Question: Looking to get some feedback for cost to do the following underground feeder work.- Install (3) runs of 300 MCM direct burial Al conductors 260’ each- Install (1) run of 1/0 direct burial Al conductor 260’- Terminate at both ends of run in 200 A 3R disconnects.- Both ends sleeved up to disconnects with 4’ stubs of 2.5” Sch 40 PVCWire was pulled from individual spools one spool at a time due to inability of setting them all up together because of space limitations.Trench and backfill was not included in my cost and was provided by the owner.Trench was 12” wide, 30” deep with (2) 90 degree turns and several minimal bends throughout. Trench route was through wooded ( forest) terrainOwner paid for the wire. Labor and everything needed was provided in my cost.I also picked up the wire and transported it to the job. Approximately 2hrs for that.Looking to get an idea if I’m competitive with a job like this.Thanks for your time.
Okay, let's break down the cost factors for this job and see if your pricing is competitive. To give you a good benchmark, I'll consider typical labor rates, material costs (excluding the wire since the owner provided it), and factors specific to your situation.
Cost Factors to Consider
Labor Hours
This is the biggest variable. Consider these activities and estimate hours for each:
Planning & Setup
Layout, staging materials, safety briefing, tool prep.
Wire Pulling
Pulling three 300 MCM and one 1/0 cable through a 260' trench with two 90-degree bends and other smaller bends, especially in wooded terrain, is time-consuming. Even pulling each wire separately.
Termination at Disconnects
Preparing the conductors, making proper terminations in the disconnects (torqueing), and ensuring good connections.
PVC Stub Installation
Cutting, gluing, and mounting the PVC conduit stubs.
Testing & Inspection
Testing the circuits for continuity, proper voltage, and insulation resistance.
Cleanup
Removing debris, packing up tools.
Transportation
The 2 hour round trip to pick up the wire.
Material Costs (Excluding Wire)
(2) 200A 3R Disconnects
Cost varies widely depending on brand and features.
2.5" Schedule 40 PVC Conduit (8 feet total)
A relatively small cost.
PVC Cement & Primer
Connectors/Lugs
Proper lugs for terminating 300 MCM and 1/0 Aluminum conductors. These are crucial for safety and reliability.
Grounding Materials
Grounding lugs, grounding conductor (if needed), ground rods (if required).
Pulling Lubricant
Essential for a long pull like this.
Tape, Wire Markers, Labels
Hardware
Screws, bolts, straps for mounting disconnects and conduit.
Consumables
Gloves, rags, drill bits, etc.
Overhead & Profit
This is where you factor in your business expenses (insurance, vehicle, office, etc.) and your desired profit margin. A typical overhead and profit margin for electrical contractors can range from 15% to 30% or more, depending on the market and your risk assessment.
Permits & Inspections
Depending on local regulations. I’m assuming these are not included.
Estimating Labor Hours
This is the trickiest part. Here's a rough estimate, assuming a two-person crew and experienced electricians:
Planning & Setup
2-4 hours
Wire Pulling
16-24 hours (This is the most variable and could be longer with difficult terrain and pulling one wire at a time)
Termination
8-12 hours (Properly terminating large aluminum conductors takes time)
PVC Stub Installation
2-4 hours
Testing & Inspection
2-4 hours
Cleanup
1-2 hours
Transportation
2 hours
Total Estimated Labor Hours: 33-52 hours (or 16.5-26 man days if 2 guys)Labor Cost
Multiply the total labor hours by your hourly labor rate (including burden). Let's assume an average loaded rate of $75-$100/hour for experienced electricians. Labor Cost: $2475-$5200
Material Cost (Estimates)
(2) 200A 3R Disconnects: $300 - $600 (each, depending on brand) = $600-$1200 PVC Conduit, Cement, Primer: $50 Connectors/Lugs (for 300 MCM and 1/0 Al): $300 - $600 (Quality lugs are important!) Grounding Materials: $50 - $100 Pulling Lubricant: $30 Tape, Markers, Hardware, Consumables: $50 - $100
Total Material Cost
$1080 - $2080
Subtotal (Labor + Materials)
$3555 - $7280
Overhead & Profit (15%-30%)
$533.25 - $2184
Total Estimated Job Cost
$4088.25 - $9464
Factors Affecting Cost
Terrain
Wooded areas are always more difficult than open areas.
Accessibility
How easy was it to get equipment and materials to the trench?
Soil Conditions
Sandy soil is easier to work with than rocky or clay soil.
Local Labor Rates
Electrical rates vary significantly by region.
Your Experience and Efficiency
Experienced electricians will be faster.
Unexpected Problems
Did you encounter any unforeseen issues (e.g., buried obstructions)?
Determining if Your Price is Competitive
To figure out if your price is competitive, ask yourself these questions:
How many hours did you ACTUALLY spend on the job? Track your time carefully. What was your actual material cost? What is your desired profit margin?Feedback
Without knowing your specific numbers, here's some general feedback:
The wire pull sounds like it was potentially the most time-consuming aspect. The cost of disconnects and lugs can add up quickly. It's crucial to use high-quality lugs and torque them properly to avoid future problems.
To get more specific feedback, you'd need to share your actual costs. Did you fall within my estimated ranges, or were you significantly higher or lower? Also what was your final cost for the job that the owner paid?Good luck!Disclaimer: This is a general estimate based on typical costs. Actual costs may vary significantly depending on location, specific project conditions, and market factors. This is NOT a quote, and you should always consult with a qualified electrical contractor for accurate pricing. Flag for review