Question: Have 3- 1/C 13.2kv #500 w/ #250 600v ground getting pulled through 4". There are 4 sets/runs. The point to point distance is 400' with 3 bends and one pull box.How many men would be needed JUST for the WIRE PULL? Roughly. I'm thinking feeder, tugger etc. it would need 4 men.
Okay, let's break down the manpower requirements for this pull. You're pulling some hefty conductors through a challenging run.
Factors to Consider
Conductor Size and Weight
500 kcmil cable is heavy and relatively stiff, especially at 13.2kV. The #250 ground adds to the overall weight and friction.
Conduit Fill
Four sets of these cables in 4" conduit will have a significant fill. This significantly increases friction.
Distance and Bends
400 feet with three bends is a moderate distance, but the bends add resistance.
Pull Box
The pull box should reduce the overall pull tension, but its effectiveness depends on its placement and size.
Tugger Capacity
The tugger needs to be adequately sized for the anticipated pulling force.
Communication
Clear communication is essential for a safe and efficient pull.
Manpower Breakdown (Rough Estimate)
Here's a breakdown of the roles and why they're needed:1.
Tugger Operator
This person is responsible for operating the tugger safely and smoothly. They need to understand the tugger's capabilities, monitor the pulling force, and respond to signals from the communication person. (1 person)2.
Feeder/Cable Feeding
This person or people is/are responsible for feeding the cable into the conduit smoothly. They need to ensure the cable is lubricated properly and doesn't get tangled or damaged. Due to the size and number of cables, this may require 2 people, one for each set and keep things feeding smooth.
This might need 2 people. (2 people)3. Communication/Safety Watch
This person acts as the eyes and ears of the operation. They monitor the entire pull, communicate between the tugger operator and the feeder, and ensure that everyone is working safely. They also watch for any obstructions or problems that might arise. (1 person)4.
Lubrication Person(s)
They need to actively apply lubricant to the cable as it's being fed to reduce friction. This is critical with the conduit fill you have. If the lubricant is applied while feeding then the feeding person can also lubricate.
Why 4 People is a Good Starting Point
Heavier Cables Need More Control
500 kcmil is substantial, and needs to be fed properly.
Coordination is Key
With multiple sets of cable, synchronizing the feed is essential.
Safety
Having enough people ensures everyone can focus on their task and be aware of their surroundings. This is crucial for a potentially dangerous operation.
Additional Considerations
Experience
Experienced personnel can make a huge difference in efficiency and safety.
Lubricant
Use a high-quality cable lubricant specifically designed for the type of cable and conduit.
Tugger Setup
Ensure the tugger is properly anchored and positioned to provide a straight, consistent pull.
Communication
Use clear hand signals or radios for communication.
Pre-Pull Inspection
Inspect the conduit run for any obstructions or damage before starting the pull.
Pulling Tension
Monitor the pulling tension carefully. Exceeding the cable's maximum pulling tension can damage the conductors.
Breaks
Provide regular breaks to prevent fatigue.*
Permitting
Ensure all required permits are in place prior to starting the pull.
In Conclusion
Based on the information you provided,
I agree that 4 people is a reasonable estimate as a starting point for the pull. You may need to add a person if there is a problematic bend or feeding location. It's better to have enough manpower to do the job safely and efficiently.It's also important to note that this is just a rough estimate. The actual number of people needed may vary depending on the specific conditions of the job site and the experience of the crew. Always prioritize safety and adjust the manpower as needed to ensure a successful pull. Flag for review