Question: I have a job that needs a 38ft x2ft deep hand dug trench. The house is on top of a steap hill that goes out to the lake. He is needing electricity ran to a Pier he is building. How much would be fair for hand dug trench with Conditions being on a steap incline while digging it. I have dug many of trenches and some by hand but not on a pretty good size incline. I want to be fair to my client who has some other potential work for me in the near future but don't want to cut my throat either with a family to support. Just would like some opinions. Thanks
Okay, digging a 38ft x 2ft deep trench by hand on a steep incline presents some significant challenges and deserves a premium price. Here's a breakdown of factors to consider and how to estimate a fair price
Factors Affecting Price:
Steepness of the Incline
This is the biggest driver of difficulty. A gradual slope is very different than a near-vertical slope. The steeper it is, the slower the work, the more physically demanding, and the greater the risk of slips, falls, and cave-ins.
Soil Type
Is it loose soil (easy to dig but prone to collapse), rocky, clay-heavy, or a mix? Rocky soil will dramatically increase time and effort. Clay can be heavy and difficult.
Access
How easy is it to get tools and materials (shovels, picks, wheelbarrow, conduit, wire) to the trench location? Long carries uphill will slow things down.
Water Table
Are you likely to hit water at 2 feet deep? If so, you'll need to pump it out, which adds time and complexity.
Obstacles
Are there roots, buried rocks, or other obstructions that will slow you down?
Safety Considerations
On a steep slope, proper shoring or benching may be necessary to prevent cave-ins, especially at 2 feet deep. This requires additional materials and labor. This is very important.
Time Estimate
How long do you realistically think it will take you to complete the job? Be honest with yourself, considering all the above factors.
Your Labor Rate
What is your normal hourly rate for digging trenches?
Profit Margin
How much profit do you need to make to cover your business expenses and provide for your family?
Pricing Methods
Here are a few approaches to pricing, ranked from simplest to most accurate:1.
Hourly Rate + Materials
This is the safest for you, if you can accurately estimate the hours.
Estimate the Hours
This is crucial. Think about how many feet you can realistically dig per hour in these conditions. Start with a lower number than you think you can accomplish, then adjust up. Don't underestimate the time. Assume the worst soil conditions until you know otherwise. Digging on a steep hill is exhausting.
Factor in Set-up and Clean-up
Include time for getting tools, laying out the trench line, removing debris, etc.
Calculate Total Labor Cost
(Estimated Hours) x (Hourly Rate)
Add Material Costs
(if you are supplying anything besides labor) Conduit, warning tape, backfill material, etc.
Add Profit Margin
(Labor Cost + Material Costs) x (Profit Margin Percentage) (e.g., 20% or higher, considering the difficulty).
Total Price = Labor Cost + Material Costs + Profit MarginExample (Using Hourly Rate)
You estimate it will take you 30 hours to complete the job. Your hourly rate is $50/hour. Labor cost = 30 hours x $50/hour = $1500 Material cost (if you are providing conduit, etc.) = $100 Profit margin = ($1500 + $100) x 25% = $400 Total price = $1500 + $100 + $400 = $20002.
Price per Linear Foot
This requires careful consideration and a good understanding of the soil and slope.
Research Average Prices
Look online or ask other contractors what they charge per linear foot for hand-dug trenches. However, remember that those prices are unlikely to account for the steep slope.
Adjust for Difficulty
Dramatically increase the price per foot due to the incline. A normal price might be $10-20/ft for easy digging. On a steep slope, you might need to double or triple that.
Calculate Total Price
(Price per Foot) x (Number of Feet)
Add a buffer for unexpected issues
Add 10-20% to cover unforeseen obstacles or problems.
Example (Using Price Per Foot)
You decide a fair price per foot is $40 due to the slope and potential soil issues. Total price = $40/foot x 38 feet = $1520 Buffer for unexpected issues = $1520 x 15% = $228 Total price = $1520 + $228 = $17483.
Fixed Price (Lump Sum)
This is the riskiest for you, but can be acceptable if you're very confident in your estimate. Only do this if you have thoroughly assessed the site and soil.
Estimate the Hours (As Above)
Do a very careful time estimate. Be conservative.
Calculate Labor Cost (As Above)
Add Material Costs (As Above)
Add Profit Margin (As Above)
Increase your profit margin significantly to account for the risk of underestimating.
Add a Contingency Fund
Include a separate line item for a "contingency fund" (e.g., 10-20% of the total) to cover unexpected problems.
Total Price = Labor Cost + Material Costs + Profit Margin + Contingency FundRecommendations
Thorough Site Inspection
Before quoting, thoroughly inspect the site. Walk the entire trench line. Dig a test hole or two to assess the soil. Take pictures. Note any potential obstacles.
Communication with the Client
Explain the challenges of digging on a steep slope. Be transparent about why the price is higher than a typical trench.
Consider a Phased Approach
If you're unsure about the soil, you could propose a price for the first 5-10 feet, then reassess and adjust the price if necessary.
Document Everything
Take photos of the site before you start, during the work, and after completion. Keep a record of your hours.
Written Contract
Get everything in writing, including the price, scope of work, payment schedule, and any assumptions you've made (e.g., "price assumes no significant rock or obstructions"). Specify who is responsible for permits (if any) and backfilling.
Safety First
Don't compromise on safety. Wear appropriate PPE (gloves, eye protection, sturdy boots). If the soil is unstable, use shoring or benching. Never work alone on a steep slope.
Be prepared to walk away
If the conditions are truly too dangerous or the client isn't willing to pay a fair price, it's better to decline the job.
Ballpark Figures
It's impossible to give an exact price without seeing the site, but here's a very rough ballpark:
Low End (Favorable Conditions, Experienced Digger)
$1500-$2000
Mid-Range (Moderate Conditions, Reasonable Experience)
$2000-$3000
High End (Difficult Conditions, Significant Risk)
$3000+Remember that these are just estimates*. Your actual price could be higher or lower depending on the specific circumstances.
Final Thought:
Don't undervalue your labor. Digging a trench on a steep slope is hard work and presents safety risks. Be fair to your client, but also be fair to yourself and your family. The potential for future work is valuable, but it shouldn't come at the expense of your well-being and a reasonable profit. Good luck! Flag for review