Topic: Utility requires inspection when no Permit exists

User: solarken, Location: Hudson, OH, USA

Asked on: Monday, November 17, 2025 at 8:58 pm EST
Answered on: Monday, November 17, 2025 at 8:58 pm EST

Question: I just completed a PV install on a new home under construction in a township that does not have any requirements for a building permit (Not for the house build and not for the solar). But our utility requires an inspection be done and evidence that it passed inspection and meets local code and NEC requirements. Has anyone been in a similar situation and what did you do to get the inspection passed documentation? The inspection passed doc is needed for the final interconnection agreement.I am NABCEP certified with an OHio electrical license, but thinking they will not let me self-inspect. There is a licensed electrician working on the electrical in the home now, but he does not know anything about solar. This place is in a fairly rural area. I did find a home inspector in the area, but I am guessing they just do general home inspections like during a home sale.

You're in a bit of a tricky situation, but it's not uncommon in areas with limited or no local building code enforcement. Here's a breakdown of how to approach this and potential solutions, along with considerations for each

Understanding the Requirements:
Utility's Authority

The utility has the leverage here. They want to ensure a safe and compliant installation before connecting to the grid. Their demand for an inspection is justified, even if the township doesn't require permits.


Local Code Adherence

Even without local enforcement, you're still obligated to install to the NEC (National Electrical Code). That's a legal and ethical imperative.

Inspection Type

Clarify with the utility
exactly what they need. Are they just looking for general compliance with NEC 690, or do they have a specific checklist or form? Get all the documentation requirements up front.

Possible Solutions (in order of most desirable to least)


Hire a Qualified Solar Inspector



Best Option

This is the ideal scenario if you can find one. This person knows solar installations, is familiar with the NEC, and can provide the documentation the utility requires.

Finding One



Start with the Utility

Ask them for a list of pre-approved inspectors or companies they've worked with in the past. They might have a preferred list.

Contact Other Solar Installers

Reach out to solar installation companies that operate in neighboring counties or regions. They might know of freelance inspectors or engineers who cover your area.


Search for "Solar Inspection Services" or "PV System Inspection"
: Use online search engines, focusing on geographic targeting near your area. NABCEP Professionals

While you're NABCEP certified, your utility may require an independent third party. However, the NABCEP website (nabcep.org) has a find installer / find professional tool. Use this to locate other professionals in the area and inquire if they can perform inspection services.


Ask for References

No matter who you consider, ask for references from previous clients.2.

Engage a Licensed Electrical Engineer (PE)



Why this works

A Professional Engineer (PE) with experience in electrical systems, particularly renewable energy, can review your installation, perform calculations, and provide a signed and stamped report certifying compliance with the NEC and relevant standards. This carries significant weight.


Finding One

Search for "Electrical Engineer renewable energy" or "Electrical Engineer solar PV design" and add your local area to the search.

Confirm Qualifications

Ensure they have experience with PV systems and understand the NEC requirements for solar installations.


Report Format

Discuss with the engineer the specific documentation requirements of the utility and ensure the report meets those needs.3.

Convince the Current Electrician to Learn (and Pay Them)



Upside

You already have someone on-site who is a licensed electrician.


Challenge

They admit they don't know solar.

Approach



Offer to Train

Provide them with resources (NEC 690 articles, online courses, manufacturer installation manuals). Offer to walk them through the system and explain the key inspection points.

Compensate for Learning

Acknowledge that they'll need to invest time in learning and adjust your payment to compensate for their effort.


Supervise Closely

If they're willing to learn, supervise their inspection closely and answer any questions.

Documentation

They'll need to be comfortable signing off on the inspection and providing the necessary paperwork.4.

Explore "Self-Inspection" Possibilities (Unlikely, but Worth Asking)



Low Probability

It's unlikely the utility will accept this due to conflict of interest, but it's worth asking them directly.

If Allowed

If they
do allow it, get very specific about what documentation they need from you as the installer. A detailed checklist, photos, and calculations will be essential. This is still not recommended as it is a potential liability and safety concern.

Liability

If allowed, be sure to have a separate set of eyes review the work.5.

Home Inspector (Least likely to work)



Typically Insufficient

Most home inspectors don't have the specialized knowledge to properly inspect a PV system for NEC compliance.


Extreme Case

If you can find a home inspector who specifically advertises experience with solar PV inspections and can provide the documentation the utility needs, then it might be an option, but be very cautious. Thoroughly vet their credentials and experience.

Key Steps to Take Now


Contact the Utility

Speak to the interconnection department and get precise information about their inspection requirements. Ask: What specific code version (e.g., NEC 2020, NEC 2023) do they require compliance with? Do they have a preferred inspector list or specific forms that must be used? Will they accept a report from a licensed electrical engineer? Will they ever consider self-inspection (unlikely)? What are the consequences of failing the inspection?2.

Document Everything

Keep detailed records of your installation, including:
Permit Applications (even if not required by the township, create one for your records) System design plans and calculations Equipment specifications and datasheets Wiring diagrams Photos of the installation process, especially critical connections and grounding Test results (voltage, current, insulation resistance)3.

NEC Compliance is Paramount

Even if it's tempting to cut corners in an area with no enforcement,
don't. Adhere strictly to the NEC. Your safety, the homeowner's safety, and the integrity of the grid depend on it.4.

Be Proactive

Start contacting potential inspectors or engineers now. Don't wait until the installation is complete.

Important Considerations



Liability

You're responsible for the safe and compliant installation of the PV system, regardless of local permit requirements.

Future Issues

A poorly installed or non-compliant system can lead to performance problems, safety hazards, and difficulties selling the home in the future.


Cost:
Factor in the cost of the inspection when budgeting for the project.By following these steps, you'll increase your chances of obtaining the necessary inspection documentation and getting your PV system interconnected to the grid safely and legally. Good luck! Flag for review