Topic: Need some feedback please

User: Alwayslearningelec, Location: NJ

Asked on: Saturday, August 17, 2024 at 9:52 pm EDT
Answered on: Thursday, March 6, 2025 at 1:18 am EST

Question: Have a job with a lot of RMC Al 4" pipe. I think the guys are off to a bad start with production units and this could seriously hurt the company(like put us out) as there is over 25,000' of this conduit.Just want to give an example of one of the runs installed so far. I understand it's tough to give feedback withoout knowing some of the particulars regarding the install but I really need some sort of feedback. The owners did agree on the labor units I used so that's that. THey have never had a job nearly this big and I really don't think they have guys that have a lot of experiecne with this big conduit. Anyway here it goes.Ceiling are open and at 25-30'Working of lifts.Floors are opend and clear.Material, bending equipment, threaders etc. I assume are close to install area. THey should be right???(4) 100' runs of 4" RMC AL on same 2-1/2' wide trapeze racks.Racks are mounts to steel with beam clamps.Run has (4) 90 degree turns and hits a pull box. At this point it's not terminating yet at the start/finish location.So just accounting for installing the the conduits( incl. elbows, cut and thread, straps etc.) and the racks. Should (2) men be able to do this in (2) weeks?On a side note. Prefab elebow would obviously make the install longer??? What would determine( remeber there is a lot of this conduit) whether they should mostly be using factory elbows or being. The job is anywhere from 4 to 14 sets of conduits in a rack.Thank you very much. Need your help.

Okay, this is a tough situation, but let's break down the installation scenario you've described and address your concerns. I'll try to give you practical feedback based on common industry practices and factors influencing RMC installation.

Assessing the Two-Week Timeframe for Two Men

Let's analyze if (2) men can install (4) 100' runs of 4" RMC AL with (4) 90-degree bends into a pull box in two weeks.

Total Conduit Footage

4 runs x 100 feet = 400 feet


Elbows

4 runs x 4 elbows = 16 elbows

Racks

4 runs on a 2.5' wide trapeze. 4 runs are very doable.


Timeframe

Two weeks (10 working days, assuming 8-hour days) = 80 man-hours

Key Activities & Time Estimates (Rough Estimates - Highly Variable)

This is where it gets tricky. Times will vary wildly based on skill, efficiency, and unforeseen delays. I will use fairly aggressive units assuming your guys are good.

Rack Installation



Assumptions

Beam clamps are pre-fitted, and the racks are easy to maneuver into position. Spacing between racks is pre-determined.

Time

Let's say 4 hours per rack setup (drilling, bolting, leveling, securing with beam clamps for all 4 runs). I'm assuming a rack will cover a 10-20' span. So 100'/10 = 10 racks. That is 4x10= 40 hours for racks.


Conduit Measurement, Cutting, and Threading



Aluminum RMC Considerations

Aluminum RMC is easier to cut and thread than steel. However, large diameter requires proper equipment and technique.


Time

30 minutes per cut/thread + 1 hour of material and equipment setup. 18 total hours

Bending



Aluminum Considerations

Aluminum RMC bends much easier than steel. But 4" is still significant and requires a good bender and experience.

Time

45 minutes per bend (including setup, adjustments, and quality check). Total time will be 4x16 elbows = 645min /60min = 12 hours.


Conduit Installation and Strapping



Assumptions

Two men working efficiently with a lift. Conduits can be easily lifted and positioned. Straps are readily available and easy to install.


Time

15 minutes per 10' section installation, including securing with straps. 400/10= 40 sections. 40 sections x 15min =600min/60min = 10hours.

Pull Box Connection
45 Minutes Miscellaneous



Time

Add 15% for misc. items. Like moving lifts, breaks, planning etc. 14 hours.

Total Estimated Time

Rack Installation: 40 hours Cutting/Threading: 18 hours Bending: 12 hours Installation/Strapping: 10 hours Misc: 14 hours Pull Box: 45 min

GRAND TOTAL

95 hours

Analysis and Recommendation

Based on these aggressive estimates,

two men are unlikely to complete the work in two weeks (80 man-hours).
They are 15 hours over time(12.5%) Overly Optimistic Estimates

The above times are very aggressive. Any delays (material shortages, equipment breakdowns, poor access, unforeseen obstacles) will push the schedule back significantly. The guys may not have the skills necessary to get these aggressive numbers.

4" RMC Handling

Handling 4" RMC, especially at that height, is physically demanding. Fatigue will slow them down.


Rack Setup and Adjustments

Rack installation, especially ensuring proper alignment for multiple conduits, can take longer than estimated.

Pulling Wire

You did not account for pulling the wire. That could take longer than the conduit itself.


Real Numbers

If these guys are coming in over 100-120 hours for all that, then you have a serious problem and the numbers the owners and yourself agreed on are way too low.

Racks

40 minutes/rack for hanging the racks is crazy. 4 racks/day is going to kill the job, and this is without running a single conduit.

Key Questions & Actions


Validate Assumptions

Are materials and equipment
truly readily available at the install location? If not, this adds a lot of non-productive time.2.

Skills Assessment

Objectively evaluate the skill level of the crew with 4" RMC and bending. Talk to them.3.

Track Progress

Meticulously track the time spent on each stage of the installation (rack, cutting, bending, installing). Compare to the estimates.4.

Identify Bottlenecks

Where are the biggest delays occurring? Address these bottlenecks immediately.5.

Communication

Talk to the installers. Understand their challenges. Are they struggling with the bender? Are materials too far away?6.

Re-Evaluate Labor Units

If the initial labor units are
clearly unrealistic based on actual performance, you must have an open conversation with the owners. Explain the challenges and the impact on the project's financial viability.7.

Document Everything

Keep a detailed log of progress, delays, and any changes to the scope of work. This documentation will be crucial for justifying cost adjustments later.

Prefabricated vs. Field-Bent Elbows

This is a crucial decision with huge cost implications.


Prefabricated Elbows



Pros

Consistent quality, faster installation (eliminates bending time), easier to maintain uniformity, often cheaper at scale.


Cons

Less flexibility to accommodate minor field adjustments. Requires precise measurements and coordination. You have to wait for them.

Field-Bent Elbows



Pros

Greater flexibility to adjust to field conditions. Allows for custom bends to avoid obstructions.

Cons

Requires skilled benders, more time-consuming, potentially inconsistent bend quality, more waste.

Recommendation: Lean Heavily Towards Prefabricated Elbows.
Volume

With 25,000 feet of conduit and 4 to 14 sets per rack, the sheer volume of bends makes prefabricated elbows the more efficient choice. The more the merrier as they say with prefab.

Cost Analysis

Get quotes for prefabricated elbows in bulk. Compare the cost (material + labor) against the estimated cost of field bending (material waste + labor). Factor in the potential time savings.


Standardization

Develop a set of standard bend angles and radii to minimize the number of different prefabricated elbow types needed. This will simplify ordering and inventory management.

Action Plan


Stop Production

At least temporarily, until you have a clear understanding of the root causes of the slow progress.2.

Skills Assessment

Work with the team to identify individuals who can perform the racks with 4" RMC. Provide additional training or bring in a specialist if needed. Consider using different teams, one that performs the racks and another the runs.3.

Prefabrication Analysis

Get quotes for prefabricated elbows. Run a detailed cost comparison.4.

Optimize Material Handling

Ensure that materials and equipment are readily available at the point of installation.5.

Revise Labor Units (If Necessary)

If the initial labor units are unrealistic, present a revised estimate to the owners with supporting data.6.

Communicate Clearly

Keep everyone informed about the challenges and the steps being taken to address them.7.

Track Progress Closely

Monitor progress daily and make adjustments as needed.

Important Considerations



Safety

Working at heights with heavy conduit requires strict adherence to safety protocols. Ensure that the crew is properly trained and equipped.


Quality Control:
Regularly inspect the installation to ensure that it meets the required standards.This project has the potential to be a significant success, but it requires careful planning, execution, and monitoring. Don't be afraid to ask for help from experienced contractors or consultants if needed. Good luck! Flag for review