Question: Is the coordination study required only for emergency system not normal power system? I heard some folks said it is not required for normal power system, but I thought it was but couldn't find reference rules in NEC, can someone help? Was it changed under 2008 edition? Thanks!
Coordination study is required for both emergency system and normal power system.Coordination study is required for both emergency and normal power systems. The purpose of a coordination study is to ensure that the protective devices in an electrical system are properly coordinated to provide selective and reliable protection against overcurrent faults. This is important to ensure that only the affected portion of the electrical system is de-energized in the event of a fault, while the rest of the system remains energized.Coordination studies are typically performed using computer software that models the electrical system and simulates various fault conditions. The study results are then used to select and set the protective devices in the system to ensure proper coordination.The National Electrical Code (NEC) requires coordination studies for emergency systems in Article 700. For normal power systems, coordination studies are not explicitly required by the NEC, but they are strongly recommended by industry standards and best practices.The 2008 edition of the NEC did not change the requirements for coordination studies. Flag for review