Topic: Calculations load help please. New to this.

User: sparkygbninja, Location: Ca

Asked on: Wednesday, November 6, 2024 at 2:02 pm EST
Answered on: Thursday, March 6, 2025 at 4:54 am EST

Question: Hello, hopefully I can make sense. I'm doing an ev charger level 2 install for a client. I. Asking for help on the calculation loads fill out sheet.Do I need to see every spec of every appliance or a/c, etc?Do I need to get the amps from what each breaker is pulling while on?Or do I just go in the nec code book to the load calculations and do it from there?Do I need to go back to the house for anything besides install?Any info helps please. I'm new to this part, if i keep asking the city guy helping but he's not specific on anything and it's confusing.He said the planner wants me to add the amps to the breakers. Don't know if that's separate or use it as a help for the load calculations.

Okay, I understand you're feeling lost with the load calculation process for an EV charger install. It's a common hurdle, especially when starting out. Let's break it down step-by-step and clarify what the city planner might be asking for.

Understanding Load Calculations - The Big Picture

The purpose of a load calculation is to determine if the existing electrical service (the main panel and the incoming wires from the utility) can safely handle the additional load of the EV charger. You're essentially asking: "Can this house safely power everything it already does plus charge this car?"Key Concepts & NEC References Article 220 of the NEC

This is your Bible for load calculations. Familiarize yourself with it.


Demand Factors

These are multipliers the NEC allows you to use because not everything in a house runs at its maximum rated current simultaneously. It acknowledges that a fridge only cycles on periodically, for example.

Continuous Load

An EV charger is considered a continuous load because it is expected to operate at its maximum current for 3 hours or more. Continuous loads must be calculated at 125% of their rating.


Calculated Load vs. Connected Load

The connected load is the sum of all the loads that could possibly be on at the same time. The calculated load is a more realistic estimation, taking into account demand factors and continuous load requirements.

Your Process - Step-by-Step
1. Existing Load Calculation (NEC Article 220) General Lighting

Use the square footage of the dwelling (finished living space only). NEC Table 220.12 provides volt-ampere (VA) requirements per square foot. Multiply the square footage by the VA/sq ft to get the general lighting load.


Small Appliance Branch Circuits

Each dwelling is required to have at least two 20-amp small appliance branch circuits (for kitchen/dining areas). NEC 220.14(H)(1) assigns 1500 VA for each of these circuits (even if they aren't fully loaded).

Laundry Circuit

Each dwelling is required to have at least one 20-amp laundry circuit. NEC 220.14(H)(2) assigns 1500 VA for this circuit.


Appliances

This is where it gets more detailed. Here's what you need:

Fixed Appliances (Ranges, Water Heaters, Dryers, Central A/C, Heat Pumps, etc.)

Look for the
nameplate rating on the appliance itself. This will give you the voltage, amperage, and/or wattage. Use this information for your calculations. NEC Table 220.55, Note 4 provides demand factors for ranges and cooking appliances.

Dishwashers, Disposals, Microwaves, etc.

Again, look for the nameplate rating on the appliance. Generally, these are considered non-coincidental loads (they're unlikely to all be on at the same time) so you include the largest of these, not all of them.

Heating & Air Conditioning



Central A/C or Heat Pump

Use the nameplate rating for the condensing unit. This will typically have a "Minimum Circuit Ampacity" (MCA) value. Use that MCA value in your load calculation. The nameplate should also show the RLA (Rated Load Amps) of the compressor and the FLA (Full Load Amps) of the fan motor.

Electric Heat

Electric heat is calculated at 100% of its connected load.


Multiple A/C or Heating Units

For dwelling units, you generally only need to include the largest of the A/C loads or the largest of the heating loads (you don't add them together). Unless there's a very specific heating/cooling system design.

Other Loads

Any other fixed-in-place loads like permanently installed hot tubs, spas, or other significant power consumers.


Demand Factors

After you've calculated the initial loads, you can apply demand factors as permitted by the NEC. For example, for dwelling units, you can typically apply a demand factor to the general lighting, small appliance, and laundry loads.2.

New EV Charger Load Calculation (NEC Article 625 and 220)
Charger Rating

You
must know the maximum output current of the EV charger you're installing. This is usually specified in amps.

Continuous Load

Multiply the charger's current by 1.25 (125%) because it's a continuous load. This is the amount of additional load you need to add to the existing load calculation. This is very important.3.

Total Calculated Load
Add the existing calculated load (from Step 1) to the new EV charger load (from Step 2).4. Service Capacity Determine the ampacity of the service entrance conductors (the wires coming into the main panel from the utility). This is usually printed on the main breaker. For example, 200A.5. Compare and Analyze Compare the total calculated load (Step 3) to the service capacity (Step 4). If the total calculated load is less than the service capacity, the existing service is adequate. If the total calculated load is greater than the service capacity, the service is not adequate, and you'll need to upgrade the service or use a load management system for the EV charger.

Answering Your Specific Questions
"Do I need to see every spec of every appliance or a/c, etc?" Yes, you absolutely need the nameplate ratings of the major appliances (range, water heater, dryer, A/C, electric heat). These loads are significant and must be accounted for accurately. For smaller appliances, a good-faith effort to estimate based on typical usage is often sufficient. "Do I need to get the amps from what each breaker is pulling while on?" No, you should not use a clamp meter to measure current while things are running for a standard load calculation. The NEC calculation method is based on nameplate ratings and demand factors, not on momentary real-time usage. Measuring real-time current draw only tells you what's happening at that specific moment and doesn't account for potential maximum load scenarios. "Or do I just go in the NEC code book to the load calculations and do it from there?" Yes, you go to the NEC and follow the methods in Article 220. That's the authoritative source for load calculations. "Do I need to go back to the house for anything besides install?" Yes, you definitely need to go back to gather the nameplate information from the appliances. You cannot accurately perform a load calculation without that information. "He said the planner wants me to add the amps to the breakers. Don't know if that's separate or use it as a help for the load calculations." This is where it gets tricky. What the planner might be asking for is a breaker schedule along with the load calculation. A breaker schedule is a list of all the breakers in the panel, their amp ratings, and a brief description of what they serve (e.g., "Kitchen Receptacles," "A/C Compressor"). The planner wants to get a handle on how the panel is utilized. The breaker schedule is NOT the same thing as the load calculation. You create the load calculation using the nameplate ratings of the appliances, not by adding up the breaker ampacities. If the planner is inexperienced, he may not realize that the breaker schedule's amp ratings rarely match the load calculations, and there can be multiple things on a single circuit. In short: Create a separate breaker schedule and make it as clear as possible.Important Considerations



Safety First

If you're not completely comfortable with load calculations, seek help from a more experienced electrician. An inaccurate load calculation can lead to overloaded circuits, overheating, and potentially fires.

Local Amendments

Be aware that your local jurisdiction may have amendments to the NEC that affect load calculation requirements. Check with your city or county's building department.


Documentation

Keep detailed records of your load calculation, including all the data you used, your calculations, and any assumptions you made. This is essential for demonstrating compliance and for future reference.*

Load Management

If the load calculation shows that the service is borderline, consider recommending a load management system to the client. These systems can automatically reduce the EV charger's current when other large loads are active, preventing overloads.

In summary


Visit the house again.
Get those appliance nameplate ratings.2. Create the load calculation. Follow NEC Article 220 meticulously.3. Create a breaker schedule. List each breaker, its amp rating, and what it serves.4. Submit both documents. Be prepared to explain your calculations to the city planner.Good luck, and don't hesitate to ask more questions as you go! Flag for review