Topic: Setting up a 2000a service

User: Electron_Sam78, Location: Palm Bay, FL

Asked on: Monday, January 31, 2011 at 2:43 pm EST
Answered on: Tuesday, May 14, 2024 at 1:00 am EDT

Question: If you were setting up a 2000A service how would you do it? What equipment would you use? I've ever only installed up to 600a services so something this large is new to me. Is it practical to to use a safety switch that big? Do they even make one that big? From the transformer I imagine it would be metering equipment, disconnect, and distribution center.This will be outside serving a recreation area. There are two separate areas so this could be split into two 1000A services.

Equipment for a 2000A Service Transformer

Outdoor-rated, network-type transformer rated for 2000A at the appropriate voltage


Meter Socket

2000A meter socket with a sight port for visual inspection

Disconnect Switch

2000A fused disconnect switch with a minimum of 100kA interrupting rating


Distribution Center

Outdoor-rated distribution center with 2000A busbars and multiple breakers for downstream distribution

Conduit and Wiring

Heavy-duty electrical conduit and wiring suitable for 2000A current-carrying capacity


Grounding System

Comprehensive grounding system, including ground rods, ground wires, and bonding connections

Practicality of a 2000A Safety Switch


Yes, it is practical to use a safety switch for a 2000A service. Safety switches, also known as circuit breakers, are available with ratings up to 2000A and higher. These devices provide overcurrent protection, short-circuit protection, and fault isolation at the service entrance.

Component Layout

From the transformer, the following equipment would be connected in series:1. Transformer secondary terminals2. Meter socket3. Disconnect switch4. Distribution center5. Downstream breakers or fusesSplitting into Two 1000A Services

Splitting the 2000A service into two 1000A services is feasible. Here are some considerations: Each service should have its own transformer, meter socket, disconnect switch, and distribution center. The two services should be physically separated to minimize the risk of faults affecting both areas simultaneously. The total load should be evenly distributed between the two services to prevent overloading one service. The metering and billing setup should be coordinated with the utility provider to ensure accurate billing for each service. Flag for review