Question: need some guidance 90.2 (b) 4 (not covered) installations of communications equipment under exclusive control of communications utilities does this apply to the service, mains and feeders as well

Okay, let's break down NEC 90.2(B)(4) and its implications for service, mains, and feeders in communications utility installations.

Understanding NEC 90.2(B)(4) The Code (NEC 90.2) defines the scope of what the National Electrical Code covers. It tells you which electrical installations are subject to the rules within the NEC. Section (B) lists installations that are NOT covered by the NEC. This is crucial. Paragraph (4) specifically excludes

"Installations of communications equipment under the exclusive control of communications utilities, located outdoors or in building spaces used exclusively for such installations"

Key Elements of 90.2(B)(4)


Communications Equipment

This refers to equipment specifically designed and used for transmitting and receiving communications signals. Think telephone exchanges, radio transmitting stations, data centers for telecom providers, etc. This
doesn't generally include general-purpose office equipment or building systems (HVAC, lighting) even if they're used by a communications utility.2.

Exclusive Control of Communications Utilities

This is a critical element. "Exclusive Control" usually means the utility owns, operates, and maintains the equipment and the electrical system powering it. It also implies the utility has the technical expertise and personnel to ensure the safety and reliability of the installation. The key is that the utility isn't simply
using the equipment; they are the sole authority and responsibility for it. This needs to be legally documented or at least clearly demonstrable.3.

Location

The equipment must be located
outdoors OR in building spaces used exclusively for such installations. This means a dedicated room or building only housing communications equipment. If the room houses other equipment (e.g., general building power panels, HVAC for the whole building), the exemption likely doesn't apply.

Does 90.2(B)(4) Apply to Service, Mains, and Feeders?
Generally, YES, but with caveats. If the entire electrical system (service, mains, feeders, and the communications equipment itself) falls under the "exclusive control" of the communications utility and is located in a space dedicated solely to communications equipment, then 90.2(B)(4) likely applies, and those elements are not covered by the NEC. Important Considerations and When the NEC DOES Apply



Shared Spaces

If the service equipment or feeders also supply power to non-communications equipment within the building (e.g., general lighting, HVAC that serves non-utility areas, other tenants), then 90.2(B)(4) does not apply to the service, mains, and feeders up to the point where they exclusively serve the communications equipment. The NEC would cover the installation up to that point.

Separation of Systems

If the communications utility has a
completely separate service, mains, and feeders dedicated only to their equipment in a dedicated space, then the exemption is more likely to apply.

Point of Demarcation

There might be a "point of demarcation" where the utility's responsibility ends and the building owner's/operator's responsibility begins. The NEC would likely apply before that point.

Local Amendments

Many jurisdictions have local amendments to the NEC. Some may modify or clarify the application of 90.2(B)(4).
Always check with the local authority having jurisdiction (AHJ).

Safety

Even if 90.2(B)(4) technically applies, good engineering practice dictates that the installation should be done safely and in accordance with recognized standards. Many utilities will still follow aspects of the NEC, even if not legally required.

Resale of power
: If the Utility is reselling power to other entities/occupants it is likely that 90.2(B)(4) does not apply to the service, mains and feeders.

In summary


Dedicated System is Key

If the service, mains, and feeders
exclusively supply communications equipment in a dedicated space under the exclusive control of the communications utility, then 90.2(B)(4) likely applies (check local amendments!).2.

Shared System Means NEC Applies

If the service, mains, and feeders
also supply other loads or non-dedicated spaces, then the NEC does apply up to the point where the system exclusively serves the communications equipment.3.

Consult the AHJ

The
final determination rests with the local Authority Having Jurisdiction (AHJ). Talk to them.

Example Scenarios



Scenario 1: Telco Central Office

A large building solely housing telephone switching equipment, backup generators, and related telecom infrastructure. The utility owns and operates the entire system. 90.2(B)(4) likely applies to the entire electrical system within that building.

Scenario 2: Data Center within a Multi-Tenant Building

A communications utility leases space in a multi-tenant office building to house a data center. The building's main electrical service supplies power to the entire building, including the data center. 90.2(B)(4)
does not apply to the building's service or the feeders up to the point where they solely serve the data center. The feeders and electrical equipment within the dedicated data center space, and under the exclusive control of the utility might be exempt, but it would depend on the specifics and the AHJ's interpretation. If the building owner maintains the electrical system up to a point, the NEC applies up to that point.

Scenario 3: Cell Tower

A cell tower with a dedicated meter and service equipment solely powering the communications equipment at the tower site. The utility owns and maintains the equipment. 90.2(B)(4) likely applies to the entire electrical system at the tower.

Recommendations


Document the Basis for Exemption

If you believe 90.2(B)(4) applies, thoroughly document why. Include ownership details, lease agreements (if applicable), maintenance agreements, and a clear description of the equipment and its exclusive use.
2.


Engage the AHJ Early

Discuss the proposed installation with the local electrical inspector before starting any work. Get their interpretation of 90.2(B)(4) and any local amendments. This can save you significant time and money.
3.


Prioritize Safety:
Even if the NEC doesn't legally apply, follow good electrical safety practices and consider using recognized standards (like IEEE, ANSI) for design and installation.By carefully considering these factors and consulting with the AHJ, you can determine whether 90.2(B)(4) applies to the service, mains, and feeders in your specific communications equipment installation. Remember to prioritize safety in all cases. Flag for review