Mike Dolt Enterprises Logo Mike Dolt Enterprises

Topic: Laundry Circuits

User: Jimmy7, Location: Boston, MA

Asked on: Thursday, November 13, 2025 at 7:48 am EST
Answered on: Thursday, November 13, 2025 at 7:48 am EST

Question: I have a customer who wants to run two circuits for an existing laundry closet that is located in a finished breezeway which is on a slab. I need to run the circuits across the unfinished basement and poke through to the laundry closet. They want two circuits in there due to the gas dryer, iron, washer, and rechargeable vacuum. The gas dryer is already installed, so working behind it will be a pain. In any case, would you just emt behind the washer and dryer on the finished Sheetrock wall? Sketch attachedSeparate question. If you’re installing a subpanel that has two factory installed ground bars the housing of the panel is sufficient, you don’t need to add a jumper between them, correct?

Okay, let's break down these questions about the laundry closet and subpanel.

Laundry Closet Circuits

Here's a recommended approach, along with considerations for your customer's situation and the provided sketch

Plan:

1. Assessment

First, confirm the following:

Local Codes

Crucially, verify your local electrical codes. The NEC provides a baseline, but local jurisdictions often have amendments. This is especially important for materials and specific requirements for laundry circuits.

Circuit Requirements

Determine the ampacity of the new circuits (likely 20A each).

Wiring Method

The following option uses EMT, which is a good choice for mechanical protection in an unfinished basement and provides a solid ground path.2.

Route Planning



Basement Run

Run the EMT across the unfinished basement, secured to the joists with appropriate EMT hangers. Maintain consistent spacing (typically every 4-6 feet, check your local code). Follow the guidance for distance below joists.

Penetration

Carefully choose your penetration point into the laundry closet. Aim for a spot that minimizes visibility and interference with existing utilities. If the wall is framed with wood studs, drill up high into a stud bay.


Laundry Closet Run

The recommendation for EMT behind the washer and dryer on the finished sheetrock wall is not a bad idea, but may be challenging due to the existing gas line and dryer.

Considerations



Gas Line Clearance

Absolutely essential! Maintain safe clearance from the gas line to the dryer. Consult your local codes for required clearance distances. If space is tight, consider re-routing the gas line by a qualified gas fitter to create more working room and clearance.

Accessibility

Plan your EMT runs so that you can access junction boxes for wiring connections
after the washer and dryer are installed. This may involve using a combination of EMT and flexible metal conduit (FMC or liquidtight flexible metal conduit (LFMC)) to make the final connections to the receptacles.

Receptacle Placement

Install the receptacles in easily accessible locations that will accommodate the appliances without strain on the cords. Consider recessed receptacles.3.

Execution



Drilling

Use appropriate drill bits and hole saws for drilling through framing and sheetrock. Be careful not to drill into existing wiring or plumbing.


EMT Bending and Cutting

Use proper EMT bending and cutting tools. Deburr cut ends.

Fastening

Use appropriate EMT fittings and connectors. Securely fasten EMT to the wall and ceiling.


Wiring

Use appropriately sized conductors (typically 12 AWG for 20A circuits). Color-code your wiring consistently (black/red for hots, white for neutral, green/bare for ground).

Connections

Make all connections inside junction boxes. Use appropriate wire connectors (wire nuts or crimp connectors).


Testing

Thoroughly test all circuits with a multimeter and circuit tester before energizing. Verify voltage, polarity, and ground integrity.

Responding to Customer Concerns



Gas Dryer

Acknowledge that working behind the gas dryer is difficult. Explain your plan to minimize disruption and prioritize safety. Emphasize the need for proper gas line clearance and the potential need to re-route it by a qualified professional.


Two Circuits

Reinforce the importance of two circuits for the appliances and rechargeable vacuum. This prevents overloading and potential fire hazards.

Finished Space

Explain that the EMT will be run neatly and securely in the basement. In the laundry closet, the EMT will be run as discreetly as possible.

Important Considerations Regarding the Laundry Equipment
Washer Outlet

The NEC requires a dedicated 20-amp circuit for the washing machine receptacle.

Dryer Outlet

The NEC states that an individual branch circuit must supply the dryer.


Location

The NEC states that receptacles shall not be installed in a face-up position in the countertop.

Subpanel Ground Bars


You are likely correct, but it depends on the subpanel manufacturer's instructions. Factory-Installed

If the subpanel comes with
two ground bars that are factory-bonded to the enclosure (the metal box), then

no
, you do not need to add an additional jumper between them. The factory bonding provides the necessary connection. Verify

Always consult the subpanel's installation instructions. They will explicitly state whether or not a jumper is required. If the instructions are unclear, contact the manufacturer's technical support.

If Not Bonded

If the ground bars are
not factory-bonded to the enclosure, or if there's any doubt, then

yes
, you must install a grounding jumper wire between the ground bars and the metal enclosure. This ensures a proper grounding path.

In summary:
Follow local codes rigorously. Prioritize safety, especially around the gas line. Communicate clearly with your customer. Verify the subpanel's grounding requirements. Test everything thoroughly. Flag for review

Previous Question Next Question