Question: So as many of you know we have a very large 4" conduit job( about 40,000'). The company have never really used cost codes before. I streesed the importance of them for tracking and future estimating purposes. Well, we setup all the cost codes( not mnay at all) and the owner/PM says he really doesn't have time to use utlize them even if the foreman is calling in time under the correct code. He seems like it's not important to know this information. I think it's critical. I keep asking what our production rate is for installing the conduit and he says he doesn't know. Very discouraging!!!!
You're right to be discouraged. What you're experiencing is a classic problem in construction: leadership not understanding the value of data and proper cost accounting. You've identified a critical need, and the PM is dismissing it. Here's a breakdown of the issues and what you can do
Why You're Right (and Why Cost Codes are Essential):
Accurate Job Costing
Cost codes are the foundation of knowing where money is being spent on the project. Without them, you're flying blind. You won't know if you're over or under budget on specific tasks.
Productivity Tracking
You're absolutely right that tracking production rates is crucial. Cost codes, combined with hours worked, allow you to calculate productivity (e.g., feet of conduit installed per hour). This information is vital for:
Identifying inefficiencies
Are certain crews slower? Are certain methods less effective?
Making mid-course corrections
If you see production lagging, you can investigate the cause and implement solutions (e.g., more manpower, different tools, improved training).
Managing change orders
If a change order requires extra conduit installation, you can accurately estimate the cost and justify the price.
Estimating Future Jobs
The most important reason. Historical data on production rates and costs is the bedrock of accurate bidding. Without it, you're guessing. You'll either underbid and lose money or overbid and lose work.
Profitability Analysis
Cost codes allow you to analyze the profitability of individual tasks. This helps you understand which aspects of your business are most profitable and where you need to improve.
Data-Driven Decision Making
Instead of relying on gut feelings, you can make informed decisions based on facts.
Identifying Areas for Improvement
Maybe you're using a specific brand of conduit that consistently takes longer to install than another. Maybe a specific installation method is less efficient. Without data, you're unlikely to identify these opportunities.
Why Your PM/Owner Might Be Hesitant (and How to Address It)
Perceived Extra Work
They may see cost coding as adding more paperwork and administrative burden, especially if they're not used to it.
Lack of Understanding of the Benefits
They may not fully grasp the long-term benefits of accurate cost tracking. They might be focused solely on the immediate task of getting the job done.
Fear of Revealing Inefficiencies
They might be worried that accurate cost tracking will reveal problems within the company.
Bad Past Experiences
Perhaps they had a poorly implemented cost coding system in the past that was more trouble than it was worth.
Resistance to Change
People naturally resist change, especially if they're already busy.
Lack of Tools/Training
They may not have the systems in place to easily collect and analyze cost code data.
What You Can Do (A Multi-Pronged Approach)
Re-Emphasize the Benefits (in Terms They Understand)
Focus on profitability
"Using cost codes will help us accurately track our costs, so we can be sure we're making a profit on this job. It will also help us bid future projects more competitively and profitably."
Highlight ease of use (if possible)
"With the cost codes we've set up, it's just a matter of the foreman selecting the appropriate code when reporting their time. It won't add significant time to their day."
Stress future bidding accuracy
"Having this data will allow us to bid similar conduit jobs much more accurately in the future, potentially winning us more work."
Focus on early detection
"By tracking costs in real-time, we'll be able to identify potential overruns early on, giving us time to address them before they impact the project's bottom line."
Use examples
If you have any past examples (even from other companies) of how cost coding saved money or improved bidding accuracy, share them.2.
Simplify the Process
Ensure cost codes are easily accessible and understandable. Keep the list short and clear. Make reporting as easy as possible. Can foremen use a mobile app to enter their time with cost codes? Can you use a simple spreadsheet? The easier it is, the more likely they are to do it. Provide training. Ensure the foreman understand the codes and reporting procedures. Offer assistance. Be available to answer questions and help with data entry.3. Start Small and Prove the Value
Pilot program
Instead of trying to implement cost codes on the entire project, suggest starting with a smaller section. This allows you to demonstrate the value of cost coding with minimal disruption.
Focus on key metrics
Identify the 2-3 most critical metrics you want to track (e.g., feet of conduit per labor hour, material costs per foot) and focus your initial efforts on collecting data for those metrics.
Present the results. Once you have some data, present it to the PM/owner in a clear and concise format. Show them how the data can be used to improve decision-making.4. Find an Ally
Is there anyone else in the company who understands the importance of cost coding? Try to get them on your side and build a coalition. If the PM/owner trusts a particular foreman or superintendent, try to convince that person of the value of cost coding and have them advocate for it.5.
Document Everything
Keep a record of your efforts to implement cost coding, including the benefits you explained and the challenges you encountered. This documentation could be helpful if the project goes over budget or if bidding accuracy becomes a problem in the future.6.
Consider a Compromise
If the PM/owner is completely unwilling to use cost codes, suggest tracking production rates in some other way, even if it's less formal. For example, you could ask the foreman to track the number of feet of conduit installed each day. Even a little bit of data is better than none.7.
Use the Data Yourself Start your own spreadsheet. Even if the PM/Owner doesn't care, YOU can start tracking the data. Talk to the foreman, and get the data you need. When bidding a job in the future, you will be ready. This will also help you get a new job somewhere else where they value this information!Important Considerations
Be respectful. Don't be confrontational or accusatory. Frame your arguments in terms of helping the company succeed. Be patient. It may take time to convince the PM/owner of the value of cost coding. Know when to let it go. If you've exhausted all your options and the PM/owner is still unwilling to use cost codes, you may need to accept that you've done what you can. However, continue to advocate for cost coding whenever possible.
Legal/Ethical Note: You have a professional responsibility to advocate for best practices. However, be careful not to cross the line into insubordination. If your efforts are consistently ignored or dismissed, you may need to consider whether this is the right company for you.This is a common challenge, but it's worth fighting for. Good luck! Flag for review