Topic: PM Inquiry

User: Alwayslearningelec, Location: NJ

Asked on: Tuesday, November 19, 2024 at 2:19 pm EST
Answered on: Thursday, March 6, 2025 at 5:25 am EST

Question: Looking for some feedback as to questions you( if you were an owner or in charge of PM running project) would ask about ongoing projects during a meeting with your project manager? These are bi-weekly meetings to evaluate how a job(s) is doing. Thanks.

Okay, if I were an owner or in charge of PM running projects, here are the types of questions I'd ask during a bi-weekly project review meeting with a Project Manager, categorized for clarity

I. Overall Project Health & Status:
"What's the overall health of the project right now (Green, Yellow, Red), and why?" (This is the starting point, a quick snapshot.) "In a nutshell, what are the top 3-5 things I should be aware of this week, both positive and negative?" (Get to the key issues quickly.) "Are we on track to meet the original objectives, scope, timeline, and budget? If not, what's changed?" (High-level alignment check.) "How confident are you that we'll deliver on time and within budget? What's your level of certainty (e.g., percentage) and what are the main factors influencing that confidence?" (Assess the PM's risk awareness and contingency planning.) "What's the single biggest challenge facing the project right now, and what's being done to address it?" (Focuses on the most pressing issue.) "What's the single biggest win/positive development this week that we can celebrate?" (Important for morale and acknowledging progress.) "Are there any changes to the project scope or requirements? If so, how will those changes be managed and their impact on the project?" "Have any stakeholders raised concerns or expressed dissatisfaction recently? If so, how are we addressing those?"II. Timeline & Schedule



"Are we currently ahead, behind, or on schedule? By how much?"
(Quantify the schedule variance.) "What are the critical path activities for the next two weeks, and what's being done to ensure they stay on track?" (Focus on the most crucial tasks.) "Are there any dependencies that are at risk of causing delays? What mitigation strategies are in place?" "Has the team successfully completed the planned tasks for the last two weeks? If not, what were the reasons, and how are those tasks being addressed?" "What is the impact of any delays on the overall project timeline?" "How is the project team tracking against the schedule baseline?"III. Budget & Resources



"Are we currently over or under budget? By how much? Explain any significant variances."
(Quantify the budget variance.) "What are the key cost drivers contributing to any budget variances?" "Are there any anticipated cost overruns? If so, what are the causes, and what steps are being taken to control costs?" "Are we utilizing our resources efficiently? Are there any resource bottlenecks?" "Do we have the right resources in place to complete the project successfully? Are there any gaps?" "How are you tracking project expenses and ensuring they align with the budget?" "What is the burn rate, and is it in line with expectations?"IV. Risk & Issue Management



"Have any new risks or issues emerged in the last two weeks? How are they being documented and tracked?"
"What are the top 3-5 highest priority risks or issues right now, and what's the status of their mitigation/resolution plans?" "Are the risk mitigation strategies proving effective? Do we need to adjust our approach?" "Are there any potential risks that could impact the project in the near future?" "Is the risk register up-to-date and accurate?" "Have any issues escalated beyond the project team's ability to resolve them? If so, what support do you need?"V. Communication & Stakeholder Management



"How effective is communication within the project team and with key stakeholders?"
"Are there any stakeholder concerns or feedback that need to be addressed?" "Have there been any changes in stakeholder expectations or requirements?" "What's the plan for communicating project progress to stakeholders?" "Are you proactively managing stakeholder expectations?" "Are there any conflicts within the team or with stakeholders that need to be addressed?"VI. Quality & Deliverables



"Are the project deliverables meeting the defined quality standards?"
"What quality assurance processes are in place?" "Have there been any quality issues or defects identified? How are they being resolved?" "Are we tracking key performance indicators (KPIs) related to quality?" "Are the project deliverables aligned with the project objectives and stakeholder requirements?"VII. PM Support & Assistance



"What support do you need from me or other stakeholders to help the project succeed?"
(This is a crucial question to ensure the PM feels supported.) "Are there any roadblocks that I can help remove?" "Do you need any decisions made or approvals obtained from me?" "Are there any resource constraints that I can help address?" "Do you have any concerns about the project that you'd like to discuss privately?"VIII. Process & Lessons Learned



"Are there any areas where our project processes could be improved?"
"What lessons have we learned so far that can be applied to future projects?" "What's working well on the project?"Tips for Effective Questioning



Be specific

Avoid vague questions. Ask for concrete numbers, dates, and details.


Listen actively

Pay attention to the PM's answers and ask follow-up questions to clarify anything that's unclear.

Focus on solutions

While it's important to identify problems, the goal is to find solutions and move forward.


Be supportive

The PM should feel comfortable being honest about challenges without fear of blame.

Document action items

Clearly assign ownership and deadlines for any actions that arise from the meeting.


Tailor the questions

Adjust the questions based on the specific project and its current phase.

Encourage Transparency

Foster a culture where the PM is comfortable sharing both good news and bad news.


Don't Micromanage:
Avoid getting into the weeds of every single task. Focus on the overall project health and key risks.By asking these types of questions regularly, you can stay informed about the progress of your projects, identify potential problems early, and ensure that your project managers have the support they need to succeed. Good luck! Flag for review