Question: Looking to get some feedback for cost to do the following underground feeder work.- Install (3) runs of 300 MCM direct burial Al conductors 260’ each- Install (1) run of 1/0 direct burial Al conductor 260’- Terminate at both ends of run in 200 A 3R disconnects.- Both ends sleeved up to disconnects with 4’ stubs of 2.5” Sch 40 PVCWire was pulled from individual spools one spool at a time due to inability of setting them all up together because of space limitations.Trench and backfill was not included in my cost and was provided by the owner.Trench was 12” wide, 30” deep with (2) 90 degree turns and several minimal bends throughout. Trench route was through wooded ( forest) terrainOwner paid for the wire. Labor and everything needed was provided in my cost.I also picked up the wire and transported it to the job. Approximately 2hrs for that.Looking to get an idea if I’m competitive with a job like this.Thanks for your time.

Okay, let's break down the cost factors for this job and see if your pricing is competitive. To give you a good benchmark, I'll consider typical labor rates, material costs (excluding the wire since the owner provided it), and factors specific to your situation.

Cost Factors to Consider



Labor Hours

This is the biggest variable. Consider these activities and estimate hours for each:


Planning & Setup

Layout, staging materials, safety briefing, tool prep.

Wire Pulling

Pulling three 300 MCM and one 1/0 cable through a 260' trench with two 90-degree bends and other smaller bends, especially in wooded terrain, is time-consuming. Even pulling each wire separately.


Termination at Disconnects

Preparing the conductors, making proper terminations in the disconnects (torqueing), and ensuring good connections.

PVC Stub Installation

Cutting, gluing, and mounting the PVC conduit stubs.


Testing & Inspection

Testing the circuits for continuity, proper voltage, and insulation resistance.

Cleanup

Removing debris, packing up tools.


Transportation

The 2 hour round trip to pick up the wire.

Material Costs (Excluding Wire)



(2) 200A 3R Disconnects

Cost varies widely depending on brand and features.

2.5" Schedule 40 PVC Conduit (8 feet total)

A relatively small cost.


PVC Cement & Primer



Connectors/Lugs

Proper lugs for terminating 300 MCM and 1/0 Aluminum conductors. These are crucial for safety and reliability.


Grounding Materials

Grounding lugs, grounding conductor (if needed), ground rods (if required).

Pulling Lubricant

Essential for a long pull like this.


Tape, Wire Markers, Labels



Hardware

Screws, bolts, straps for mounting disconnects and conduit.


Consumables

Gloves, rags, drill bits, etc.

Overhead & Profit

This is where you factor in your business expenses (insurance, vehicle, office, etc.) and your desired profit margin. A typical overhead and profit margin for electrical contractors can range from 15% to 30% or more, depending on the market and your risk assessment.


Permits & Inspections

Depending on local regulations. I’m assuming these are not included.

Estimating Labor Hours

This is the trickiest part. Here's a rough estimate, assuming a two-person crew and experienced electricians:

Planning & Setup

2-4 hours


Wire Pulling

16-24 hours (This is the most variable and could be longer with difficult terrain and pulling one wire at a time)

Termination

8-12 hours (Properly terminating large aluminum conductors takes time)


PVC Stub Installation

2-4 hours

Testing & Inspection

2-4 hours


Cleanup

1-2 hours

Transportation

2 hours

Total Estimated Labor Hours: 33-52 hours
(or 16.5-26 man days if 2 guys)Labor Cost

Multiply the total labor hours by your hourly labor rate (including burden). Let's assume an average loaded rate of $75-$100/hour for experienced electricians. Labor Cost: $2475-$5200

Material Cost (Estimates)

(2) 200A 3R Disconnects: $300 - $600 (each, depending on brand) = $600-$1200 PVC Conduit, Cement, Primer: $50 Connectors/Lugs (for 300 MCM and 1/0 Al): $300 - $600 (Quality lugs are important!) Grounding Materials: $50 - $100 Pulling Lubricant: $30 Tape, Markers, Hardware, Consumables: $50 - $100

Total Material Cost

$1080 - $2080

Subtotal (Labor + Materials)

$3555 - $7280

Overhead & Profit (15%-30%)

$533.25 - $2184

Total Estimated Job Cost

$4088.25 - $9464

Factors Affecting Cost



Terrain

Wooded areas are always more difficult than open areas.


Accessibility

How easy was it to get equipment and materials to the trench?

Soil Conditions

Sandy soil is easier to work with than rocky or clay soil.


Local Labor Rates

Electrical rates vary significantly by region.

Your Experience and Efficiency

Experienced electricians will be faster.


Unexpected Problems

Did you encounter any unforeseen issues (e.g., buried obstructions)?

Determining if Your Price is Competitive

To figure out if your price is competitive, ask yourself these questions:

How many hours did you ACTUALLY spend on the job?
Track your time carefully. What was your actual material cost? What is your desired profit margin?Feedback

Without knowing your specific numbers, here's some general feedback:


The wire pull sounds like it was potentially the most time-consuming aspect.
The cost of disconnects and lugs can add up quickly. It's crucial to use high-quality lugs and torque them properly to avoid future problems.

To get more specific feedback, you'd need to share your actual costs. Did you fall within my estimated ranges, or were you significantly higher or lower? Also what was your final cost for the job that the owner paid?Good luck!Disclaimer: This is a general estimate based on typical costs. Actual costs may vary significantly depending on location, specific project conditions, and market factors. This is NOT a quote, and you should always consult with a qualified electrical contractor for accurate pricing. Flag for review