User: Alwayslearningelec, Location: NJ
Asked on: Tuesday, September 2, 2025 at 9:24 am EDT
Answered on: Wednesday, September 3, 2025 at 1:38 pm EDT
Question: Would you labor conduit within CMU block wall differently that say conduit surface mounted or even recessed? I know you have ot install it in sections/stages as the bricky lays his rows so there is more comeback time. I believe.
Yes, you would definitely approach conduit installation within CMU (Concrete Masonry Unit) block walls differently than surface-mounted or recessed conduit. Here's a breakdown of the key differences and considerations
Key Differences and Considerations for Conduit in CMU Walls:
Installation Timing and Phasing
Coordination is Critical
You absolutely must work very closely with the mason (bricklayer). The conduit installation is directly integrated with the block-laying process.
Section-by-Section
Install conduit in sections after a course (row) of blocks is laid. This typically involves running conduit horizontally within a course, then transitioning up or down in the next course by using 90-degree bends or offsets, or through cutouts.
Comeback Time
You will have substantial "comeback" time because you have to wait for courses to be laid. Plan your schedule and manpower accordingly. Communication with the mason is critical to minimize delays.
Physical Support and Securing
Direct Attachment
You can't use traditional surface mounting methods. Instead, you'll likely use a combination of:
Straps and Clamps
Secure the conduit directly to the CMU block. Use fasteners designed for concrete/masonry (e.g., concrete screws, expansion anchors, powder-actuated fasteners)
Embedment
Conduit can be embedded in mortar joints but be careful to avoid creating weak points.
Vertical Support
Vertical runs will need to be supported in accordance with code (every 10 ft. typically). Consider using straps or clamps attached to the CMU block itself.
Prevent Movement
Ensure the conduit is securely fastened to prevent movement during the block-laying process. Loose conduit can shift, get crushed, or cause alignment problems with boxes and other components.
Protection from Damage
Physical Protection
CMU construction is rough. Protect conduit from damage during the process.
Marking
Clearly mark the location of conduits to prevent accidental damage during block placement.
Planning and Layout
Detailed Drawings
More detailed drawings are required to show exact conduit routing, bend locations, and box placements within the block wall.
Avoid Conflicts
Plan carefully to avoid conflicts with other utilities, reinforcement steel, or structural elements within the wall.
Access
Consider future access for maintenance and modifications.
Conduit Type and Material
Rigid Metal Conduit (RMC) or Intermediate Metal Conduit (IMC)
These are generally the preferred choices for CMU walls due to their strength and durability. They can withstand the stresses of construction better than EMT or PVC.
Electrical Metallic Tubing (EMT)
EMT can be used, but extra care is needed to prevent crushing or bending.
PVC
PVC is less common within CMU walls due to its lower physical strength. If used, it should be schedule 80 for physical protection.
Box Installation
Flush Mounting
Electrical boxes are typically flush-mounted within the CMU wall.
Box Positioning
Coordinate the box placement with the mason before the block is laid. You might need to cut out a portion of the block to accommodate the box.
Box Support
Securely support the boxes to the CMU. Methods include:
Mortar
Carefully mortaring around the box to hold it in place. Be careful not to get mortar inside the box.
Straps/Anchors
Using straps or anchors to attach the box directly to the CMU.
Box Extenders
May be needed if the box ends up recessed too far into the wall.
Code Compliance
NEC (National Electrical Code)
All installations must comply with the NEC. Pay particular attention to grounding and bonding requirements.*
Local Codes
Check for any local codes or amendments that may apply to CMU wall installations.
Summary of Key Differences Compared to Other Methods
| Feature | CMU Wall Installation | Surface Mount | Recessed (Stud Wall) -------------------|----------------------------------------------------------|---------------------------------------------------|------------------------------------------------------
Timing | Integrated with masonry work | After wall construction | After wall construction, before finishing
| Support | Direct attachment to CMU | Straps/clamps to surface | Straps/clamps to studs |
| Conduit Type | RMC/IMC often preferred | Varies (EMT, PVC, RMC, etc.) | Varies (EMT, PVC) |
| Planning | Highly detailed planning required | Less detailed planning | Moderate planning |