Question: Hello,so, a 25' #4 copper wire was used to connect the rebars with a 8' copper rod, which was driven into the ground (1), and the town inspector came out and had us placed a J rebar with wire ties on the footer (3), and then sticking a short #4 rebar into the ground and connect it to the J rebar (2).Then he approved the slab and footer.I am not aware that this is a code-compliant method.Does anyone has an insight to this?

Okay, let's break down this grounding situation and whether it likely meets code. You're right to be skeptical; it sounds... unconventional. The goal is to create a grounding electrode system. Here's a breakdown of the issues and possibilities, keeping in mind this is a general assessment and a local electrical inspector's interpretation always prevails

The Components You Described and Their Likely Issues:
(1) 8' Copper Ground Rod & 25' #4 Copper Wire

This
is a common component of a grounding electrode system. A single ground rod might be sufficient, but often two ground rods at least 6 feet apart are required. A 25' #4 copper wire from the rebars to the rod is long and perhaps unnecessary. A shorter distance is better to minimize resistance.

(2) Short #4 Rebar Sticking Into the Ground Connected to a J-Rebar

This is highly problematic. The National Electrical Code (NEC) has stringent requirements for what constitutes an acceptable grounding electrode. A short piece of rebar driven into the ground almost certainly does NOT meet those requirements. The connection of the short rebar to the J-rebar using wire ties is also a weak electrical connection and would not be acceptable.

(3) J-Rebar in the Footer

This is the most likely source of confusion and possible misinterpretation. If the J-rebar is
encased in at least 2 inches of concrete that is in direct contact with the earth it MAY qualify as a concrete-encased electrode (also known as a "Ufer Ground"). The requirements for Ufer grounds are pretty specific:

Minimum Size

The rebar must be at least 20 feet long of at least 1/2" diameter rebar.

Encased in Concrete

It must be fully encased in at least 2 inches of concrete in direct contact with the earth.


Purpose of the "J"

The "J" bend is often used to bring the rebar out of the concrete for connection to the grounding electrode system.

Why This Arrangement Raises Red Flags



Insufficient Grounding Electrode

The short rebar driven into the ground is very likely not a code-compliant grounding electrode. It doesn't meet the requirements of a ground rod (length, driving depth), a concrete-encased electrode (length, proper encasement), or a ground plate.


Poor Connections

Wire ties alone are generally not acceptable for making grounding connections. Grounding connections need to be robust, mechanically sound, and corrosion-resistant. Approved grounding clamps or exothermic welds (cadwelds) are typically required.

Potentially Redundant & Unnecessary

If the J-rebar is properly installed as a Ufer ground, the additional ground rod may or may not be required by local code and soil conditions. The inspector likely has to take a reading to determine this.


Long Wire Run

A 25' #4 wire run to the rebar may be a bit lengthy.

Possible Explanations (Why the Inspector Might Have Approved It)



Ufer Ground Confirmation

Maybe the inspector was primarily interested in ensuring the
existence of a concrete-encased electrode and not necessarily its primary function. He may have tested it and found it adequate. But, the additional short rebar to J-rebar is still incorrect.

Local Code Variations

Some jurisdictions might have amendments to the NEC that allow for variations in grounding methods. Highly unlikely, but possible.

Misunderstanding

It's possible there was a misunderstanding in the communication between you and the inspector. He may have thought something was being done differently.


Temporary Measure?

Very unlikely, but perhaps the inspector viewed the short rebar and wire tie connection as a temporary measure to satisfy an immediate concern, with the understanding that a proper connection would be made later.*

Compromise Solution?

Sometimes inspectors make compromises to address immediate concerns, even if the final installation isn't strictly by-the-book. This is risky, as it could cause issues later.

What You Should Do


Politely Ask for Clarification

The best course of action is to contact the inspector (or their supervisor) and politely ask for clarification. Explain your concerns and ask them to specifically cite the code section they believe this arrangement complies with. Frame it as wanting to ensure the system is safe and meets all requirements.2.

Consult with a Licensed Electrical Contractor

Have a qualified electrician review the installation and provide their opinion. They can assess the grounding system, take measurements, and advise on whether it meets code and is safe. They can also provide documentation to back up their assessment.3.

Review Local Amendments

Check your local building and electrical codes for any amendments to the NEC that might be relevant.

In summary, based on your description, the grounding arrangement is highly suspect. It's crucial to get clarification from the inspector and, ideally, a licensed electrician. The short rebar driven into the ground and connected with wire ties is almost certainly not code-compliant.