Question: I live in a house that has a 200amp service coming off a pole to serve the primary home. There is a detached garage 10-12 feet away from the house, that has a separate 200amp service coming off a different pole. We are looking at having a breezeway built that would allow us to walk from the garage to our house, without getting hit with the weather elements. A friend of mine informed me that this could be a liability, as if I connect my garage to my house, it would be considered one structure, thus breaking NEC code for having two services at one residence.I am struggling to understand the reasoning behind this, and if there is any reasonable option for me to take. It seems I could build a breezeway between the two structures, but leave that breezeway disconnected from one of the sides by 6-12in, and technically I wouldn't be breaking any rules, but if I touch them together, I am then breaking the rules. What is crazy is that I would have never thought twice about this. Building a breezeway wouldn't require any permits where I am located, just simple carpentry would get it done.
You've hit on a common but often misunderstood area of the National Electrical Code (NEC) regarding multiple services for a single building. Let's break it down
The "One Building, One Service" Rule (Generally)
The NEC generally aims to limit a single building or structure to a single service. This is primarily for safety and simplification of the electrical system: Coordination
Having multiple services makes it harder to coordinate overcurrent protection (breakers and fuses). If something goes wrong, figuring out which service is feeding the problem becomes complex.
Grounding
Proper grounding is crucial for safety. Multiple services can lead to multiple ground points, creating potential differences and potentially dangerous circulating currents.
Fire Safety
Firefighters need to be able to quickly shut down power to a structure in case of a fire. Multiple services make this more difficult and potentially dangerous.
Accidental Backfeed
In the event of a power outage and generator being used, the potential of accidentally feeding the utility grid is higher.
The Breezeway Complication
Your friend is correct: connecting the house and garage with a breezeway can be interpreted as making them a single structure under the NEC, especially if it is a fully enclosed structure. This is where things get nuanced, as it's subject to the "Authority Having Jurisdiction" (AHJ), which is typically your local building inspector or electrical inspector.
Why 6-12 Inches Doesn't Solve the Problem
While you might think a small gap would keep them separate, the NEC focuses on the intent and functionality of the space. If the breezeway provides a continuous, weather-protected pathway, most inspectors will consider the structures functionally connected. The code is not usually interpreted as an exact measurement of space, but rather a design with functionality in mind.
Exceptions to the "One Building, One Service" Rule
The NEC does allow multiple services in certain situations, but these are specific and usually require the AHJ's approval: Large Square Footage
If the building is so large that a single service cannot adequately handle the load, multiple services might be permitted. This usually applies to commercial or industrial buildings.
Different Occupancies
If different parts of the building have significantly different uses (e.g., a house with a separate commercial business attached), separate services might be allowed.
Capacity Requirements
If the electrical usage is so large that the utility company is unable to provide all the power needed to the single service panel.
What You Should Do (In Order of Priority)1. Consult Your Local Electrical Inspector (AHJ)
This is the most important step. Tell them about your plans for the breezeway and the existing dual services. Ask them directly how they would interpret the situation and what options you have. Their interpretation is what matters. Do this before you start construction.2.
Consider a Subpanel
The most common and generally recommended solution is to feed the garage from a subpanel in your house.
Pros
Complies with the NEC, simplifies the electrical system, and reduces potential safety issues.
Cons
Requires running a larger feeder cable from the house to the garage, which can be costly. You'd also need to consider the load calculations to ensure your house service can handle the additional load.
Steps
Have an electrician calculate the electrical load requirements of the garage. Determine if your existing 200A house service has enough capacity to handle the additional load. If so, install a subpanel in the garage fed by a appropriately sized circuit breaker from your main house panel with correct size wiring buried between house and garage. Disconnect and remove one of the utility service lines so that the entire home and garage are only fed by one meter. Remove the original meter panel from the garage, but leave it in place.3.
Seek Professional Electrical Advice
Hire a licensed electrician who is familiar with local codes to evaluate your situation and provide recommendations. They can perform load calculations, assess the capacity of your existing service, and design a safe and compliant solution.4.
DOCUMENT everything
If you proceed with any work, keep detailed records of permits, inspections, electrical plans, and communications with the AHJ. This is essential for future reference and potential sale of the property.
Important Considerations
Cost
Rewiring or consolidating services can be expensive. Get multiple quotes from qualified electricians.
Property Value
Non-compliant electrical work can negatively affect the value of your property and create problems during a sale.
Safety
This is not a DIY project. Electrical work can be dangerous, and improper wiring can create fire hazards or electrocution risks.
Don't Try to Get Around the Rules:
While the 6-12 inch gap might seem like a clever workaround, it's unlikely to satisfy an inspector and could create more problems than it solves. It's best to be upfront and honest about your plans and work with the AHJ to find a safe and compliant solution.In summary, talk to your local electrical inspector. They will be the final say on what is acceptable in your area. A subpanel is likely the best long-term solution, but get a professional evaluation before making any decisions. Flag for review