Topic: Cost Estimate: Temporary Generator

User: Prototype1, Location: Kansas City

Asked on: Thursday, January 23, 2025 at 2:38 pm EST
Answered on: Thursday, March 6, 2025 at 7:43 am EST

Question: I am working on a quick disconnect generator project and creating a cost estimate. We have seven generators in storage, consisting of three 300 kW, two 400 kW, and two 500 kW units.I have obtained a list of buildings from the user, which includes over 30 buildings. My task is to determine which generator can power each building. To do this, I have researched the Main Distribution Panel (MDP) size for each building and performed calculations to determine the required generator size.For example, Building 40 has an MDP size of 208Y/120 3P 4W 1000A. Using the formula:I x E x 1.731000I calculated that the required generator size is 287.87 kW. Since we have a 300 kW generator available, I know it can handle the load.To bring the 300 kW generator to the building and connect it to the Main Distribution Panel, what line items do I need to include in my estimate? The goal is to power the critical circuits with the generator.We already have the 300 kW generator on standby, and the MDP is already installed in the building. This will be a temporary generator setup, which will be used for 3 to 4 days when the building experiences an outage. After that, the generator will be returned to storage and made available for use in other buildings.Currently, my estimate includes a manual transfer switch and a safety switch. I am also considering sizing the wire and conduit, as well as Camlock connectors. However, I lack experience in this area and am unsure what other equipment I may need.

Okay, let's break down the line items you need to include in your estimate for deploying a 300kW generator to power critical circuits in Building 40 for 3-4 days. You're on the right track with the components you've already identified. Here's a more comprehensive list, broken down into categories, along with explanations and considerations

1. Equipment & Materials:
Manual Transfer Switch (MTS)

This is essential. It isolates the building from the utility grid before connecting the generator, preventing backfeeding and potential damage to the grid and personnel.

Be sure to size the MTS appropriately for the building's amperage (1000A in your example) and voltage (208Y/120 3P 4W).
Consider the MTS rating for continuous load and fault current.
Safety Switch (Disconnect Switch)

A safety switch (disconnect) installed close to the generator will allow for safe isolation for service and maintenance. Size this appropriately for the generator output amperage.

Generator Connection Cable/Cord (Sizing & Type)



Wire Gauge Calculation

This is critical! Calculate the required wire gauge based on the generator's output current at 208V (300kW / (208V 1.73 0.8 PF) = ~1042 Amps, assuming a power factor of 0.8). Use appropriate ampacity charts to determine the correct wire gauge for the distance between the generator and the MTS. Over-sizing slightly is always better than under-sizing. Consider voltage drop over the cable run; longer runs require thicker cable. You will likely need to use multiple conductors in parallel, it will be better to use larger cables for fewer parallel runs.

Cable Type

SOOW cable is a common choice for temporary generator connections because of its flexibility and durability. Other options include Type W cable and cable tray rated cable.


Length

Accurately measure or estimate the distance between the generator placement and the MTS. Add extra length for connections and slack.

Quantity

Determine the number of conductors needed (typically 5 for 3-phase, neutral, and ground).


Conduit (if required)

If you are running the cable underground or need to protect it from physical damage, you'll need conduit. Rigid metal conduit (RMC) or intermediate metal conduit (IMC) are common choices. PVC conduit is less expensive but may not be suitable for all situations.

Size

Calculate the conduit size based on the number and size of conductors you are pulling.


Fittings

Include couplings, connectors, and straps for the conduit run.

Length

Measure the length of the conduit run.


Camlock Connectors (or other quick disconnects)

These are essential for quickly and safely connecting the generator.

Amperage Rating

Choose connectors rated for at least the generator's full output current.


Configuration

Ensure the connectors match the voltage and phase of the generator and the MTS (208Y/120 3P 4W in your example). Common configurations include 16 Series Camlocks.

Quantity

You'll need connectors for each conductor (3 phases, neutral, ground) at both ends of the cable (generator and MTS).


Color Coding

Use standard color coding (Black, Red, Blue for phases, White for Neutral, Green for Ground) to avoid misconnections.

Grounding

This is critical for safety!


Grounding Rod(s) & Clamps

If the generator doesn't have a robust grounding system, you may need to drive a grounding rod near the generator and connect it to the generator's ground lug.

Grounding Wire

Use appropriately sized grounding wire to connect the generator frame to the grounding rod and the MTS grounding point.


Fuel



Fuel Tank (if needed)

Does the generator have an onboard fuel tank sufficient for 3-4 days of operation? If not, you'll need an external fuel tank. Consider a double-walled tank for environmental protection.


Fuel

Estimate the generator's fuel consumption rate (gallons per hour) at the anticipated load. Multiply this by the operating hours to determine the total fuel needed. Factor in a safety margin.

Fuel Delivery

Include the cost of delivering fuel to the site.


Extension Cords & Lighting

For safety and convenience.

Barricades and Warning Tape

To cordon off the generator area and prevent unauthorized access.


Signage

"Generator in Use," "Authorized Personnel Only," and other relevant safety signage.

2. Labor & Services



Transportation



Generator Transport

The cost to transport the generator from storage to the building. Consider truck rental, fuel, and driver costs.

Equipment Transport

The cost to transport all other equipment (cables, MTS, tools, etc.).


Installation/Setup



Electrician Labor

This will be your biggest labor cost. Include the cost of a qualified electrician to:
Inspect the generator and MTS. Run and connect the cable/conduit. Install the Camlock connectors. Perform all electrical connections. Verify proper grounding. Test the system.

Labor Hours Estimate

Accurately estimate the number of labor hours required. This depends on the complexity of the installation, the distance between the generator and the MTS, and any site-specific challenges. Get input from your electrician.

Permitting (if required)

Check local codes to see if a permit is required for temporary generator installations.


Testing & Commissioning

After installation, thoroughly test the system to ensure it's working correctly. This includes: Verifying voltage and phase rotation. Load testing the generator. Checking for any overheating or other issues.

Fueling & Maintenance



Fuel Delivery Labor

If you're using an external fuel tank, include the labor cost for fuel delivery.


Generator Monitoring

Someone should check the generator regularly for proper operation, fuel levels, and any potential problems.

Minor Maintenance

Include a small allowance for minor maintenance tasks (e.g., adding oil, cleaning air filters).


Decommissioning & Removal



Disconnecting and Disassembling

The cost to disconnect all the equipment and disassemble the temporary installation.


Equipment Removal

The cost to remove the generator, cables, MTS, and other equipment from the site.

Generator Return

The cost to transport the generator back to storage.

3. Contingency



Unexpected Issues

Always include a contingency (5-10%) to cover unexpected problems, such as damaged equipment, unforeseen site conditions, or additional labor requirements.

Important Considerations



Safety

Safety is paramount. Ensure all personnel involved are properly trained and equipped with the necessary PPE. Follow all applicable electrical codes and safety regulations.


Local Codes

Be sure to comply with all local electrical codes and regulations regarding temporary generator installations.

Generator Condition

Thoroughly inspect the generator before deployment to ensure it's in good working order.


Critical Load Identification

Confirm with the user exactly which circuits are considered "critical" and need to be powered by the generator. This will help you size the MTS and select the appropriate circuits to connect.

Load Shedding

Consider implementing load shedding strategies to prevent overloading the generator. This involves turning off non-essential loads if the generator's capacity is reached.


Communication

Establish clear communication protocols with the building occupants to keep them informed about the generator's operation and any potential disruptions.

Example Estimate Snippet (Building 40 - 300kW Generator):
| Line Item | Description | Unit | Quantity | Unit Cost | Total Cost

------------------------------- | --------------------------------------------------------------------------- | ------- | -------- | --------- | ----------
Manual Transfer Switch (MTS) | 1000A, 208Y/120, 3P 4W, NEMA 3R | Each | 1 | $3,500 | $3,500
Safety Switch | 1200A, 240V, 3P | Each | 1 | $1,500 | $1,500
SOOW Cable | #500 MCM, 208Y/120 3P 4W (with ground) | Feet | 75 | $35/ft | $2625
Camlock Connectors | 400 Amp, 208Y/120, 3P 4W set (5 per side) | Set | 2 | $150 | $300
Grounding Rod | 8 ft Copper Ground Rod with Clamp | Each | 1 | $50 | $50
Electrician Labor (Install) | Installation, testing, and commissioning | Hours | 24 | $125 | $3000
Generator Transportation | Trucking from storage to site | Trip | 1 | $500 | $500
Fuel (Diesel) | Estimated consumption for 4 days | Gallons | 200 | $4/gallon | $800
Contingency | 5% of subtotal | - | - | - | [Calculate] |Remember to get actual quotes from suppliers and subcontractors for accurate pricing. This detailed breakdown should help you create a more comprehensive and accurate cost estimate for your quick disconnect generator project. Good luck! Flag for review