Topic: branch circuit or feeder ?

User: jimbo123, Location: Portage, Indiana NEC: 2008

Asked on: Thursday, December 23, 2010 at 11:50 pm EST
Answered on: Monday, May 13, 2024 at 11:31 pm EDT

Question: I ran 3 phase conductors and a egc to a pvc box with a main breaker, 160' run.The field device wiring went out in another conduit to a different location, now i find out i need 3 control wires from the pvc box to the panel where i got the 3 phase wires from. My question is do need another conduit for the control wires ?

Yes, you need another conduit for the control wires.The National Electrical Code (NEC) requires that control wires be run in a separate conduit from power wires. This is because power wires can create electromagnetic interference (EMI) that can disrupt the operation of control wires.The EMI from power wires can cause the control wires to pick up noise, which can lead to errors in the control system. In some cases, the EMI can even cause the control system to fail.To avoid these problems, it is important to run the control wires in a separate conduit from the power wires. This will help to ensure that the control wires are protected from EMI and that the control system operates properly. Flag for review

Previous Question Next Question