Question: I need suggestions. I have two rigid pipes coming from underground through concrete into a single gang fd box. Unions are two wide in diameter. How do I install these pipes into the box. I can't twist the box onto two pipes. The pipes are 1-1/2" apart Center to Center.
Option 1: Use a "Double Hub" Conduit Body Install a double hub conduit body (similar to a single gang fd box but with two openings) onto the concrete. Thread the pipes into the hubs on either side. Secure the pipes and conduit body with locknuts.
Option 2: Use a "Reducer" Conduit Body Install a single hub conduit body (like a standard gang fd box) onto the concrete. Thread a reducer fitting into the hub. The reducer should have a 1-1/2" opening on one end to match the pipe diameter and a larger opening (e.g., 2") on the other end. Thread the pipes into the 1-1/2" openings of the reducer. Secure the pipes and conduit body with locknuts.
Option 3: Use a "Split Union" Split unions are two-piece unions that can be installed without twisting. Thread a male threaded end of one half of a split union onto each pipe. Slide the other half of the split union over the male threads and tighten with a wrench. Connect the split unions together by screwing them into each other.
Option 4: Use a "Flex Clamp" Flex clamps are two-piece clamps that can accommodate slightly different pipe diameters. Clamp each pipe with a flex clamp. Use a threaded rod to connect the two clamps together and tighten with nuts.
Option 5: Custom Fabrication* If none of the above options are suitable, you can have a custom-fabricated fitting or bracket dibuat which fits the specific dimensions of your installation. Flag for review