Question: Hey everyone,I’ve been involved in a few projects recently where electrical work was heavily dependent on how the rest of the construction was scheduled and budgeted. It made me realize how important coordination is between trades. For example, if wiring or panel installations get delayed because framing or drywall isn’t ready, it can throw the whole timeline (and budget) off balance.That’s why I’ve started paying more attention to the overall construction estimate at the very beginning of the project. Having accurate numbers not only helps clients but also makes it easier for us electricians to plan our work without running into surprises.How do you all handle this in your projects? Do you get involved in early cost discussions, or do you typically rely on the GC to handle it?
This is a great topic and a really important one for electricians and all subcontractors to understand! You're spot on about the domino effect caused by delays in other trades. Here's how I've seen this handled, and my own approach
Common Scenarios and Approaches:
Relying on the GC (Most Common, Least Ideal)
This is often the default. The GC is supposed to manage the schedule, budget, and coordination. However, this can be problematic, especially on larger or complex projects. The GC might not fully understand the interdependencies or might not communicate them effectively. This can lead to last-minute requests, compressed schedules, and change orders.
Limited Involvement in Early Cost Discussions
Often, the electrician submits their bid based on the plans and specifications. There might be a brief negotiation on price, but little discussion about the overall project budget or potential cost drivers from other trades. This leaves the electrician somewhat blind to the bigger picture.
GC Shared Budgets and Regular Coordination Meetings
This is a better scenario. Some GCs are more transparent and share the overall project budget with key subcontractors. They also hold regular coordination meetings where trades can discuss dependencies, potential conflicts, and upcoming milestones. This fosters collaboration and helps everyone stay informed.
Proactive Involvement in Early Planning and Value Engineering
This is the ideal scenario. The electrician (and other key subs) is involved from the very beginning, even during pre-construction. They can contribute valuable insights regarding constructability, cost optimization, and potential risks. This can lead to better planning, fewer change orders, and a more successful project overall.
How I Handle It (Trying to Move Towards the Ideal)
1.
Always Ask for the Schedule (and Understand It)
My first question to the GC, after reviewing the plans, is, "Can I see the preliminary schedule?" I want to see when they're planning on needing my work to be done and how it relates to other trades. This helps me identify potential bottlenecks and plan accordingly.2.
Ask Clarifying Questions During Bidding
Don't just assume anything. Ask specific questions about site access, availability of power, phasing, and other factors that could impact your labor and material costs. Document these questions and the answers you receive.3.
Communicate Early and Often
If I foresee any potential problems based on the schedule or plans, I raise them with the GC immediately. "Hey, I noticed the framing is scheduled to be completed two weeks before we need to start rough-in. Is there any flexibility there? We need the walls closed in for security and to keep the weather out before we start pulling wire."4.
Track Change Orders Meticulously
Even with the best planning, changes happen. Keep a detailed record of all changes, including the reasons for the change, the impact on your work, and the associated costs.5.
Build Relationships with Other Trades
Having good relationships with other subcontractors (framers, plumbers, HVAC, etc.) can be invaluable. You can often work together to find solutions to problems and avoid conflicts. A quick phone call to the framer to ask about a specific wall height can save a lot of headaches.6.
Consider the Big Picture
While it's tempting to focus solely on your own scope of work, try to understand the overall project goals and constraints. This will help you make informed decisions and contribute to the overall success of the project.7.
Value Engineering Suggestions (When Appropriate)
If you see opportunities to reduce costs without compromising quality or safety, suggest them to the GC. This shows that you're a team player and can help build trust. "Hey, I see you've specified X type of conduit here. We could potentially use Y type, which is less expensive and still meets code, saving you $X."
Challenges and Considerations
GC Resistance
Not all GCs are receptive to input from subcontractors. Some may view it as interference. It's important to be respectful and diplomatic in your approach.
Time Constraints
Getting involved in early planning takes time and effort, which can be challenging when you're busy bidding on other projects.*
Contractual Obligations
Review your contract carefully to understand your responsibilities and rights. Be sure your contract clearly outlines the scope of your work, payment terms, and change order procedures.
In conclusion, while relying solely on the GC is common, proactive involvement and communication are crucial for electrical contractors to manage risk, control costs, and ensure the success of their projects. Building relationships with other trades and understanding the overall project context are key to achieving this.
What are some specific examples you've encountered where better coordination or early involvement could have made a significant difference in one of your projects? That might spark even more discussion! Flag for review