User: pgrovetom1, Location: Sonoma California
Asked on: Saturday, September 14, 2024 at 11:12 pm EDT
Answered on: Thursday, March 6, 2025 at 2:27 am EST
Question: When neither a ground mount solar string array and the inverters are located within 50 ft of a building ( both outdoors), are panel rapid shutdown devices required in California. The solar array is mounted on a gentle hillside on a steel frame with 18" underground conduits carrying the DC string pairs to the Inverter. The Inverter has a built in and labeled DC disconnect. The inverters are mounted on a pressure treated wood post structure similar to the utility post intended to provide some sun/weather protection and a place to physically mount the inverters and there are 3 Tesla Powerwall2's mounted on a concrete pad. The PG&E utility power arrives underground to a 4x6" pole mounted 400A panel which acts as the place where the inverter/battery system meets the AC wires that go to the home via underground approximately 50 ft conduits that have multiple sub-panels inside the home. The AC power from the inverter/Powerwall2 battery system are carried via a trough system to the utility 4x6" post. The utility comes up the 4x6" post up from underground. The AC for the home goes via conduits down the 4x6" post and underground to the home. So neither the inverters nor the ground mount solar arrays DC penetrates the home in any way. It does not come within 50 feet of the home. Only the AC from the utility or inverters penetrate the home via conduits as it was before the solar was installed. The NEC language suggests this situation does not require a rapid shutdown function for the solar arrays.This system was permitted and built in 2019. The reason I am asking is I'm thinking of adding an additional ground mount array and another inverter. If I do this will it now require the array rapid shut down function given there has been 2 NEC updates since 2019 with slightly different language. thanks
You're right to be cautious and re-evaluate based on NEC updates. Here's a breakdown of the rapid shutdown requirements, how they've changed, and how they likely apply to your situation, focusing on the most relevant parts of the NEC and California's specific amendments
Key NEC Concepts for Rapid Shutdown
Rapid Shutdown Initiating Device
A switch or other device (often integrated into inverters) that initiates the rapid shutdown sequence.
Controlled Conductors
Conductors that need to be brought to safe voltage levels during rapid shutdown (usually DC conductors from the PV array).
Rapid Shutdown Outside the Array Boundary
The NEC defines how far conductors can extend outside the array boundary before needing to be controlled by rapid shutdown. This distance has varied in past code cycles.
Relevant NEC Code Changes (and California Amendments) NEC 2017
Defined rapid shutdown requirements in Section 690.12. Established a 1-foot boundary inside the array and an 10-foot boundary outside the array where conductors must be brought to no more than 30 volts within 30 seconds of rapid shutdown initiation.
NEC 2020
Significant Change
Removed the "inside/outside array" concept and created a uniform boundary. Now, conductors more than 1 foot from the array boundary must be brought down to 30 volts within 30 seconds. This significantly expanded the area requiring rapid shutdown. The rapid shutdown equipment must be listed.
NEC 2023
While the core principle remains the same (1-foot boundary), the language is clarified, and some exceptions are better defined. There are increased requirements for documentation and labeling.
California's Amendments (Important!) California adopts the NEC with amendments. These amendments can be stricter than the base NEC. You MUST check the California Electrical Code (CEC) for the specific code cycle you are operating under. Typically, California aligns with the NEC, but it's crucial to confirm. The California Building Standards Commission publishes these amendments.
Analysis of Your Situation and How the Code Updates Impact You1. Grandfathering
The crucial question is whether your original 2019 installation is "grandfathered" under the 2017 NEC (or the California version of it at the time). Generally, if your system was permitted and inspected under a previous code cycle, you don't have to retrofit it to meet the latest code when adding to it. However, the AHJ (Authority Having Jurisdiction - your local building department) has the final say. They could require you to upgrade the entire system to meet the current code, especially if the addition is significant. This is very location-dependent, and you must confirm with your AHJ.2.
If Not Grandfathered (or if AHJ Requires Updates)
The newer NEC versions (2020 and 2023) would likely require rapid shutdown for your new array. Here's why:
1-Foot Boundary Rule
Since your inverter is located away from the array, the DC conductors from the array extend far beyond the 1-foot boundary.
Voltage Reduction
Those extended DC conductors must be brought down to 30V or less within 30 seconds of rapid shutdown initiation.
How to Achieve Compliance
This typically means using:
Module-Level Rapid Shutdown Devices (MLRD)
These devices (like Tigo TS4-A-F, SolarEdge optimizers, Enphase microinverters) are attached to each panel or pair of panels. They shut down the voltage at the panel level when the rapid shutdown is activated.
String Inverter with Built-in Rapid Shutdown
Some newer string inverters have built-in rapid shutdown capabilities, but they still usually require compatible MLRDs at the panel level.
Specific Points to Consider Distance from Buildings is No Longer the Only Factor
The NEC used to consider proximity to buildings as a primary factor. Now, the 1-foot boundary from the array is the main trigger for rapid shutdown requirements.
The Inverter's DC Disconnect is NOT Enough
A DC disconnect is required, but it doesn't fulfill the rapid shutdown requirements. Rapid shutdown needs to reduce the voltage in the conductors outside the array boundary, not just disconnect the inverter.
Tesla Powerwall
The Powerwall's presence doesn't directly affect the rapid shutdown requirements for the solar array. The rapid shutdown rules focus on the DC conductors coming from the panels.
Conduit
Enclosing conductors in conduit does not eliminate the rapid shutdown requirement.
Recommendations1. Contact Your AHJ (Building Department)
This is the most important step. Explain your existing system and your plans for expansion. Ask them: Is the existing system grandfathered under the code in effect at the time of installation? Will the addition of a new array trigger a requirement to upgrade the entire system to the current code? What specific version of the California Electrical Code (CEC) are they enforcing? Are there any local amendments to the CEC that affect rapid shutdown requirements?2.
Consult with a Qualified Solar Installer/Electrician
Get a professional who is familiar with the current NEC and CEC requirements in your area to assess your system and provide a code-compliant solution for the new array. They can help you choose the right rapid shutdown devices and integrate them with your existing system.3.
Review the Current California Electrical Code (CEC)
Download the latest CEC document from the California Building Standards Commission website and carefully read Section 690.12 (Rapid Shutdown of PV Systems) and any related amendments.
4.
Documentation
Make sure you keep meticulous records of all equipment, permits, inspections, and communication with the AHJ.
In summary, while your 2019 installation might be grandfathered, adding a new array will likely trigger the updated rapid shutdown requirements. The safest course of action is to consult with your local AHJ and a qualified solar installer/electrician to ensure your system is code-compliant. Flag for review