Question: GC want me to figure dropping conduit and wire to floor for removal by others after we disconnect it.Not exactly sure how to approach capturing right amount of time to drop conduit/wire to floor that is run exposed on ceilings. Obviously depends on size and length of run.Would you cut it in sections in place then drop it.

You're right, there's no one-size-fits-all answer. Breaking it down and estimating the factors will get you the best estimate. Here's a breakdown of how to approach estimating the time, along with things to consider

I. Assessment & Planning (Critical First Step - Don't Skip!)
Site Visit is Mandatory (if possible)

A thorough site visit is essential. You can't accurately estimate without seeing the actual conditions.


Documentation

Take pictures and videos.

Conduit Material

Is it rigid, EMT, IMC, PVC, or flexible? Rigid takes longer to cut and work with. PVC is easy to cut but might be brittle depending on age.


Conduit Size(s)

Diameter of the conduit is a HUGE factor in cutting time, weight, and ease of handling. Make note of all sizes.

Conduit Length(s)

Total length of each run to be removed. Longer runs require more cutting, support, and handling.


Wire Size(s) and Type(s)

What kind of wire (THHN, XHHW, etc.)? How many conductors? Larger gauge wire is heavier and harder to pull/handle. Aluminum wire is lighter but may require more care due to oxidation/brittleness.

Wire Fill

How full is the conduit? Heavily filled conduit is harder to pull wire from.


Mounting/Supports

How is the conduit supported? Straps, unistrut, j-hooks, wire hangers? How far apart are the supports? Are the supports easy to remove (screws, bolts, or rusted/seized)?

Accessibility

Is there clear access with a ladder or lift? Are there obstructions (pipes, ductwork, other conduit)? Is it over equipment that needs protection? Is it in a tight, awkward space? Is there good lighting?


Height

The higher the conduit, the more time it takes due to ladder work and potential use of a lift.

Hazards

Identify any hazards: energized equipment nearby, asbestos (if old building), water/sprinkler lines, slippery floors, trip hazards.


Permits/Requirements

Are there any site-specific safety requirements, permits, or procedures to follow? (e.g., lockout/tagout)

Communication

How does the GC want it? Is there coordination with other trades, or does it need to be gone by certain day?

II. Breaking Down the Work (Time Estimate)
1. Preparation



Safety Setup

Setting up barriers, warning signs, and drop cloths. (15-30 minutes, possibly longer)

Tool Gathering

Getting all necessary tools and materials to the work area (saw, cutters, screwdrivers, wrenches, pliers, tape, markers, etc.). (15-30 minutes)


Lockout/Tagout

If the circuit is still live, proper lockout/tagout procedures are required. This can take 30 minutes to an hour, depending on the system.

Safety First!
Lift/Ladder Positioning

Moving and positioning the lift or ladder for each section of work. (5-15 minutes per position change)2.

Cutting/Disconnecting Conduit



Cutting Conduit

This is where the biggest variability is.

Small Conduit (1/2" - 3/4" EMT)

5-10 minutes per cut (using a powered cutter). 10-20 minutes with a manual cutter.


Medium Conduit (1" - 2" EMT/Rigid)

10-20 minutes per cut (powered cutter). 20-40 minutes with a manual cutter.

Large Conduit (2.5" - 4" Rigid)

20-45 minutes per cut (powered cutter). Manual cutting is very difficult and time-consuming.


PVC Conduit

Much faster to cut (a few minutes per cut), but you might need to be careful if it's old and brittle.

Support Removal

Removing straps, hangers, etc. Factor in seized or rusted hardware. Assume 2-5 minutes per support, but add extra time for difficult ones.3.

Wire Removal



Pulling Wire

This can be easy or extremely difficult depending on the wire fill, number of bends, and length of the run.

Easy Pull

5-10 minutes per 50 feet.


Moderate Pull

10-20 minutes per 50 feet.

Difficult Pull

20-45+ minutes per 50 feet. You might need wire pulling lubricant.


If conduit is short

can sometimes be simpler to leave the wire in and let the demolition crew deal with it, just make sure it is dead.

Cutting Wire

If you can't pull the wire, you'll need to cut it in sections. This takes a few minutes per cut.4.

Lowering Materials



Lowering Conduit Sections

Important to estimate a time factor for safely lowering each section to the floor. The size and weight of the section will determine this. Consider using rope to safely lower heavier sections. (5-15 minutes per section, depending on weight/size).

Lowering Wire

Coiling and securing the wire as you lower it. (5-10 minutes per coil).5.

Cleanup

Gathering scrap materials and preparing them for removal by others. (30-60 minutes, depending on the quantity of scrap).

III. Example Calculation

Let's say you have a 100-foot run of 1" EMT conduit with moderately filled wires, supported every 10 feet, about 12 feet high.

Preparation

30 minutes.


Lockout/Tagout

0 minutes (already de-energized).

Lift/Ladder

20 minutes (total for positioning).


Cutting (Every 10 feet)

10 cuts 15 minutes/cut = 150 minutes.

Support Removal

11 supports 3 minutes/support = 33 minutes.

Wire Pulling

100 feet, moderate pull, 20 minutes per 50 feet = 40 minutes.

Lowering Conduit

10 sections
10 minutes/section = 100 minutes.

Lowering Wire

2 coils
10 minutes/coil = 20 minutes.

Cleanup

45 minutes.


Total

30 + 20 + 150 + 33 + 40 + 100 + 20 + 45 =

438 minutes (7.3 hours)
IV. Factors to Add to Your Estimate



Complexity Factor

Add a percentage (10-30%) to account for unforeseen issues, delays, or difficulties.


Learning Curve

If you haven't done this type of work before, add time for learning and adjustment.

Breaks

Factor in reasonable breaks for your crew.


Travel Time

Travel to and from the job site.

Material Procurement

Time to acquire any necessary materials.

V. Communication with the GC



Be Clear and Detailed

Explain your assumptions and the factors that influence your estimate.

Contingency

Include a contingency in your bid to cover unexpected problems.


Change Orders

Make it clear that any changes to the scope of work (e.g., additional conduit runs, unexpected difficulties) will require a change order and additional compensation.

Get it in Writing

Ensure your estimate and any subsequent changes are documented in writing.

Key Tips



Use Unit Pricing

Develop a unit price for different types of conduit and wire removal. This will make future estimates faster.

Track Your Time

Keep track of the actual time it takes to perform similar tasks. This will help you refine your estimates over time.


Don't Lowball:
It's better to overestimate slightly than to underestimate and lose money.By carefully assessing the job, breaking it down into smaller tasks, and considering all the relevant factors, you can create a more accurate and profitable estimate. Remember safety is paramount! Flag for review