User: blueheels2, Location: Raleigh, NC
Asked on: Saturday, March 22, 2025 at 6:26 pm EDT
Answered on: Saturday, March 22, 2025 at 6:26 pm EDT
Question: Have there ever been any big changed in the ampacity chart in the past 50 to 60 years?I have a multifamily apartment where the underground feeder from the transformer to the meter mains failed last night. I have seen the wire in the main/pull box and in the transformer. Wire from the transformer is a single set of 500 AL (2 hots 1 neutral) that comes up through the slab into a junction box. A splice is made in that j/box splitting the 500/s into 2-500’s that land on a 60@ amp breaker.Power Company (Duke) says that the cable is customer owned, customer problem.However the wire from transformer to junction box is only rated for 310 amps current NEC. It’s interesting to me that in the j-box below the main they splice and make 2-500’s which would be good for the 600 amps, and send that to the breakers.Makes me think the wire from transformer to junction box is Dukes wire and from the tap to the breaker is reallly the customers.Plannning a complete replacement of the wire but due to the way things are wired I could never get parallel 500’s from the transformer to the junction box. Single 3” GRC leaves tap box and goes under the slab and stubs outside of the building footprint. Service is in a step down area slash 1/2 basement. No way to get there.So am I right in thinking wire from transformer to j-box is under power company rules and from the j-box to the breaker is under NEC? Or when these were built (est 1965-1980) the NEC allowed a single set of 500 Al to feed a multi family dwelling ?Sorr for the rambling post.
Okay, let's break down this complex situation. You're dealing with a service entrance issue, which is always tricky due to the varying jurisdictions and codes involved.1. Ampacity Changes Over Time
Yes, ampacity values in the NEC have changed significantly over the past 50-60 years. Several factors influence this: Improved Insulation Technology
Modern insulation materials can withstand higher temperatures, leading to increased ampacity ratings for the same conductor size. Older insulation types like RH, RHW, etc., had lower temperature ratings than modern THHN, XHHW, etc.
Better Understanding of Heat Dissipation
Research and testing have led to a more refined understanding of how conductors dissipate heat in different installation scenarios (in conduit, direct burial, in free air, etc.).
Revised Ambient Temperature Corrections
Ambient temperature correction factors (how much you have to reduce ampacity based on the surrounding temperature) have also been adjusted over time.
Harmonic Considerations
With the increased use of non-linear loads (electronics, etc.), harmonic currents can significantly increase conductor heating. Modern ampacity calculations sometimes need to account for this.
2. Utility vs. Customer Responsibility
Generally, the point of demarcation (where utility responsibility ends and customer responsibility begins) is at the service point. The service point is typically defined as the connection point of the utility's equipment to the building's wiring. This is often the lugs in the meter enclosure. Based on your description, the most likely scenario is this
Duke Energy's responsibility likely ends at the transformer lugs. The wire from the transformer lugs through the junction box and to the meter mains is the customer's responsibility. Even though the utility initially installed the wire from the transformer lugs, it becomes the customer's responsibility. The utility likely provided the tap box so their employees could work on the transformer without killing the building. Important
Review your local utility's service rules and regulations. They will have a clear statement of the demarcation point. Call Duke Energy and ask for a clear definition of their responsibility point. They may have records of the original installation that can help clarify the ownership of the wiring.
3. The Original Installation (1965-1980)
A single 500 kcmil aluminum conductor serving a multi-family dwelling in that era could have been acceptable, depending on the code edition and the calculated load. However, it's very unlikely it was code-compliant to feed a 600A overcurrent protection device. The code requires overcurrent protection to protect conductors at their ampacity rating. NEC requirements for load calculations for multi-family dwellings were different then. Demand factors (the percentage of total connected load that is expected to be in use simultaneously) were often more generous than they are today. So, a smaller conductor might have been considered adequate. The original installation could have been grandfathered in under earlier code editions if it met the code requirements at the time of installation. However, when you make significant changes or upgrades, the "grandfathering" may be lost, and you'll have to comply with the current code.4. Your Problem
You're correct: a single 500 kcmil aluminum conductor rated at 310 amps cannot feed a 600 amp overcurrent device under current NEC. The parallel 500 kcmil conductors from the junction box to the breakers are appropriately sized for a 600 amp load, assuming the conditions of use allow for that ampacity. (This assumes you are using the 75C ampacity values for the cables)5. Recommended Actions
Confirm Ownership
Absolutely clarify with Duke Energy where their responsibility ends. Get it in writing if possible. Request any available documentation from them regarding the original service installation.2.
Load Calculation
Perform a thorough load calculation for the entire building according to the current NEC. This will determine the minimum service size you need. Consider future load growth too (electric vehicle charging, etc.).3.
Code Compliance
The NEC requires that you protect conductors at their ampacity rating and the overcurrent device should be rated no higher then the lowest ampacity of any piece of equipment on the circuit.4.
Feeder Replacement Options
If you absolutely cannot get parallel conductors from the transformer to the junction box due to the existing conduit
Consider using larger conductors if possible within the 3" conduit. This may require using compact stranded conductors or conductors with higher temperature ratings.
If the load calculation permits
You might be able to reduce the size of the overcurrent protection device in the meter mains (if possible/allowed) to a value that matches the ampacity of a larger single conductor in the existing 3" conduit. This is unlikely, but it's worth exploring.
Complete Service Upgrade
The best solution is likely a complete service upgrade. This will involve: Installing a new conduit run (potentially a larger size). Installing new conductors (properly sized for the calculated load and code requirements). Potentially upgrading the meter mains to accommodate the new service. This is the most expensive option, but it ensures compliance, provides a reliable service, and allows for future load growth.
Important Considerations
Permits
You will need permits for this work.
Licensed Electrician
This is a job for a qualified and licensed electrical contractor experienced in service entrance work.
Inspection
The installation will be inspected by the local electrical inspector.
Coordination
Coordinate closely with Duke Energy and your electrical contractor to ensure the new service meets all their requirements.
In summary, the most likely scenario is that the wiring from the transformer lugs through the junction box is customer owned. The mismatched ampacity of that wire and the 600A breaker is a code violation that you'll need to correct during the replacement.Consulting with a qualified electrical engineer and a licensed electrical contractor is highly recommended* to ensure a safe and compliant installation. Flag for review