Question: I've gotten several different answers on how to do this, would greatly appreciate the help!So there's a main service at a building with a ground to neutral.we're tapping off our main solar disconnect some hundred feet away outside line side of the service (the service is inside a building).would a ground electrode be required to be installed at the solar disconnect, or must it be a direct gec to the existing ground rod? would we run a ground wire to connect that ges system to the main service ges, how would we do that? or does the neutral count as what ties the two ges systems together?Can't find any code articles that say one way or the other, once again really appreciate the help!

Okay, this is a common point of confusion and I can see why you're getting different answers. Let's break it down based on the NEC (National Electrical Code) and common best practices.

The Short Answer (and then we'll explain why)



Yes, a Ground Electrode System (GES) is required at the solar disconnect.
You DO NOT need a direct GEC (Grounding Electrode Conductor) to the existing ground rod at the main service. Instead, you need to bond the GES at the solar disconnect to the main service's GES. The neutral DOES NOT count as the bond between the GES systems. Run an Equipment Grounding Conductor (EGC) to connect the solar disconnect's GES to the main service GES.The Explanation (Breaking down the NEC)

Here's the rationale and the applicable NEC (2020 version) considerations, though earlier or later versions of the NEC will have similar requirements:1.

Line Side Tap and Separately Derived System

You're tapping the solar system line side of the main service disconnect. This effectively creates a separately derived system. A separately derived system (SDS) is a power source that has no direct electrical connection to the building's existing system (other than the grounding connection). Your solar system is creating its own "power" and feeding it into the existing system.

NEC 250.30
and 250.32 are key articles for separately derived systems.2. Grounding Separately Derived Systems (250.30)



250.30(A)
states that for an SDS, a grounding electrode system (GES) shall be installed at the location of the SDS. 250.30(A)(1) describes the methods for establishing the GES, which includes the use of electrodes specified in 250.52(A)(1) through (A)(7). This typically means a ground rod, ground ring, concrete-encased electrode (ufer), etc. Therefore, you need a ground rod (or other acceptable electrode) driven at the location of the solar disconnect.3. Bonding the GES Systems (250.32)



250.32
requires that the GES for the separately derived system (your solar disconnect) be bonded to the existing building's grounding electrode system. This is crucial for safety. 250.32(A) Exception allows you to avoid the requirement for a local GEC if the service-entrance grounding electrode is used, but in that situation it requires you to follow 250.32(B). The easiest and most common way to meet that requirment is as described in 250.32(B)(1) This bond is established using an Equipment Grounding Conductor (EGC). This is NOT the same as the GEC. The EGC is run with the circuit conductors from the solar disconnect back to the main service equipment. The EGC's purpose is to provide a low impedance fault current path back to the source. 250.32(B)(1) requires that the size of the EGC used to connect the seperately derived system's electrode system to the building's electrode system is in accordance with 250.122, which relates to the circuit overcurrent protective device size. Why not use the neutral? The neutral should not be used as the primary fault current path. It's already carrying normal load current. A fault should be cleared as quickly and safely as possible, and the EGC provides that low-impedance path.4. Why all this matters



Safety

Proper grounding and bonding are essential to clear faults quickly and safely, minimizing the risk of electric shock.


Voltage Stabilization

Proper grounding helps maintain a stable voltage reference, reducing the likelihood of voltage fluctuations that could damage equipment.

Lightning Protection

While not a primary lightning protection system, a well-grounded system provides a path for lightning energy to dissipate.

Steps to Take


Install a Ground Electrode System at the Solar Disconnect

Drive a ground rod (or other approved electrode per NEC 250.52) near the solar disconnect.
2.


Connect the Solar Inverter/Disconnect to the GES

Connect the grounding terminal of the solar inverter/disconnect to the ground rod using a properly sized grounding electrode conductor (GEC).3.

Run an Equipment Grounding Conductor (EGC) with the Circuit Conductors

Run an EGC from the solar disconnect back to the main service panel. This EGC MUST be sized according to NEC 250.122, based on the size of the overcurrent protection device (breaker or fuse) protecting the solar circuit.
4.


Connect the EGC at the Main Service Panel

Terminate the EGC at the main service panel's grounding bus bar. This bus bar is already bonded to the building's main grounding electrode system.

Important Considerations



Local Codes

Always check with your local electrical inspector and AHJ (Authority Having Jurisdiction). They may have specific requirements or interpretations of the NEC.

Qualified Electrician

This type of work should be performed by a licensed and qualified electrician familiar with solar installations and grounding requirements. Improper grounding can be dangerous and can void warranties.


Equipment Instructions

Follow the manufacturer's instructions for the solar inverter and disconnect regarding grounding.

In summary

Yes, you need a ground rod at the solar disconnect. No, you don't need a separate GEC all the way back to the main service's ground rod. Instead, you bond the two GES systems together using an Equipment Grounding Conductor (EGC) run with the circuit conductors back to the main service panel. This EGC provides the necessary fault current path.