Question: My work has been all resi NM to date and I'm starting to do some EMT work. I recognize the install learning curve is on me. My question is about pricing. I've seen info on this form and others quoting labor at 4-8 hours per 100ft of 3/4 EMT installed, pulling 3-10AWG stranded 2-6 hours per 100ft, with the range covering degree of difficulty, number of boxes, etc.My next job is in the 50x60 garage of a barndo, 32ft center height. I'll be installing high bay lights and general use 20A receptacles around the perimeter. Are folks pricing generally per foot EMT, per foot wire pulling? and how much?

Okay, transitioning from residential NM to EMT in a barndo garage is a good step up! Here's a breakdown of pricing strategies and factors to consider for your situation, along with considerations specific to a barndo garage

Pricing Philosophy: "Time + Materials + Overhead + Profit"

The core of any electrical pricing is understanding your costs and adding a reasonable profit margin. Don't just guess; track your time on similar tasks to refine your pricing.

Breakdown of Costs for EMT Work1. Materials



EMT Conduit

3/4" EMT price per foot (check local suppliers). Factor in couplings, connectors, straps, set screw vs compression fittings.


Wire

10 AWG THHN stranded (price per foot per color).

Boxes

4" square boxes, covers, mud rings, etc.


Receptacles

20A receptacles, plates. Consider whether they are standard or heavy duty, single or duplex, etc.

High Bay Lights

Cost per fixture (including any mounting hardware).


Fasteners

Screws, anchors, etc.

Grounding

Grounding wire, connectors, grounding bushings.


Consumables

Drill bits, cutting oil, tape, wire lube, etc.

Optional

Pull string/rope for wire pulling.


Optional

Concrete anchors, Unistrut, straps, screws2.

Labor

(This is the most variable part, and where your experience will improve your accuracy)

Conduit Installation



Cutting & Bending

Time to cut, ream, and bend EMT to fit your layout. 32ft center height requires a lift of some sort.

Mounting

Time to secure conduit to the structure.


Assembly

Time to connect sections with couplings and connectors.

Box Installation



Mounting

Time to mount boxes to the structure.

Connecting Conduit

Time to connect conduit to boxes.


Wire Pulling



Pulling Wire

Time to pull wire through the conduit runs. Consider the length of the runs and the number of bends.


Terminating

Time to connect wire to receptacles and lights.

Fixture Installation



Mounting

Time to mount high bay lights. This includes connecting the wiring.

Grounding



Grounding Conductor Installation

Time to run and connect the grounding conductor.

Cleanup

Time to clean up the work area.


Layout and Planning

Don't forget to allocate time for planning the layout and conduit runs.3.

Overhead



Vehicle Expenses

Gas, maintenance, insurance.


Insurance

Liability, worker's compensation (if applicable).

Tools

Amortization of tool costs (benders, cutters, threaders, etc.)


Office Expenses

Phone, internet, software, etc.

Licenses & Permits

Cost of permits and licenses.4.

Profit

A percentage on top of your total cost to ensure your business is sustainable. 10-20% is common.

Pricing Methods - and Recommendations for You
Per Foot Pricing (EMT & Wire)

This is common, but you

MUST
factor in difficulty. It's a good starting point, especially when you're building experience.
EMT

Determine a per-foot price that covers materials (conduit, connectors, straps), labor (cutting, bending, mounting), and a portion of your overhead and profit. Start with the $4-8 range you mentioned, and adjust based on the specifics of the job (height, number of bends, mounting surface).

The height is a HUGE factor here.
Wire

Determine a per-foot price for wire pulling that covers the wire itself, labor (pulling, terminating), and overhead/profit. Use the 2-6 hour range per 100ft as a starting point.


Time & Materials

Track your time meticulously. Bill your hourly rate plus the cost of materials. This is a good option if you're unsure about the job's complexity. Be TRANSPARENT with the customer. Give them an estimate of hours, but explain that it's subject to change.

Lump Sum

This is the riskiest for you, especially when you're new to EMT. You need to be very accurate with your estimate. It's generally best to avoid this until you have more experience.


Hybrid

A combination of methods. For example, you might price the EMT installation per foot, and the high bay light installation as a fixed price per fixture.

Specific Considerations for the Barndo Garage
Height

32ft center height is a HUGE factor. You

WILL
need a lift of some sort. This adds to your costs (rental, transportation, operation). Factor this into your labor and overhead.
Mounting Surface

Is it steel frame, wood frame, or something else? This will affect your mounting methods and labor.

Access

Is it easy to get materials and equipment into the garage?


Barndo Construction

Barndos can sometimes have unique structural elements that make running conduit challenging. Be aware of potential obstructions.

Customer Expectations

Discuss the scope of work in detail with the customer. Make sure they understand what is included in your price.

Steps to Take Before Pricing
1. Site Visit

Absolutely essential. Assess the conditions, take measurements, and identify any potential challenges. Talk to the customer about their expectations.2.

Plan Your Layout

Sketch out the proposed conduit runs and box locations. This will help you estimate the amount of material needed.3.

Get Material Prices

Contact your local suppliers for current pricing on conduit, wire, boxes, and fixtures.4.

Estimate Labor Hours

Break down the job into individual tasks and estimate the time required for each. Be realistic and add a buffer for unexpected problems.5.

Calculate Overhead

Determine your hourly overhead rate.6.

Add Profit

Apply your desired profit margin to the total cost.7.

Present Your Quote

Provide the customer with a detailed quote that outlines the scope of work, materials, labor, and total price. Be clear about any assumptions or exclusions.

Example (Simplified - for illustration only)

Let's say you estimate:
100ft of 3/4" EMT 300ft of 10 AWG wire 10 boxes 6 high bay lights Lift Rental for 3 days: $500Material Costs: EMT: $2.00/ft = $200 Wire: $0.50/ft = $150 Boxes: $5.00/box = $50 Lights: $200/light = $1200 Other Materials (connectors, straps, etc.) = $100

Total Materials = $1700


Labor Estimate: EMT Install: 16 hours Wire Pulling: 8 hours Box Installation: 4 hours Light Installation: 6 hours Other Labor (planning, cleanup): 4 hours Total Labor = 38 hours

Labor Rate: $75/hour Total Labor Cost = $2850

Overhead: Let's say your overhead rate is $25/hour
Overhead Cost = $950

Lift Rental: $500Total Cost: Materials: $1700 Labor: $2850 Overhead: $950 Lift: $500 Total Cost = $6000

Profit (15%):
Profit = $900Total Job Price: $6900

This breaks down to: EMT Price per Foot: $200/100ft = $2.00/foot for materials. Your labor rate covers the install. So in this scenario, you might quote $8/foot installed for the 3/4 EMT. Wire pulling: similar logic. $150/300ft = $0.50/foot for materials. Your labor rate covers the install. In this scenario, you might quote $2/foot for pulling and terminating 3-10AWG THHN.

Key Takeaways



Don't Underestimate the Height

It dramatically impacts labor and equipment costs.


Track Your Time

The more you track your time on EMT jobs, the more accurate your estimates will become.

Get Multiple Quotes

Shop around for the best prices on materials.


Be Transparent with the Customer

Explain your pricing and be willing to answer their questions.

Start Small

If possible, start with a smaller EMT job to gain experience before tackling a large project like this.


Safety First:
Always prioritize safety when working with electricity and at heights.Good luck! This is a great opportunity to expand your skills and grow your business. Remember to be thorough, communicate clearly with the customer, and learn from each job. Flag for review