User: tommyrice, Location: Chapel Hill, NC
Asked on: Thursday, December 30, 2010 at 7:45 pm EST
Answered on: Monday, May 13, 2024 at 11:40 pm EDT
Question: in a recent nec forum discussion,someone said "technically you couldn't use a 3 ph panel on single ph service ".i understand the concept of not using something unless it's listed for the job you're doing. i have a customer who owns a storage bldg. that was previosly a lumber yard.he hopes by switching back to single ph , he can reduce the minimum monthly charge by the power co. i would like to change out the meter base,re-use the same mast,panel(which already has 120volt lts and recepts).i would just re-arrange breakers to land on phases that have power.it would save money on cost of panel and labor.would you guys go along with this from an inspectors standpoint?
NEC 408.1 states, "Electrical equipment shall be installed and used in accordance with any instructions included in the listing or labeling."NEC 110.3(B) states, "Electrical equipment intended for use in outdoor or wet locations shall be approved for such use."A 3-phase panel is not listed for use on single-phase service. Additionally, the panel may not be suitable for outdoor use unless it is specifically labeled for such use.
From an inspector's standpoint
I would not approve the installation of a 3-phase panel on single-phase service. This would be a violation of NEC 408.1 and could pose a safety hazard. I would also require that the panel be replaced with a panel that is listed for outdoor use. This is required by NEC 110.3(B).
Additional considerations
It is not clear whether the existing panel is listed for single-phase service. It is important to verify this before making any modifications. If the existing panel is not listed for single-phase service, it should be replaced.* It is also important to ensure that the new meter base is compatible with the existing mast.
Conclusion:
Based on the information provided, I would recommend replacing the existing panel with a new panel that is listed for single-phase service and outdoor use. This would ensure that the installation is safe and code-compliant. Flag for review