Question: Really can't do much of any interior electrical work until after structural steel is complete correct? Or starting on floors above then you can work on floors below? It's a 3 story building.

You're generally right, but let's break it down to give you a more nuanced answer. You'll likely have different phases of electrical work.

General Principle

Safety and accessibility are paramount. You can't safely and efficiently run permanent electrical services if the structural steel isn't in place and generally inspected.

Why the Delay?
Conduit Runs & Support

Many electrical conduit runs need to be attached to the structural steel. You need the steel in place to know where the conduit can be supported.


Structural Changes

It's rare, but sometimes adjustments are made to the steel during erection. Running electrical before this could lead to rework if the steel is modified.

Safety

Steel erection is inherently dangerous. Having electrical workers in the same area as steel workers significantly increases the risk of accidents (dropped objects, etc.).


Accessibility

Once the steel is up, it provides walkways and points for lifting materials, making electrical work easier and safer.

Stages of Electrical Work and Steel Completion

Here's a possible phased approach to electrical work, relative to the steel completion:1.

Pre-Steel (Very Limited)



Underground Rough-in

You
can often start with underground conduit runs before steel erection. This includes running conduit for services coming into the building. Ensure these are accurately located relative to the future steel columns. Get the engineer's approval.

Grounding Grid

You can install the grounding grid (a network of buried copper wire connecting to the building's ground) before the steel goes up, as its location is generally fixed.

Temporary Power

Setting up temporary power for the steel erectors (and later other trades) is critical. This usually requires some electrical work at the perimeter, but it's a separate system from the building's permanent electrical.2.

During Steel Erection (Limited, Specific Tasks)



Embedded Conduits

Some conduits need to be embedded in the concrete slab, and those slabs might be poured after the steel is up. This requires close coordination with the concrete contractor. This should be carefully planned with your design team.

Sleeves

Install sleeves through steel members for future conduit runs.


Grounding to Steel

As steel is erected, ground it per code requirements.3.

After Steel Erection, Before Floor Slabs (1st Phase Rough-In)



Main Service Entry

Install the main electrical service equipment and meter.


Vertical Risers

Run vertical conduit risers and wiring from the service to the upper floors. These are often in shafts, so make sure the shafts are prepared.

Main Distribution Panels

Install the main electrical distribution panels on each floor.


Conduit Runs (Horizontal)

Start running the major horizontal conduit runs across each floor.

Grounding and Bonding

Complete grounding and bonding throughout the steel structure.4.

After Floor Slabs Are Poured (2nd Phase Rough-In)



In-Slab Conduit

Install conduit within the floor slab for outlets, data, and other systems.

Wall Rough-In

Start running conduit and boxes within interior walls
after the walls are framed (or at least the locations are precisely known).5.

After Walls are Closed (Trim-Out/Final Connections)



Wiring Devices

Install outlets, switches, light fixtures, etc.

Panel Wiring

Final wiring of the electrical panels.


Testing and Commissioning

Testing all systems and ensuring they are operating correctly.

Working on Lower Floors While Steel is Erected Above

The key here is isolation and safety.

Absolutely Coordinate

You
must have a very clear safety plan with the steel erectors and the general contractor.

Protected Work Zones

Work areas on lower floors MUST be completely isolated and protected from overhead hazards. This often means physical barriers (e.g., netting, solid barriers) to prevent falling objects.

Communication

Constant communication between the trades is vital. Everyone needs to know what everyone else is doing.


Sequencing

Carefully plan the sequencing of work to minimize conflicts. Maybe electrical work is done on one side of the building while steel erection is on the other.

Inspections

Thorough inspections are required to ensure work is being done safely and to code.

Important Considerations



Local Codes

Always comply with local building codes and electrical codes. They may have specific requirements for working around steel erection.

Engineer Approval

Always get the approval of the structural engineer and electrical engineer for any deviations from the plans.


Coordination Meetings

Regular coordination meetings between the electrical contractor, steel erector, GC, and other trades are essential.

Change Orders

Be prepared for potential change orders if unexpected conditions arise.

In Summary:


You can't typically begin major interior electrical work
before the structural steel is complete. However, there are some pre-steel tasks (underground, grounding) and some tasks that can be done concurrently with extreme care and coordination. Working on lower floors while steel is erected above is possible* with strict safety protocols and careful planning. A phased approach to the electrical work is crucial. Always prioritize safety and communication. Consult with your design team and the general contractor to develop a detailed plan. Flag for review