Mike Dolt Enterprises Logo Mike Dolt Enterprises

Topic: em tap

User: sparky=t, Location: Colorado

Asked on: Thursday, January 6, 2011 at 7:06 pm EST
Answered on: Monday, May 13, 2024 at 11:56 pm EDT

Question: have a job that we are quoting, replace exisiting ATS, it is fed off of a 300 amp 480 volt switchboard (ITE) dated 1985, tapped right after main switch using 750 kcmil AL, service has 3000a KRPC fuses, customer now wants to add a disco between main disco and ATS for testing (this is an retirement / nursing facility) with out dropping the whole building , problem is board is full up, electrical room is full, I can get a breaker & enclosure in on the opposite wall after moving xfrmr, however that puts me just under 25' of tap and the largest conduit I can get into board is 2" due to over head clearances. by the way siemens does not have drawings any more as it is 25 yrs and the PA plant closed.Ideas? thanks

Option 1: Use a Remote Monitoring System

Install a remote monitoring system that allows the ATS to be tested without interrupting power to the building. This system would connect to the ATS via a communication network and enable remote monitoring and control.

Option 2: Install a Bypass Switch

Add a bypass switch between the ATS and the critical load. When testing the ATS, the bypass switch can be closed to maintain power to the critical load while the ATS is offline.

Option 3: Extend the Tap with a Distribution Panel

Install a distribution panel outside the switchboard and tap into the 750 kcmil AL after the main switch. The distribution panel can house a breaker for the disco. This solution requires running additional conduit and cabling.

Option 4: Use a Smaller Breaker

If the space in the switchboard is limited, consider using a smaller breaker for the disco. This may require increasing the conductor size to maintain voltage drop within acceptable limits.

Option 5: Enlarge the Existing Conduit

If possible, enlarge the existing 2" conduit to accommodate a larger conductor size. This may require modifications to the switchboard or electrical room.

Additional Considerations



Coordination with Building Management

Ensure that the testing procedure does not interfere with critical building systems or patient care.


Safety Precautions

Implement appropriate safety measures, including lockouts and tagouts, to prevent accidental energization during testing.*

Code Compliance:
Consult with local and national electrical codes to ensure compliance with all applicable regulations. Flag for review

Previous Question Next Question