Topic: New home questions

User: tonype, Location: New Jersey

Asked on: Sunday, January 23, 2011 at 8:12 am EST
Answered on: Tuesday, May 14, 2024 at 12:39 am EDT

Question: New townhouse (had "Final" approval on the main box)1. Wiring to fire pump - are zip ties supports to the water pipe legit?http://i15.photobucket.com/albums/a352/TonyPE/IMGP0528.jpg2. Terminal bar in main panel not plumb - can this inadquate inadequte securing to the panel (I have never seen this before)?http://i15.photobucket.com/albums/a352/TonyPE/IMGP0521.jpg3. HVAC plenum return duct - took the cover off - 2 open boxes (I think at least one was for a receptalce that was abandoned when they realized it interfered with the return grill). Even if cover plates are provided to these boxes, are these allowed in a return plenum?http://i15.photobucket.com/albums/a352/TonyPE/IMGP0530.jpg

  1. The answer is yes - zip ties are legit supports for the wiring to the fire pump. The National Electrical Code (NEC) does not specify any particular method for supporting wiring to a fire pump, and zip ties are a common and acceptable method.2. The answer is no - the terminal bar in the main panel is not plumb and is inadequately secured to the panel. The NEC requires that all electrical equipment be securely mounted and that all wiring be properly supported. The terminal bar in this case is not securely mounted and could potentially come loose, which could create a hazardous condition.
    3. The answer to the HVAC plenum return duct is no - open boxes are not allowed in a return plenum. The NEC requires that all electrical boxes be covered and that all wiring be properly supported. The open boxes in this case are not covered and could potentially create a hazardous condition.
Flag for review

Previous Question Next Question