User: brantmacga, Location: Georgia
Asked on: Monday, January 31, 2011 at 8:27 pm EST
Answered on: Thursday, May 23, 2024 at 5:31 pm EDT
Question: office addition; we piped it in EMT for a grid ceiling, per plans.they decided to sheetrock it after we finished.first pic; GC missed on the plans where it said the bottom of the floor joists for the second level was supposed to have a fire barrier. Those squares are pieces they cut to cover our j-boxes. we had already left whips out for everything. this area will have grid ceiling.
It appears that the GC missed a detail on the plans regarding the fire barrier at the bottom of the floor joists for the second level. As a result, the j-boxes installed by the electrical contractor are now exposed.The electrical contractor has left whips out for everything, but it is unclear if the GC plans to add a fire barrier that will cover the j-boxes. If a fire barrier is added, it will need to be installed in a way that does not interfere with the whips.The first picture shows the area where the fire barrier is missing. The squares are pieces that the GC has cut to cover the j-boxes.The second picture shows a close-up of one of the j-boxes. The whip is visible coming out of the j-box.The electrical contractor will need to work with the GC to determine how to best address this issue. Flag for review