Topic: Large Wire Footages

User: Alwayslearningelec, Location: NJ

Asked on: Wednesday, November 12, 2025 at 10:17 am EST
Answered on: Wednesday, November 12, 2025 at 10:17 am EST

Question: For large feeder sizes how does the field/PM go about coming up with the footages when buying? Not the estimate I'm sure lol. True tape, company shop drawings?

You're right, the initial estimate is just that - an estimate. When it comes time to procure large feeder cable for a project, accuracy is paramount. Here's how the field/PM typically arrives at precise footages

1. Comprehensive Review of Approved Documents:
Approved for Construction (AFC) Drawings

This is
the starting point. These are the official drawings approved for the build, incorporating all changes and revisions.

Shop Drawings

Often, electrical contractors create their own detailed shop drawings based on the AFC drawings. These shop drawings often incorporate specific manufacturer product data and show precise routing, termination locations, and mounting details. These should be approved by the engineer of record before use.

Bill of Materials (BOM)

Developed from the shop drawings, the BOM lists
everything needed, including cable types and estimated lengths.

Conduit Routing Plans

Detailed plans showing the exact paths of the conduits housing the feeders. These might be incorporated into the shop drawings or exist separately.

2. Detailed Measurement and Verification



Physical Walkthroughs (if possible)

Ideally, the field team
physically walks the planned route. This is especially crucial for complex runs, existing buildings, or areas with potential obstructions.

"True Tape" Measurement

This is the core of the process. Using a measuring wheel (for straight runs) and a physical tape measure (for bends, offsets, and around obstacles), the team meticulously measures the actual conduit path.

Add for Vertical Runs

Remember to account for vertical rises and drops.


Mark on Drawings

The measured lengths should be clearly marked directly on the AFC/shop drawings.

Software-Based Measurement



CAD Software

If the AFC drawings are in CAD format, the field team or the office team can use CAD tools to accurately measure the distances of the cable runs directly on the digital drawings.

BIM (Building Information Modeling)

If the project uses BIM, the 3D model provides highly accurate length measurements and can identify potential clashes and issues before installation.


Consider Conduit Fill

Even with precise measurements, remember to account for conduit fill requirements and derating factors. This can influence the required cable size and, potentially, the overall run length if you need to upsize the conduit.

3. Adding Buffer/Waste Factor



Importance

A crucial step is to add a buffer (safety factor) to the measured length. This accounts for:


Slack for Termination

Enough slack at the panels, transformers, or equipment for neat and easy termination.

Routing Adjustments

Unforeseen obstacles or minor adjustments needed during installation.


Waste

Inevitable waste due to cutting and handling.

Buffer Percentage

The percentage added varies depending on factors like cable size, run complexity, and company policy, but it's usually in the range of 5% to 15%. Larger, stiffer cables and more complex runs typically require a larger buffer.


Minimum Slack

Also, consider a minimum amount of slack. For example, always add at least 10 feet of extra cable to the total length regardless of other factors.

4. Coordination and Communication



Field-to-Office Communication

Clear communication between the field team (doing the measuring) and the office team (placing the order) is essential.


Review with Project Engineer/Design Team

If there are any significant discrepancies between the measured lengths and the original design, it's important to review them with the project engineer or design team to ensure the cable will still meet the project requirements.

5. Company-Specific Procedures and Tools



Standardized Forms

Many companies have standardized forms or checklists for recording measurements and calculating cable lengths.


Custom Spreadsheets

Some companies use custom spreadsheets that automatically calculate the total cable length based on the measured lengths, buffer factors, and other inputs.*

Cable Pulling Software

Some specialized software packages can help plan cable pulls, calculate pulling tensions, and estimate cable lengths.

Example Scenario


AFC drawings show a feeder run between Panel A and Transformer B.
2. The field team walks the route, notes that the conduit runs through a tight corner, and identifies some cable tray that wasn't shown on the original drawings.3. Using a measuring wheel and tape measure, they measure the straight sections, the length through the corner, and the length along the cable tray.4. They add for vertical rises and drops.5. They mark the measured lengths on a copy of the AFC drawing.6. Back in the office, they add a 10% buffer for slack and waste.7. The PM reviews the calculations and approves the cable order.In summary, buying the correct amount of large feeder cable involves a blend of careful review of approved drawings, meticulous field measurement, a healthy dose of buffer for unexpected issues, and clear communication between the field and office teams. True tape, and shop drawings are critical. Flag for review