Question: Gents,It is my understanding that the industry is moving away from doing live 480V bus ties on Switchgear. Due to NFPA, OSHA and so forth.It is also my understanding that some sites are not in phase and live buss tieing can be very dangerous in this condition.My current switchgear contractor just emailed me and told me they are no longer allowed to do it.So this is all very understandable.However, my site has 40 substations that were built for live bus tieing. My maintenance guy has been closing bus ties out here for 40 years without incident. They even practice closing live 480V bus ties on a monthly basis to train people. ON several occasions they have even closed EVERY single buss tie on site....with all 40 of our 4160V breakers fully closed. All bus ties perform flawlessly, in perfect phase.So although this rule is good for most, I don't see how it applies to my site. I feel there is an exception here.If this rule is actually infused, We will likely have 3 times the amount of shutdowns per year costing big money in production. (no one likes losing money)What are other people doing in regards to this assuming you have the same in phase switching that I have? Oh ya, our guys ALWAYS wear the full 40 calorie moon suit when switching anything in our switchgear.I realize this is a touchy subject for the moderators, but I believe it is one that should be openly discussed.

You've raised a valid concern and a real dilemma. Here's a breakdown of the situation and some points to consider, as well as what others might be doing

Understanding the Concerns and Why the Shift
Safety First

NFPA 70E (Electrical Safety in the Workplace) and OSHA regulations are increasingly focused on reducing arc flash hazards. Live switching, even in seemingly "perfect" conditions, always carries a risk of arc flash due to unforeseen issues (dirt, corrosion, equipment malfunction). The consequences of an arc flash at 480V are severe, and the standards are designed to minimize that risk.


Potential for Phase Issues

While your system might consistently be in phase, the contractor is likely wary of the inherent risk. Phase shifts can occur due to: Utility Grid Changes: The utility feeding your substations can experience changes that affect phase relationships. Generator Issues: If you have on-site generators, their synchronization could drift. Transformer Problems: Transformer faults or changes in tap settings can impact phase angles. Wiring Errors: Maintenance errors or undocumented modifications can introduce phase problems.

Contractor Liability

Your contractor is responsible for the safety of their employees. If an incident occurs during live switching, even if your equipment is deemed "safe," they will be held accountable. Their insurance company and internal safety policies likely prohibit this practice.


Human Error

Even with skilled technicians, mistakes happen. A dropped tool, a moment of distraction, or misreading an instrument can have catastrophic consequences during live switching.

Why Your Situation Seems Different (But Still Has Risks)
Historical Success

40 years of incident-free operation is compelling evidence of a well-maintained and reliable system.


Rigorous Training

Monthly training and the use of appropriate PPE (the 40-calorie suit) demonstrate a strong commitment to safety.

Consistent In-Phase Operation

If your system consistently exhibits proper phase alignment, it reduces the immediate risk of a catastrophic event.


Production Impact

The potential for increased shutdowns and the associated financial losses are a legitimate concern.

What Others Are Doing (And How to Approach Your Situation)
1. Detailed Engineering Study



Phase Angle Monitoring

Implement continuous phase angle monitoring at key points in your system, especially at each substation bus tie. This provides real-time data and alerts you to any deviations.


Load Flow Analysis

Conduct a comprehensive load flow study to model your system's behavior under various operating conditions. This can identify potential phase angle shifts and voltage drops.

Short Circuit Study

A short circuit study would analyze the impact of closing bus ties, or possible phase shifts under fault conditions.


Reliability Centered Maintenance
- Use your historic data to predict failures and properly allocate resources.2. Risk Assessment and Mitigation Plan



Formal Risk Assessment

Conduct a formal risk assessment that considers the specific hazards associated with live bus tie operations in your system. Involve your contractor, your maintenance team, and a qualified electrical engineer.


Mitigation Strategies

Develop a comprehensive mitigation plan that addresses each identified risk. This might include:

Strict Procedures

Reinforce and document detailed, step-by-step switching procedures.


Enhanced Monitoring

Implement continuous monitoring of voltage, current, and phase angle at the bus ties.

Remote Switching

Consider installing remote-operated bus tie switches that can be controlled from a safe distance.


Redundant Protection

Ensure that your protective relaying system is properly coordinated and provides adequate protection against faults.3.

Negotiation with Your Contractor



Present Your Data

Share the results of your engineering studies and risk assessment with your contractor. Demonstrate that you have a thorough understanding of the system and a proactive approach to safety.


Seek Alternatives

Explore alternative solutions that might satisfy both your production needs and the contractor's safety concerns. This could involve:

Limited Live Switching

Restricting live switching to specific circumstances (e.g., during emergencies or for brief testing).


Detailed Pre-Switching Checks

Implementing a rigorous pre-switching checklist to verify phase alignment, voltage levels, and equipment condition.

Contractor Oversight

Having a qualified contractor representative present during live switching operations.4.

Consider a Dedicated On-Site Team

If live bus ties are critical for your site, consider a dedicated, in house electrical maintenance team. This would eliminate reliance on a contractor, and give you greater control of operations, but at the cost of personnel.5.

Upgrades / Retrofits

Install new switchgear with modern interlocks to prevent closing out of phase. Install relaying to prevent closing out of phase.

Important Considerations



Documentation

Meticulously document all procedures, training, maintenance activities, and monitoring data. This is essential for demonstrating due diligence and managing risk.

Compliance

Ensure that your practices comply with all applicable NFPA 70E and OSHA regulations. Consult with a qualified safety professional to ensure compliance.


Continuous Improvement

Regularly review and update your procedures, training, and mitigation strategies based on experience and new information.

In conclusion:
While your history of successful live bus tie operations is notable, the industry trend is towards minimizing live switching due to inherent safety risks. A comprehensive risk assessment, engineering studies, and negotiation with your contractor are essential to finding a solution that balances safety, production, and cost.Remember, safety should always be the top priority. Even with a "perfect" system, the potential consequences of an arc flash or other electrical incident are too severe to ignore. Flag for review