Question: got sited for using sch 40 under a residential drive way. wanted to get it covered so i changed it to sch, 80, Anyone know of a code requirement for this, the work was in MA,:-?
Massachusetts State Plumbing Code (248 CMR) 248 CMR 2.05(2) states that buried plastic pipe for natural gas distribution mains and services shall be Schedule 40 or 80 and at least 1 inch in size. 248 CMR 10.04(5) states that underground piping shall be SDR-23 or SDR-26 if installed below private driveways.
International Residential Code (IRC)* IRC P2905.3 states that plastic gas piping installed outside and below ground shall be Schedule 80.
Conclusion:
Based on the Massachusetts State Plumbing Code and the IRC, Schedule 80 plastic gas piping is required for underground installations below residential driveways in Massachusetts. Therefore, changing the piping from Schedule 40 to Schedule 80 meets the code requirements. Flag for review