Question: A 40 unit multi-family condo building is looking to increase elec. capacity.I'm not totally clear on what exactly they're looking to do but it sounded like the service to each dwelling unit has become undersized.They want to add larger loads within the units, they mentioned electric heat pumps etc.They also mentioned they want to add EV chargers, so I'll assume they want to also upsize their house panel as well.1) Assuming a whole new meter center, demo/replace with new feeds to each dwelling unit & house panel. That's a huge amount of work obviously.That kind of work cannot be done live and would need power shutoff to all building. Please give me a sanity check here to make sure I'm not overlooking anything.2) If it ends up being less intensive, for example assume the feed to each unit is adequate & main service is adequate but the meter/breaker to each unit at the meter center just needs to be upsized. Could this be done live?I ask because apparently they had some contractors tell them it can be done live & some tell them it can't be done live.They don't want the tenants to lose power during the upgrades.Thanks
Okay, this is a common scenario and a good question. You're right to be concerned about the logistics and potential for live work. Let's break it down
1. Sanity Check - Complete Service Upgrade (New Meter Center & Feeds)
You are absolutely correct. A full service upgrade involving replacing the meter center and individual unit feeds requires a complete power shutdown. There's no safe or practical way to do this energized. Here's why: Safety
Working on energized service equipment is extremely dangerous. You're dealing with high currents, potentially lethal voltages, and arc flash hazards. No reputable contractor should recommend doing this live.
Code Compliance
Most electrical codes (NEC in the US, similar codes in other regions) prohibit work on energized service equipment unless it's absolutely unavoidable for specific diagnostic or safety reasons. An upgrade like this doesn't qualify.
Practicality
Cutting and splicing service conductors, connecting to the main bus, and installing new metering equipment requires de-energized conditions. It's physically impossible to do it safely and effectively while live.
Potential Damage
Attempting to work live can lead to short circuits, equipment damage, fires, and injuries.
2. Meter/Breaker Upsizing Only (Assuming Adequate Feeds)
This is where things get trickier, and the conflicting advice comes in. Here's the breakdown: Potentially Possible... With Extreme Caution & Specific Circumstances, but HIGHLY DISCOURAGED. Even if the main service and feeders were adequate, working at the meter center poses very large risks that outweigh the benefits
Theoretical Scenario
If only the individual unit breakers within the existing meter center need to be upsized, and the main service capacity and individual unit feeder conductors are demonstrably adequate for the increased load (verified by load calculations), very limited live work might be considered.
However, this is still extremely risky and generally not recommended. It would involve carefully isolating and de-energizing one specific meter position while the rest of the meter center remains energized.
Key Requirements for Any Live Work (Even Limited)
Highly Qualified Personnel
Only specially trained and authorized electricians with extensive experience in working on energized equipment should even consider this.
Proper PPE (Personal Protective Equipment)
Full arc flash protection is mandatory, including suit, gloves, face shield, and hearing protection.
Detailed Work Plan & Risk Assessment
A comprehensive plan must be developed outlining the exact steps, potential hazards, and mitigation strategies.
Lockout/Tagout (LOTO) Procedures
Strict LOTO procedures must be followed to prevent accidental re-energization.
Emergency Procedures
Clear procedures for handling arc flash or other emergencies must be in place.
Permitting
Any live work likely requires special permits and approval from the local electrical inspector.
Why it's Still Discouraged
Arc Flash Risk
Working in close proximity to energized busbars and conductors significantly increases the risk of arc flash. Even with PPE, the consequences can be severe.
Human Error
A single mistake can have catastrophic consequences.
Difficult Working Conditions
Limited space and access within the meter center make it difficult to work safely and efficiently.
Potential for Damage
Accidental contact with energized components can damage equipment and cause outages.
Dealing with Tenant Power Outages: Mitigation StrategiesSince a complete power shutdown is likely unavoidable, here's how to minimize the impact on tenants:
Detailed Planning & Scheduling
Coordinate the work with the utility company and tenants to minimize the downtime.
Advance Notice
Provide tenants with ample notice of the planned outage, explaining the reasons and the estimated duration.
Phased Approach
If possible, break the project into smaller phases to minimize the number of tenants affected at any one time.
Temporary Power
Explore the possibility of providing temporary power to critical areas (e.g., refrigerators, medical equipment) using generators or portable power stations. This is expensive, but can be a huge benefit to the tenants.
Tenant Communication
Keep tenants informed of the progress of the work and any changes to the schedule.
Incentives
Consider offering tenants a small rent reduction or other incentive to compensate for the inconvenience.
Recommendations
Reject Live Work Proposals
Do not accept any proposals that involve working on energized service equipment without a full outage. It's unsafe and irresponsible.2.
Thorough Load Calculation
Conduct a detailed load calculation for each unit and the entire building to determine the actual electrical demand. This will inform the sizing of the new service equipment and feeders. Factor in the EV chargers.3.
Engage a Qualified Electrical Engineer
Hire a licensed electrical engineer to design the upgrade and ensure compliance with all applicable codes.4.
Get Multiple Bids
Obtain bids from multiple reputable electrical contractors with experience in multi-family service upgrades.5.
Prioritize Safety
Make safety the top priority throughout the project.
In summary, while theoretically limited live work might be possible in specific scenarios for upsizing individual unit breakers, it is highly risky, generally not recommended, and should only be considered with extreme caution and under very strict conditions. A full outage is the safest and most reliable approach for a comprehensive service upgrade. Good luck! Flag for review