Question: A customer has a existing Enphase solar system and wants to add a small Energy storage system to use their solar during an outage, to do this I recently learned about a type of ATS called a Microgrid Interconnect Device (MID) [defined in the code] Its basically a automatic 200A disconnect rather than 'transfer', think of a ATS with no generator landed.Their solar person is proposing to use a goofy looking 'meter socket adapter' despite not being allowed by our utility.They want an electrical contractor (me) to install a 'separate meter can downstream of the utility meter'.I dont know why they even bother with this, seems like a hack to me, so I am asking you experts your thoughts on thisHere is the unit:https://enphase.com/download/iq-meter-collar-data-sheetWhat would you do here and if you have installed one how well do these things work?I am not familiar with Enpahse products and their site is so full of fluff its unusable, do any of you more up to date with Enphase people know if have a 3R ATS like enclosure or 'stand alone MID' product that does not make me look like a I am clown nose?I take it then dont, but I'd love to be worng.Then I noticed it takes a 24V control cable, and in the past I have done controls for commercial ATS's that mix and match brands so I got thinking can I use the Enphase 24V with a off the self 200A ATS?Thanks everyone for reading.

Okay, let's break down this Enphase microgrid integration situation and address your concerns. You're right to be skeptical – the "meter socket adapter" approach often feels like a workaround and can raise red flags with utilities.

Understanding the Problem and Enphase's Approach Enphase Ecosystem

Enphase excels at grid-tied solar systems. Their microinverters convert DC power from solar panels directly to AC at the panel level, simplifying installation and offering per-panel monitoring. However, integrating backup power (off-grid capability) has traditionally been a weak point.


The Challenge of Backup Power

To use solar during an outage, you need a way to disconnect from the grid (to prevent backfeeding power that could endanger utility workers) and a way to create a local, isolated "microgrid." This typically involves an automatic transfer switch (ATS) and some form of energy storage (batteries).

Enphase's Meter Socket Adapter (IQ Meter Collar)

This device is designed to
simplify (though it often complicates) the microgrid connection. It's a passive device that goes between the existing utility meter and the meter socket. The Enphase Encharge storage system can sense a grid outage. When it does, it initiates an open and then connects, isolating the home from the grid. The problem, as you've discovered, is that many utilities don't allow these, as they can tamper with metering and create potential safety issues.



The "Separate Meter Can Downstream" Idea

This is a way to placate the utility. The adapter (between the actual service meter and meter base) is still there doing its thing, and a separate meter can downstream from the 'adapter' would satisfy the utility (the meter itself is irrelevant since there is no load past the meter, you can just jump it)

Why the Meter Socket Adapter Can Be Problematic

Utility Approval

As you've already found, utilities often prohibit these due to concerns about metering accuracy, potential tampering, and safety. This is the biggest hurdle.


Code Compliance

Ensure this approach complies with all local electrical codes and NEC requirements, particularly regarding service equipment, disconnects, and interconnection with the grid. It is likely that the utility-side meter will not qualify for the service entrance disconnect.

Complexity

While intended to be simple, these adapters can add complexity and potential points of failure.


Aesthetics

They aren't exactly beautiful.

Your Concerns are ValidYou're right to question this approach. It often feels like a workaround, and it's essential to do things the right way, even if it's more work.

Alternatives and Recommendations1.

Prioritize Utility Approval

This is the first step. Get written approval from the utility for any proposed interconnection method. Without it, you're dead in the water. Clearly explain how the system will work and provide documentation.2.

Enphase's Preferred Solution: MID-Compliant ATS (Microgrid Interconnect Device)



IQ System Controller

Enphase has transitioned away from heavy reliance on the meter socket adapter. The key component for safe, code-compliant microgrid formation is the

Enphase IQ System Controller (specifically the IQ System Controller 2). This device is
not just an ATS; it's a sophisticated energy management system that handles grid isolation, microgrid formation, and communication with the Enphase storage system.

Why it's Better

The IQ System Controller provides a clear, code-compliant point of interconnection with the grid. It offers features like rapid shutdown initiation, generator integration, and load management. It's designed to meet UL 1741 SA requirements for grid support.

Installation

The IQ System Controller is typically installed
between the main service panel and a subpanel that will be backed up by the Enphase storage system.

Outdoor Rated Options

While not a "3R ATS-like enclosure" in the traditional sense, the IQ System Controller 2 is outdoor rated (NEMA 4X) and can be mounted outside near the main service panel. It looks more like a high-end disconnect switch than a standard ATS.

Enphase Disconnects Enphase does sell some disconnects that are rated for outdoor use, but they are not a true 'ATS'3.

Off-the-Shelf ATS with Enphase Integration (Potentially Complex)



Your Idea about the 24V Control

This is theoretically possible, but it can be very complex and not recommended unless you have extensive experience with control systems and a deep understanding of both the Enphase system and the chosen ATS.

Challenges



Compatibility

Ensuring perfect timing and coordination between the Enphase system and the ATS can be tricky. You need to understand the Enphase communication protocols.

Safety

A mismatched system could create safety hazards if the grid isolation and microgrid formation aren't handled correctly.


Warranty

Modifying the Enphase system or using it in a way not intended by the manufacturer could void the warranty.

Steps to Take


Contact Enphase Support

Talk to Enphase technical support directly. Explain the situation, your concerns, and the utility's requirements. Ask them for the recommended solution for a grid-tied system with backup power in your area. They can provide documentation and diagrams.2.

Talk to the Utility

Engage with the utility early in the process. Present the proposed system design and get their feedback and approval.3.

Review NEC and Local Codes

Ensure that the proposed installation complies with all applicable electrical codes.4.

Present a Clear Proposal to the Customer

Outline the different options (meter socket adapter vs. IQ System Controller), their pros and cons, and the potential issues with utility approval. Let the customer make an informed decision.

In Summary Ditch the meter socket adapter unless you have explicit utility approval. It's often more trouble than it's worth. Focus on the Enphase IQ System Controller as the preferred solution. It's designed for safe, code-compliant microgrid formation. Avoid trying to cobble together an off-the-shelf ATS with the Enphase system unless you have extensive experience and are willing to take on the risks and complexity. Prioritize utility approval and code compliance.Good luck with the project! Let me know if you have any more questions. Flag for review

Previous Question Next Question