Mike Dolt Enterprises Logo Mike Dolt Enterprises

Topic: Industrial and inspections

User: dm9289, Location: Pennsylvania

Asked on: Thursday, September 18, 2025 at 1:31 pm EDT
Answered on: Thursday, September 18, 2025 at 1:31 pm EDT

Question: I have worked in manufacturing for about 40 years mainly 3 different places. I lived through many upgrades and never seen any inspection or 3rd party plan review. Is this normal? Are manufacturing facilities with an engineer on staff exempt?

Okay, this is a great question, and the answer is nuanced. Here's a breakdown of why you might not have seen external inspections and plan reviews in your 40 years of manufacturing experience, and what influences that

Why You Might Not Have Seen External Inspections/Plan Reviews:
Nature of the Upgrade/Project

A lot depends on the
scope of the upgrades you've seen.

Minor Maintenance & Repair

Routine maintenance, like replacing a motor, fixing a conveyor belt, or patching a floor, rarely requires external permits, plans, or inspections.

Equipment Changes In-Kind

If you replace an old machine with a new, similar machine that doesn't require significant changes to utilities (electrical, plumbing, ventilation), you might not need a permit.


Process Improvements

Changes to manufacturing processes that don't involve significant building modifications or regulated equipment often fall under internal responsibility.

Jurisdictional Regulations

Building codes and permitting requirements are highly localized.


Rural vs. Urban

Rural areas often have less stringent enforcement than urban areas.

State Variations

States have different adoption levels of model building codes (e.g., IBC, IMC, IFC, NFPA).


Local Amendments

Cities and counties can amend the state-adopted codes, making requirements even more specific.

Enforcement Practices

Even if regulations
exist, the degree of enforcement varies.

Understaffed Departments

Building departments may be understaffed and prioritize residential or high-risk commercial projects.

Complaint-Driven Enforcement

Sometimes, inspections only happen if a complaint is filed (e.g., by a neighbor, a worker, or a competitor).


"Grandfathering"

Older manufacturing facilities may have been built under previous, less stringent codes. Upgrades may not trigger a requirement to bring the entire facility up to current code, only the specific area being modified.

Internal Expertise & Risk Management

Some companies, especially larger ones, have strong internal engineering and safety teams. They might conduct their own rigorous reviews and inspections, feeling confident in their ability to meet or exceed code requirements. This doesn't necessarily
exempt them from external requirements, but it can lead to a smoother permitting process (if required) and a lower likelihood of problems.

Type of Manufacturing

The nature of the manufacturing process impacts regulation. Food processing, chemical manufacturing, and facilities dealing with hazardous materials are more likely to face stringent inspections and plan reviews.

Misunderstanding the Process

Sometimes, inspections
do happen, but you might not be aware of them. They could be focused on specific equipment (e.g., pressure vessels, elevators, fire suppression systems) and handled by a different department or contractor.

Engineer on Staff & "Exemption"

Having an engineer on staff
rarely provides a complete exemption from external plan reviews and inspections. Here's why:

Liability

Building departments want to ensure compliance with the minimum safety standards. They are ultimately liable if something goes wrong. They are more likely to accept work stamped by a local engineer as adequate, but plan reviews and inspections may still be required.

Conflict of Interest

Even the most ethical internal engineer is still employed by the company. An independent review provides an objective perspective.


Code Expertise

Building codes are complex and constantly evolving. Even a skilled engineer might not be fully up-to-date on every aspect of the code. Building department plan reviewers are typically specialists in the relevant codes.

Specific Equipment/Systems

Certain systems (fire suppression, elevators, electrical) often require inspections by certified third parties, regardless of internal engineering expertise.


Local Laws

The permitting agency follows local laws and rules.

When External Inspections/Plan Reviews ARE Typically Required in Manufacturing



New Construction

Building a new manufacturing facility almost always requires full plan review and inspections.


Significant Alterations

Major renovations that change the building's structure, occupancy classification, or fire safety systems.

Changes in Occupancy

Changing the use of a space (e.g., converting warehouse space to a laboratory) will trigger plan reviews and inspections.


Installation of Regulated Equipment

Boilers, pressure vessels, elevators, and fire suppression systems typically require inspections by certified third parties.

Environmental Permits

Wastewater discharge, air emissions, and hazardous materials storage often require permits and inspections by environmental agencies.


Expansions

Increasing the building's footprint usually requires plan review and inspections.

Projects Affecting Fire Safety

Alterations that impact the means of egress (exits), fire-rated walls, or fire suppression systems are almost always subject to review.


Projects Affecting Accessibility

ADA compliance is often reviewed during renovations.

How to Find Out the Specific Requirements in Your Area


Contact Your Local Building Department

This is the most direct approach. Call or visit their website. Be prepared to describe the type of project you're planning.2.

Consult a Local Architect or Engineer

They will be familiar with the local codes and permitting process.3.

Review Local Ordinances

Many cities and counties publish their building codes and related ordinances online.

In summary:
It's possible you haven't seen external inspections and plan reviews due to the nature of the projects, lax enforcement, or grandfathering. However, it's also possible they happened without your direct knowledge. Having an engineer on staff rarely provides a full exemption. To be certain, check with your local building department. It is always wise to check with the local jurisdiction before starting a project, whether you are the owner, contractor, or an employee. Flag for review

Previous Question Next Question