Question: Am I making a mountain out of a mole hill?New building with 3 phase service coming in. Power company sent in CCW rotation, no big deal. So all the power coming off the MAIN switchboard is CCW (Brown-Orange-Yellow). This board feeds several motor loads and ATS's.Rather then switch the phases at the incoming point, the EC decided to swap the phases at the generator and have CCW rotation going to the ATS's. 2 of the ATS's feed other switchboards. The EC swapped phases at the input to these switchboards, so now these switchboards are CW (Brown-Orange-Yellow).So as you go through the building, some places are A-B-C is Brown-Orange-Yellow and other's it is B-A-C is Brown-Orange-Yellow.They used colored wiring not phase tape.While not an actual violation, I believe in the future after several site manager turnovers, this could be an issue.What say you?Thank you.
Whether or not you are making a mountain out of a molehill depends on the specific consequences of having different phase rotations in different parts of the building.
Potential Consequences
Safety issues
If equipment is not designed for a specific phase rotation, it could malfunction or cause electrical hazards.
Maintenance challenges
Technicians may need to rewire or adjust equipment to match the different phase rotations, which could increase maintenance costs and downtime.
Confusion and errors
Electricians or other personnel working on the system could become confused and make mistakes due to the inconsistency in phase rotations.
Code compliance
While not a direct violation, the inconsistent phase rotations could raise questions about code compliance and may require additional documentation or labeling.
Resolution
To address these potential consequences, it is recommended to:
Standardize the phase rotation
Either switch the phases at the incoming point or at all the ATSs so that the phase rotation is consistent throughout the building.
Use phase tape
This will make it easy to identify the phases and prevent confusion or errors.*
Document the system
Create a clear and concise diagram or documentation that explains the phase rotation in different parts of the building.
Conclusion:
While the inconsistent phase rotations may not be a major issue initially, they could create significant challenges and risks in the future. It is prudent to address this issue proactively to ensure the safe and efficient operation of the electrical system. Flag for review