Question: We are trying to get through plan check at a dental office in downtown Los Angeles. The Plan Checker is saying that I have to install Hospital Grade Receptacles per a correction. I have been looking at Article 517 and we did provide a redundant ground MC to satisfy the 517.12 "wiring methods" portion. However, I?m having a hard time locating where we need to install the Hospital Grade Rec. This Facility does not have med gas nor hospital beds. Although they are calling the rooms as OP 1, Op 2, these rooms are not operating rooms. I have an appointment tomorrow to clear the corrections and want to make sure I?m in the right. Any help would be appreciated.
Hospital Grade Receptacles (HGRs)
HGRs are typically required in medical facilities where the continuity of electrical power is critical for life-saving equipment. However, the NEC does not explicitly require HGRs in dental offices.
NEC Article 517
Article 517 of the NEC applies to healthcare facilities, including dental offices. However, Section 517.12, which addresses wiring methods, does not require HGRs. Instead, it requires a redundant ground conductor (RGC) for "grounded circuits that are part of the normal electrical system."Your Situation
Based on the information you have provided, it appears that you have already satisfied the NEC requirements by providing an RGC. Therefore, it is not clear why the Plan Checker is requiring HGRs.
Recommended Course of Action Review the Plan Checker's Correction
Determine the specific reason why HGRs are being required.
Consult with a Qualified Electrical Inspector
Get an independent opinion on whether HGRs are necessary in your facility.
Attend the Appointment Prepared
Gather any relevant documentation, including the NEC code and the Plan Checker's correction, to support your argument.
Be Respectful but Assertive
Explain your understanding of the NEC requirements and why you believe HGRs are not necessary.
Offer Alternative Solutions
If the Plan Checker insists on HGRs, you could propose alternative solutions such as installing GFCI receptacles or bonding the receptacle mounting box to the RGC.
Consider Appealing the Decision: If the Plan Checker still requires HGRs, you may have the option to appeal the decision to a higher authority. Flag for review