Question: I am trying to understand bidding( upfront fixed price) and can't seem to wrap my head around what the goal is. If I have calculated my hourly rated based on expenses and profit then it seems like a bid would be my hourly rate + materials+markup. So it begs the question why not just work T&M and arrive at the same place?But I have read enough and actually done some fixed price work to know there is definitely a difference. I like not having to keep track of every hour, nut, and bolt after a fixed price bid has been agreed on. I also have made extra money this way by bidding higher than what T&M would be. But this leads to my main question, how much higher should the fixed price be than the projected T&M cost?If I have a project that I am estimating will be $10K if done T&M, how much do I say it will cost as a fixed price? Is the answer "as much as the market will allow"? Or is there some percentage that makes sense?I am in a market with low competition and plenty of higher dollar projects. I'd like to make the maximum profits but at some point it feels greedy to just add extra thousands of dollars to a bid(fixed price). Where is the sweet spot?In my case, I do 100% residential work. Thanks for the thoughts
You've hit on the core dilemma of fixed-price bidding: balancing profit, competitiveness, and customer perception. You're right, there's a significant difference between T&M and fixed-price, and you're experiencing the tension between wanting to maximize profit and fearing you'll price yourself out of the market. Let's break this down
Why Fixed Price Bidding (Isn't Just T&M)?
Risk Transfer
You're absorbing the risk of overruns, delays, or unexpected issues. This is a service you're providing to the client. They're paying for certainty.
Perceived Value
A fixed price provides the client with budget certainty. They know the total cost upfront, which is a huge selling point for many homeowners. This perceived value allows you to command a premium.
Efficiency Incentive
Fixed-price incentivizes you to be as efficient as possible. The faster and more efficiently you complete the project, the more profit you keep. This doesn't always exist with T&M (though ethical T&M should still strive for efficiency).
Simplicity for Clients
Many homeowners dislike the uncertainty of T&M, the tracking of hours, and the potential for cost creep. Fixed-price simplifies the transaction.
Higher Profit Potential
As you've observed, you can often bid higher than a projected T&M cost and still win the job.
How Much Higher Than Projected T&M Should a Fixed Price Be?
There's no magic percentage, and you're right, "as much as the market will allow" is part of the answer, but it needs nuance. Here's a framework:1. Calculate Your Base Cost (Projected T&M)
This is your starting point. Be meticulous here. Include: Labor (including benefits, payroll taxes, etc.) Materials (be realistic) Subcontractors (if any) Permits and Fees Equipment Rental (if applicable) Overhead (a percentage covering your office expenses, insurance, etc.)
Profit Margin (your desired profit on a basic project)
Let's say 10-15% on top of your base cost. This is your "bare bones" profit.2.
Add a Risk Buffer
This is where the art comes in. Consider these factors:
Project Complexity
Is it a straightforward kitchen remodel or a complex addition with unforeseen structural challenges? The more complex, the higher the risk buffer.
Age of the Home
Older homes often hide surprises (wiring issues, plumbing problems, asbestos, etc.). Add a larger buffer for older homes.
Client Personality
(This is critical!) Is the client detail-oriented, prone to change orders, or generally difficult to work with? Clients who are difficult will require additional time, patience, and communication, which all take billable time.
Weather
Will the project be affected by weather? Add a buffer for potential delays.
Availability of Materials
Are any materials difficult to obtain or subject to price fluctuations? Factor in potential delays and cost increases.
Your Experience
How confident are you in your estimate? If you're unsure about certain aspects, add a contingency.
Risk Buffer Percentages
This is where you start to experiment. Here are some guidelines:
Low-Risk (simple, straightforward)
5-10% on top of your base cost + profit.
Medium-Risk (some potential unknowns)
10-15% on top of your base cost + profit.
High-Risk (old homes, complex designs, difficult clients)
15-25%+ on top of your base cost + profit. Don't be afraid to walk away from extremely high-risk projects if the potential profit doesn't justify the stress.3.
Consider Your Market & Competition
Research
Get bids from competitors (or have friends/family get bids pretending to be clients). This gives you a sense of the market range.
Value Proposition
What makes you different? Do you offer superior customer service, higher-quality materials, or faster turnaround times? These justify a higher price.
Perceived Value
Are you working on a high-end home? The owners might be willing to pay a premium for peace of mind and quality workmanship.4.
Your "Walk-Away" Price
Know the absolute lowest price you're willing to accept before you present the bid. Stick to it. If the client balks, be prepared to walk away. This protects your profit and prevents you from resenting the project.5.
Presenting the Bid
Transparency (to a point)
Don't break down every line item, but be prepared to explain the scope of work and the value you're providing.
Confidence
Present your bid with confidence. You're an expert, and you're providing a valuable service.
Payment Schedule
A good payment schedule can help with cash flow and reduce your risk.
Example
Projected T&M Cost: $10,000 Desired Base Profit (15%): $1,500 Base Cost + Profit: $11,500 Risk Assessment: Medium-risk (some unknowns in the existing structure) - 12% Risk Buffer: $11,500 0.12 = $1,380 Fixed Price Bid: $11,500 + $1,380 = $12,880
Is It Greedy?
It's only greedy if you're providing subpar work or taking advantage of clients. If you're delivering excellent results, providing great customer service, and honoring your commitments, you deserve to be compensated fairly. Remember, you're running a business, not a charity.
The Sweet Spot
The "sweet spot" is where you're consistently winning projects while achieving your desired profit margins. It's a moving target that requires constant monitoring and adjustment. Track your bids, win rates, and actual project costs to refine your estimating process.
Key Takeaways: Fixed-price bidding is about more than just calculating costs. It's about managing risk, providing value, and commanding a premium for your expertise. Don't be afraid to price yourself higher than the competition if you offer a superior service. Continuously analyze your bidding process and adjust your risk buffers based on your experiences. Know your "walk-away" price and stick to it.* Focus on providing exceptional value and building a reputation for quality and reliability.Residential work adds a personal touch that can make or break a bid. Clients need to trust you with their home and their money. Making sure to build that trust and provide a clear project scope are important factors to consider.Good luck! Flag for review