Question: I'm new to the business side of electrical work. Is there a easy, fast way to estimate T & M on small jobs or residential jobs. The current job i'm estimating is a older home made of brick and plaster walls. it has a small basement. 1 st floor is around 600' with 6 rooms. 2 nd floor is around 800' with 7 rooms and the 3 floor is 25x25 attic could possibly be a bedroom. The meter is already in place it's a 400amp meter base with a 200 amp breaker. Almost all of the work will have to be wiremold because of the solid walls. Any help i will greatly appreciate. Thanks Phillip.
Estimating Time and Material (T&M) on Small Residential JobsStep 1: Estimate Labor Hours Measure the square footage of each room and hallway. Multiply the square footage by 0.25 hours per square foot for the first floor and 0.28 hours per square foot for the second floor (due to more complex wiring). Add an additional 0.15 hours per room for wiring the attic. Add 0.5 hours for installing wiremold in all rooms.
Step 2: Estimate Material Costs For wiremold, estimate 10 feet per room and 5 feet per hallway. For wire, estimate 25 feet of 12/2 NM-B wire per room and 15 feet for each hallway. Include other materials such as outlets, switches, and conduit (if needed).
Step 3: Apply Labor Rate and Material Markup Use a labor rate of $50-$75 per hour for residential electricians. Apply a markup of 15-25% on materials to cover overhead and profit.
Sample Calculation
1st Floor (600 sq ft): 600 x 0.25 hr/sq ft + 6 x 0.15 hr/room + 0.5 hr = 16.5 hours 2nd Floor (800 sq ft): 800 x 0.28 hr/sq ft + 7 x 0.15 hr/room = 23.6 hours Attic (25 x 25 sq ft): 25 x 25 x 0.15 hr/sq ft = 0.94 hours Wiremold: (6 rooms + 5 hallways) x 15 feet = 165 feet Wire: (6 rooms + 5 hallways) x 35 feet = 385 feet
Material Costs
Wiremold: 165 feet x $0.75/foot = $123.75 Wire: 385 feet x $0.20/foot = $77.00 Outlets: 6 x $1.50 = $9.00 Switches: 5 x $2.00 = $10.00
Markup
Materials: $219.75 x 20% = $43.95
Total Estimate
Labor: (16.5 + 23.6 + 0.94) x $60 = $2448.00 Materials: $219.75 + $43.95 = $263.70 Total: $2448.00 + $263.70 =
$2711.70Note: This is just an estimate, and the actual price may vary depending on the specific materials and labor costs in your area. Flag for review