ultimately, the fairness of the POCO's decision likely depends on



The POCO's communication practices.
The specific tariff agreements in place. Local regulations.

The customer could try to negotiate with the POCO or consult with a lawyer to determine their rights. However, a collaborative approach, where the customer and the POCO work together to find a solution (e.g., installing a load management device), is often the most effective. Flag for review