Question: I have a customer with an old home, the current Federal Pacific meter/main panel has exterior plumbing running underneath and multiple conduits running up to the panel. Service is overhead.The current panel/meter location is not Green Book compliant. The only complaint location is 20 feet away.What I am considering is installing a meter base only at the Green Book compliant location which ideally would need to be installed as close to the edge of the building as possible. And installing a new main panel in the same location as the old panel.How close to edge of building a meter can be placed is one of my questions, Green Book shows clearances but I did not see a minimum from the edge of a building.

Okay, let's break down this situation with the Federal Pacific panel replacement, Green Book compliance, and the relocation considerations. This is a common scenario, and proper planning is crucial.

Understanding the Challenges Federal Pacific (FPE) Panel

These panels are known for potential safety hazards due to breaker malfunction issues. Replacing it is the correct course of action.


Green Book Compliance

Meeting your local utility's Green Book (or equivalent) requirements for meter placement is mandatory.

Obstacles

Existing plumbing and conduits present physical constraints.


Distance

20 feet between the old and ideal location adds complexity.

Proposed Solution Breakdown


Your plan of installing a remote meter base at the Green Book compliant location and then a new main panel at the old location is a common and valid approach. Here's a detailed look:1. Meter Base Relocation (Green Book Location)



Edge of Building Question

You're right; the Green Book primarily focuses on clearances
around the meter (working space, height, obstructions, etc.) and not specifically a minimum distance from the building's edge.

The most reliable answer on this comes directly from your local utility company.
Call them and specifically ask what their policy is for meter placement at or near the edge of a building. Factors they consider might include: Accessibility for meter readers

They need to be able to safely and easily read the meter.

Maintenance access

They need to be able to access the meter for maintenance or replacement.


Physical protection

Is the location prone to damage from vehicles, landscaping, or other sources?

Local Ordinances

There might be local zoning or building codes that influence placement.


Mounting

Ensure the meter base is securely mounted to the building and properly grounded according to code. Use a weather-tight enclosure and fittings.2.

New Main Panel at Old Location



Size and Capacity

Determine the appropriate size (Amperage) and number of circuits needed for the new panel. Plan for future expansion.


Physical Constraints

Carefully assess the existing plumbing and conduits. Can you work around them without disturbing them? Will you need to relocate or reroute any of them?

If plumbing is involved, you'll need a licensed plumber.
Wiring



Service Entrance Conductors (SECs)

These are the conductors running from the new meter base to the new main panel. This is where you'll likely need to run new conduit, either above ground or underground (depending on aesthetics, local code, and feasibility).

Sizing the SECs

These conductors must be sized appropriately for the service amperage (e.g., 200A service requires appropriately sized conductors). Consult the NEC and local amendments for proper sizing based on the ampacity and conductor type.


Overcurrent Protection

The main breaker in the new main panel provides overcurrent protection for the entire service.

Grounding and Bonding

Proper grounding and bonding are critical for safety. Follow NEC requirements (Article 250) meticulously. This includes grounding electrode conductor(s) to a grounding electrode system (e.g., ground rod, water pipe).


Load Calculation

Perform a load calculation to ensure the new panel and service size are adequate for the existing and anticipated load.

Disconnect

The main panel needs to be a service disconnect, easily accessible to the homeowner and clearly labeled.

Important Considerations & Steps
1. Utility Company Consultation (Crucial)

This is the
most important step.

Contact them first.
Explain your situation and proposed solution. Get their specific requirements for meter base location, including proximity to the building edge, acceptable mounting methods, conduit requirements, inspection procedures, etc. They may have specific approved meter base models you must use. They may require you to submit a plan for approval before starting any work. Involve them early in the process to avoid costly mistakes and delays.2. Permits

Obtain all necessary electrical permits from your local building department before starting any work.3.

Professional Expertise



Licensed Electrician

This work
must be performed by a qualified and licensed electrician. Service entrance work is dangerous and requires specialized knowledge of codes and safety practices.

Plumber (if needed)

If you need to relocate any plumbing, hire a licensed plumber.4.

NEC Compliance

Ensure that all work complies with the latest edition of the National Electrical Code (NEC) and any local amendments.5.

Coordination

Coordinate closely with the utility company and the electrician throughout the project.6.

Inspection

Schedule inspections with both the utility company and the local building department at the appropriate stages of the project.

Key Considerations for the Remote Meter/Main Panel Setup
Voltage Drop

Over a 20-foot run, voltage drop
could become a concern, especially under heavy load. Your electrician should calculate the voltage drop to ensure it remains within acceptable limits (typically 3% maximum). If it's close, using larger gauge conductors for the service entrance conductors will mitigate voltage drop.

Accessibility

Ensure the meter is accessible to the utility company for reading and maintenance. The panel needs to be accessible for maintenance and repair.

Aesthetics

While safety and compliance are paramount, consider the aesthetics of the installation. Try to minimize the visual impact of the conduit run.

In summary:
Talk to your utility company first* to get their specific requirements. Then, hire a licensed and experienced electrician to perform the work according to code, ensuring safety and compliance. Don't cut corners on service entrance work. Flag for review