Question: Bidding a very large site job where there are at least 40 different structures being fed underground. It's A LOT of duct banks and large wire. Probably a lot of money in copper. Not sure if it has to be turned over to owner. GC wrote an RFI asking if all underground utilities can be abandoned in place. They replied they must all be removed in their entirety.1. Would you actually estimate time to remove all those conductors from all the conduits? Asking because would that be what you would do if you got the job?2. Would you just disconnect and safe off and let GC remove all utilities as they are digging up ground in all the areas? But then how would you handle being able to get the copper?Thanks

Okay, this is a big job with significant potential profit and significant risk. Let's break down the issues and how I would approach estimating and handling it.1. Estimating Conductor Removal Time vs. Leaving in Place YES, Estimate for Removal

Given the owner's response that ALL utilities must be removed entirely, you absolutely MUST estimate the time to remove the conductors from the conduits. There's no getting around it. This is a significant cost driver.


Why It's Essential to Estimate Removal



Compliance

You're legally and contractually obligated to fulfill the owner's requirement.


Liability

If you leave it in place and the owner later finds out, you're liable for the cost of removal and potential penalties.

Cost

The owner is going to charge you back if they must deal with the wiring.

Estimating Time for Conductor Removal

This is where detailed planning is crucial. You need to account for many factors:


Conduit Size and Type

(PVC, RMC, etc.) This will affect how easily the conductors pull. Larger conduits, especially with sweeps, will be easier.

Conductor Size, Type, and Condition

Thicker conductors are harder to pull. Old, brittle insulation will be more prone to damage and make pulling difficult. Consider if it's copper, aluminum, or copper-clad aluminum.


Run Lengths

Longer runs mean more friction and resistance.

Number of Bends/Sweeps

Each bend increases pulling resistance. Get accurate counts from the drawings.


Accessibility

How easy is it to access both ends of each conduit run? Are they buried deep or near the surface? Are there obstructions?

Pulling Equipment

You'll likely need a powered wire puller. Factor in the time to set up, operate, and move the puller.


Crew Size and Skill

Experienced electricians will be faster and more efficient.

Potential for Conduit Damage

Sometimes, pulling conductors can damage the conduit, requiring repair or replacement. Account for this risk.


Disposal

Where will the removed conductors be staged? How will they be transported off-site?

Estimating Methodology


Review the Drawings

Thoroughly analyze the site plans and electrical drawings to identify all conduit runs, sizes, types, lengths, and bends.2.

Create a Spreadsheet

Organize the conduit runs by structure or area. List the conductor sizes, types, and estimated lengths.3.

Research Labor Units

Find labor units for pulling conductors of various sizes and types. Consult NECA manuals, RSMeans, or your company's historical data. Adjust these units based on your specific project conditions (run lengths, accessibility, bends, etc.).4.

Apply Contingency

Add a contingency factor (e.g., 10-20%) to account for unforeseen delays or difficulties.5.

Consider Different Estimating Methods
6. Get Sub Contractor Pricing

There are many demo companies that specialize in removing old wiring.

2. Disconnecting, Safe Off, and Letting GC Remove vs. Taking the Copper
The Dilemma

You want the copper value, but you also want to minimize your involvement in the demolition process.


Here's the problem
You have to remove the wiring, and now you have to find a place to stage it. You have to protect the wiring. You have to move it to the recyclers. You will have to pay your workers to pull the wiring. The GC has to dig up the ground anyway, do you just want the copper? My recommendation Give them a price to remove the wiring. Call your copper guy and give them a price to remove it. Call a demo company and give them a price to remove it. All three are going to give you pricing that will leave you a profit.

Things to keep in mind



Documentation

Take photos and videos of the work before, during, and after. This is crucial for resolving any disputes.

Safety

Ensure all work is performed safely and in compliance with OSHA regulations.


Change Orders

If you encounter unforeseen conditions that significantly impact the removal time or cost, submit a change order to the GC immediately.

Communication is Key



Communicate with the GC and Owner

Keep them informed of your progress and any potential issues.


Get Clarification

If you have any doubts about the requirements or scope of work, get written clarification from the GC and/or owner.*

Document Everything:
Maintain detailed records of all work performed, labor hours, materials used, and any changes or delays.This is a complex project, but with careful planning, accurate estimating, and clear communication, you can successfully complete the job and maximize your profit potential. Flag for review