Question: when a feeder breaker feeds a fused disconnect, which one should be coordinated to activate first. fuse or breaker? I understand they are in series so the outage will be the same regardless, but should the breaker trip before the fuse blows? I believe its easier to reset the breaker than to install a new fuse, is this correct?
You are correct in your thinking. In a coordinated system, the breaker should trip before the fuse blows. Here's why: Ease of Restoration
As you mentioned, resetting a breaker is significantly easier and faster than replacing a fuse. Minimizing downtime is a key goal in electrical system design.
Cost
Fuses are a consumable item. Blowing a fuse incurs a replacement cost (labor and materials), whereas resetting a breaker is free.
Selective Coordination
The principle of selective coordination ensures that only the closest upstream protective device to a fault operates, minimizing the impact of the outage. In this case, if a fault occurs in the load fed by the fused disconnect, you'd ideally want the fuse to blow only if the breaker fails to clear the fault.
Damage Prevention
If a smaller overcurrent exists for a longer duration, allowing the breaker to trip first can prevent the fuse from being damaged or weakened by the heat generated before its eventual operation.
How to achieve coordination
Time-Current Curves (TCC)
Coordination studies rely heavily on comparing the time-current curves of the breaker and the fuse. The breaker's TCC should lie below and to the left of the fuse's TCC. This means that for any given fault current, the breaker will trip faster than the fuse will blow.
Ampere Ratings
Typically, the breaker's ampere rating will be higher than the fuse's ampere rating, allowing the breaker to handle normal load fluctuations without nuisance tripping, while the fuse provides backup protection.
Fuse Type
Selecting the correct type of fuse is crucial. Fast-acting fuses, time-delay fuses, and current-limiting fuses all have different characteristics that affect their coordination with breakers.
Consult an Engineer
Coordination studies are complex and require expertise in electrical system design and protective device characteristics. Always consult a qualified electrical engineer to perform a coordination study and ensure proper protection and selectivity.
Important Considerations
Fault Current Magnitude
For very high fault currents, the fuse might operate almost simultaneously with the breaker, even with proper coordination. However, the goal is to ensure the breaker operates first for lower-level overloads and short circuits.
Available Fault Current
The available fault current at the location of the devices is critical. This information is used to calculate the operating times of the devices and to ensure that they can interrupt the fault current safely.*
Code Requirements: Electrical codes (like the NEC in the US) may have specific requirements for selective coordination in certain applications, such as emergency systems or life safety equipment.In summary, coordinating the breaker to trip before the fuse blows is the preferred approach in most applications to minimize downtime, reduce costs, and improve system reliability. Proper coordination requires careful selection of breaker and fuse characteristics, thorough analysis using time-current curves, and consideration of available fault current. Always consult with a qualified electrical engineer for coordination studies. Flag for review