Topic: Seismic Bracing Assistance

User: Dustin Foelber, Location: Chapel Hill, NC

Asked on: Monday, August 19, 2024 at 9:46 am EDT
Answered on: Thursday, March 6, 2025 at 1:20 am EST

Question: Good Morning GentsGetting my butt kicked with the seismic requirements on a healthcare project. I have combed through the OSM details but I am unable to find an answer to a few basic questions. If anyone could help with these I would greatly appreciate it. Project is in Los Angeles at UCLA. I believe CEC is AHJ.Seismic Bracing RequirementsSeismic Bracing RequirementsWhat is the minimum trade size in which seismic is not required?What is the minimum distance from the deck for a trapeze and single conduit in which seismic is not required.What is the minimum lbs per foot in which seismic is not required?

Good morning! Seismic bracing can definitely be a challenge, especially in high seismic zones like Los Angeles. Let's break down your questions based on the information available from ASCE 7-16 (which is typically referenced by the CEC) and common industry practices.

Disclaimer

I am an AI and cannot provide professional engineering advice. You should consult with a qualified structural engineer or a seismic specialist who is licensed in California to ensure your design complies with all applicable codes and project-specific requirements.

Key Code & Standards to Reference



ASCE 7-16

"Minimum Design Loads and Associated Criteria for Buildings and Other Structures". Chapter 13 is crucial for seismic design of nonstructural components.


OSHPD Preapproval (OPA) program

If the hospital project falls under OSHPD jurisdiction, consult the OPA program to see if there is an OPA for your design.

Addressing Your Questions

It is important to note that most of the specific sizes and quantities of components where seismic bracing is not required is left to the Engineer of Record or approved by the AHJ. These numbers can also change with different revisions of ASCE.

1. What is the minimum trade size in which seismic bracing is not required?
General Guidance

ASCE 7-16 and OSHPD guidelines do not provide a specific cut-off trade size for bracing requirements. Instead, the primary determinant is the
importance factor of the equipment, and the component importance factor of the nonstructural elements.

ASCE 7-16 Section 13.6.2 states that Seismic Restraint Not Required



If the component is positively attached to the structure, if the component weighs 20 lbs. or less, or if the component is suspended from a structural member.
A component is exempt from meeting the force design requirements if it's component importance factor (Ip) is equal to 1.0. This is determined in ASCE 7-16 Table 13.
1.3
Practical Interpretation

The typical interpretation is that
very small and lightweight conduit runs do not require bracing. However, what constitutes "very small" and "lightweight" is subjective. OSHPD has been known to provide specific requirements to projects within its jurisdiction.



Recommendation

Check with the AHJ/Engineer of Record for project specific requirements. Consider a cut-off size based on engineering judgement, considering the rigidity of the installation, the height above the floor, and the potential for interaction with other systems if it were to fall. For example, you might decide that conduit 1" and smaller, rigidly mounted close to the structure, does not require bracing, but conduit 1 1/4" and larger always requires bracing.

2. What is the minimum distance from the deck for a trapeze and single conduit in which seismic is not required?


ASCE 7-16 & OSHPD

Again, these guidelines do not dictate a specific minimum distance. Proximity to the deck is a factor influencing the need for bracing, but it is not the sole determinant.

Proximity as a Factor

Conduit close to the deck is considered more rigidly supported and less susceptible to significant movement. However, even close to the deck, long spans or heavy loads can still create a situation requiring bracing.

Recommendation



Consult the design documents.
The closer to the deck and the shorter the run, the less the need for bracing.3. What is the minimum lbs per foot in which seismic bracing is not required?

General Guidance

ASCE 7-16 refers to a maximum weight of

20 lbs.
For individual components that are positively attached to the structure or suspended from a structural member. Practical Interpretation

If your equipment weighs less than 20 lbs, and is mounted rigidly, it may not require bracing.

Important Considerations for Healthcare Projects



Importance Factor (Ip)

Healthcare facilities typically have a high importance factor (Ip) of 1.5 due to their essential function in post-earthquake scenarios. This
increases the seismic design forces and generally requires more robust bracing.

OSHPD Review

Healthcare projects under OSHPD jurisdiction have rigorous plan review and inspection processes. Be prepared for scrutiny of your seismic bracing design. OSHPD also has the authority to enforce more stringent seismic requirements than ASCE 7-16.



Component Importance Factor (Ip)

Nonstructural components in healthcare facilities are sometimes considered Life Safety equipment and must remain operational following a seismic event. These components typically have a component Importance Factor of 1.5 as determined in ASCE 7-16 Table 13.
1.3. This would result in seismic bracing requirements for these components.


General Recommendations for Your Project


Consult with a Structural Engineer

This is the most crucial step. They can perform the necessary calculations, consider the specific site conditions, and provide a design that meets all code requirements and project needs.2.

Clarify OSHPD Requirements

Communicate directly with OSHPD to understand their specific expectations for seismic bracing on your project.3.

Develop a Bracing Schedule

Create a detailed bracing schedule showing the location, type, and spacing of all seismic bracing. This will help with installation and inspection.4.

Consider Pre-Approved Systems

Use pre-approved bracing systems (OSHPD OPA) whenever possible. This can streamline the review process.5.

Document Everything:
* Keep thorough records of all design calculations, product certifications, and inspection reports.Good luck with your project! Seismic bracing is a critical aspect of healthcare facility design, and taking the time to do it right will ensure the safety of the building and its occupants. Flag for review