Question: Project Overview:The homeowner's goal is to install the largest possible solar PV system on two buildings, totaling 17.160 kW DC / 13.611 kW AC. This system would consist of (39) 440W modules and (39) Enphase iQ8A-72-M-US microinverters.The city has no size restrictions, only requiring that the system is structurally and electrically sound, but it's the utility that is restrictive.The Utility's Restriction:The utility, Ameren (MO), has limited the homeowner's initial solar PV system size to a maximum of 9.715 kW DC. This limitation is based on the last 12 months of the customer's electricity usage, which is standard procedure.However, the homeowner's future energy needs are expected to increase significantly due to the recent installation of a new hot tub and the planned purchase of two used electric vehicles (EVs) by October 2025.Proposed Solution:To bypass the utility's initial size limit while still installing the full system, the following strategy is being considered:Initial Interconnection: Submit an interconnection application to Ameren for (22) 440W modules totaling a 9.680 kW DC system. However, the plan set would show the entire (39) module system being installed.Partial Energization: Only connect and energize (22) of the (39) solar modules. This will bring the initial system size to 9.680 kW DC, which is just below the utility's 9.715 kW DC limit. The remaining 17 modules will be installed but will remain dormant and non-functional.Future Expansion: Once the homeowner's electricity usage increases due to the hot tub and EVs, a new interconnection agreement can be submitted to Ameren to connect and energize the remaining 17 modules.Your thoughts and advice would be greatly appreciated!
Okay, this is a common problem and your proposed solution is a creative attempt to address it. Let's break down the potential pros, cons, and alternatives of this approach.
Analysis of the Proposed Solution
Pros
Installs the Full System Now
Avoids a future, more expensive, and potentially disruptive second installation. This saves on labor costs and allows the homeowner to benefit from potential tax credits/incentives that might not be available later.
Potential for Gradual ROI
Even at the smaller size, the homeowner benefits from reduced electricity bills immediately.
Avoids Size Restriction Headache Later
By having the entire system installed, future interconnection should be easier and faster than if the homeowner were to install a completely new system.
Capitalizes on Current Pricing
Installation prices might increase by the time the customer wants to add the additional panels.
Reduced Interconnection Fees Interconnection fees may be lower, since you are already an existing customer.
Cons/Risks
Honesty and Ethics
This approach relies on a slightly gray area in terms of honesty. You are installing the entire system but only interconnecting a portion initially. If discovered, this could lead to penalties from the utility, including potential disconnection of the entire system.
Utility Discovery
Ameren might discover the full system installation during an inspection or through other means (e.g., noticing the complete system on satellite imagery).
Code Compliance
The dormant portion of the system still needs to comply with electrical codes, including rapid shutdown requirements. How will these be met for the disconnected panels and microinverters? They might be connected to the bus wires, even though they are not energized.
Microinverter Warranty
The warranty on the unenergized microinverters could be affected. Check the manufacturer's warranty terms for long-term storage or non-operation. Enphase might require a commissioning test to activate the warranty, so running the system to test them out is important.
Potential for Panel Degradation
Unused panels, though not directly energized, are still exposed to the elements. This could potentially affect their long-term performance, although the impact is likely minimal.
Complexity for the Homeowner
The homeowner needs to fully understand the situation, the risks involved, and how to properly energize the remaining panels in the future. Clear documentation is essential.
Future Interconnection Uncertainty
Even with the system installed, Ameren could still impose different restrictions when the homeowner applies for the expansion. Utility policies can change.
Financial Risk
If the homeowner doesn't add the EV's or hot tub, and then never connects the other panels, then the customer wasted a portion of the investment.
String Inverter Compatibility
Even though the homeowner is using microinverters, if they switched to string inverters when they added the additional 17 panels, they would then have to pay for a hybrid solution and have two separate inverters, which isn't ideal.
Alternative Solutions and Recommendations
Transparency and Communication with Ameren
The best approach is often transparency. Explain the homeowner's future energy plans to Ameren and explore options for a phased interconnection. Some utilities have programs that allow for future capacity upgrades with pre-approval. Ameren might be more accommodating if they understand the situation upfront. A detailed energy usage forecast, backed by documentation (e.g., EV purchase agreements), can strengthen the case. This might mean submitting a larger system proposal but agreeing to a staged interconnection.2.
Battery Storage
Consider installing a smaller PV system coupled with battery storage. The batteries can be charged from the grid during off-peak hours and discharged during peak demand to offset the higher energy consumption from the hot tub and EVs. Battery inverters can bypass the restriction of the 9.715 kW DC by drawing power off the batteries.
3.
Load Management
Implement a load management system that prioritizes the use of solar energy and minimizes grid consumption. Smart appliances, EV chargers with adjustable charging rates, and automated energy management systems can help reduce peak demand and make the case for a larger PV system.4.
Incremental Installation (Less Risky than the Proposed Approach)
Install the initially approved 9.680 kW DC system. After a year of documented increased energy usage, submit a new interconnection application for the remaining capacity. This approach is less risky but delays the full system installation.
5.
Future-Proofing the Wiring
Regardless of the chosen approach, ensure the wiring and conduit are sized to accommodate the full 17.160 kW DC system. This will save on costs and labor during any future expansion. The homeowner can run wires in the attic to a junction box and cap them off until the customer wants to add the additional panels.
6.
Professional Engineering Stamped Letter
A licensed engineer can do an analysis of the structural integrity of the roof. Also, if the homeowner is willing to pay for the additional cost, they can do a full study on the electrical load the customer is expected to use in the future.
Specific Advice for the Proposed Solution (If Pursued)
Documentation is Key
Meticulously document the system configuration, including which panels are connected and which are not. Provide detailed instructions to the homeowner on how to energize the remaining panels.
Clearly Label the Unused Components
Mark the disconnected panels and microinverters with clear labels indicating that they are not energized and should only be connected by a qualified electrician.
Check Enphase Warranty
Contact Enphase to confirm the warranty implications of storing the microinverters in an unenergized state.
Rapid Shutdown
Ensure that the dormant portion of the system meets all rapid shutdown requirements.
Consult with Legal Counsel
Before proceeding with this approach, consult with an attorney specializing in solar energy to assess the legal risks and potential liabilities.
Homeowner Agreement
Have the homeowner sign an agreement acknowledging the risks and responsibilities associated with this approach.
In conclusion:
While the proposed solution is clever, it carries significant risks. Transparency and communication with Ameren are generally the best course of action. Exploring alternative solutions like battery storage, load management, or a phased interconnection approach may be more prudent. If the homeowner is set on this, ensure they fully understand the risks and that all necessary precautions are taken to minimize potential problems. A licensed electrical engineer must be involved to ensure all wiring and safety protocols are followed. Flag for review