User: Delcobob, Location: Oklahoma City
Asked on: Tuesday, January 4, 2011 at 9:50 am EST
Answered on: Monday, May 13, 2024 at 11:47 pm EDT
Question: For a 100A temporary feeder to a job site from a 400A 120/208V single phase temp panelboard, is a grounding conductor required to be ran with the underground direct burial phase conductors, or is a ground rod drven at the load end 100A panelbord OK?
A grounding conductor is required to be installed with the phase conductors. Flag for review