Question: So there’s big Subdivision I’m doing no electrical plans. Nothing met the guy out there to do temps I told him hey let’s put the temps an inch or two away from the building then we don’t have to move it again. He knew what we’re doing. I said good then I get wind after I did them all that they need to be 400 A no mention of it before. He’s upset because he wanted him 400 but there’s no in writing and I’ve never seen a temp 400 amp and he never told me just more problems just venting
Okay, I understand your frustration. This sounds like a classic communication breakdown on a project, which unfortunately happens way too often. Let's break down the issues and potential steps you can take
The Core Problem: Lack of Clear Communication & Documentation
The biggest issue is the lack of clear, written communication regarding the electrical requirements. Verbal agreements are easily forgotten, misinterpreted, or denied. You're right to be frustrated that the 400A requirement was not explicitly stated before you installed the temporary power.
Why This Matters Cost
400A temporary power is significantly more expensive than a standard setup (e.g., 200A). The materials, labor, and potential permitting are all impacted.
Time
Upgrading the temporary power now will likely cause delays.
Liability
If anything goes wrong with the electrical system, the lack of clarity can create liability issues.
Professionalism
Ultimately, this impacts the overall perception of your work and the entire project.
What You Can Do Now
Documentation is Key
Create a Memo-to-File
Immediately write down everything you remember about the conversation with the contractor. Include the date, time (as accurately as possible), what you said, and what he said (or didn't say) about the 400A requirement. This serves as your record of events.
Search for Supporting Documents
Look through any existing project documents you may have. Emails, meeting minutes, site plans, etc. – anything that might indirectly hint at the required power load.
Document the Current Situation
Take photos of the installed temporary power setup, including the breakers, meters, and any labeling. This visually documents what was installed based on the information you had at the time.2.
Communicate (Again, but Strategically)
Email Communication is Preferred
Avoid phone calls (unless you immediately follow up with an email summarizing the call). Email provides a written record.
Start with Inquiry
Instead of being accusatory, frame the email as a clarification request. Something like:> "Subject: Temporary Power Clarification - [Subdivision Name]>> Hi [Contractor Name],>> Following up on the temporary power installations at the [Subdivision Name] project. To ensure we're meeting all requirements, could you please provide the specific electrical load calculations for each temporary service? I want to make sure the installed services are appropriately sized for the project needs.>> As discussed on-site, the current installations are [e.g., 200A services] at each [location]. Please let me know if these services will need to be adjusted.>> Thanks,> [Your Name]"
Wait for a Response
Give the contractor a reasonable time to respond (e.g., 24-48 hours).
Address the Issue Directly (If Needed)
If the contractor insists on the 400A requirement without providing documentation, you can respond with something like:> "Thanks for the clarification. While I understand the desire for 400A service, this requirement was not communicated prior to the installation of the temporary power. Based on the information available at the time, [200A services] were installed.>> To proceed with upgrading to 400A service, we will need a written change order outlining the scope of work, associated costs, and any potential project delays. I want to ensure we have a clear record of the changes and approvals before proceeding."3.
Involve Your Supervisor/Project Manager (If Applicable)
Keep them informed of the situation and the steps you've taken. This is crucial for project oversight and potential budget adjustments. They might have additional insight into the project requirements or the contractor's expectations.4.
Get Quotes for the Upgrade
Obtain quotes for the cost of upgrading the temporary services to 400A. This will help you understand the financial implications of the change order.5.
Consider the "Why"
Try to understand why the contractor now needs 400A. Is it a legitimate need driven by specific equipment or processes, or is it just a preference? If it's a legitimate need, then upgrading might be unavoidable. If it's just a preference, there might be room for negotiation.
Important Considerations
Permitting
Be aware of local permitting requirements for temporary electrical services. Upgrading might require re-permitting.
Safety
Electrical work is dangerous. Ensure that any upgrades are performed by qualified and licensed electricians.
Contract Review
If you have a contract with the contractor, review it carefully for clauses related to changes, scope of work, and communication protocols.
Lessons Learned (For Future Projects)
Document Everything
Always get project requirements in writing, especially electrical specifications.
Early Communication
Proactively communicate with all stakeholders early in the project to clarify expectations and identify potential issues.
Pre-Construction Meetings
Insist on pre-construction meetings to discuss all aspects of the project, including electrical needs.
Use Standard Forms
Use standardized forms (e.g., change order requests, RFIs) to track and document project changes.*
Confirmation Emails: After verbal conversations, send a confirmation email summarizing the key points discussed.You're not alone in experiencing this type of project miscommunication. By documenting everything, communicating clearly, and involving your supervisor, you can navigate this situation and prevent similar issues in the future. Good luck! Flag for review