Question: NEC figure 310.60 has a note: Max. depth to top of electrical duct banks shall be 30 in.Will this 30 in. is from the top of electrical duct bak to finished grade level? I have seen some elec. details indicates from top of duct bank to grade is 42" or more as minimum....Thanks!
Yes, the 30-inch maximum depth specified in NEC Figure 310.60 is measured from the top of the electrical duct bank to the finished grade level.While some electrical details may indicate a minimum depth of 42 inches or more from the top of the duct bank to grade, this is not required by the NEC. The NEC's requirement for a maximum depth of 30 inches is intended to ensure that the duct bank is not buried too deeply, which could make it difficult to access and maintain.If a deeper burial depth is necessary for a particular installation, it is important to consult with a qualified electrical engineer to ensure that the duct bank is properly installed and protected. Flag for review