Topic: 590.4(G) interp.

User: Hendrix, Location: New England

Asked on: Monday, February 7, 2011 at 12:51 pm EST
Answered on: Tuesday, May 14, 2024 at 1:15 am EDT

Question: Does this mean that a piece of ser run form a temp service, sleaved through a piece of 2" pvc, can be spliced just below the job trailer to another piece of ser and into the panel without a box ?

No, it does not mean that. A piece of SER run from a temp service, sleeved through a piece of 2" PVC, cannot be spliced just below the job trailer to another piece of SER and into the panel without a box.According to the National Electrical Code (NEC), all splices in electrical wiring must be made in an approved electrical box. This is for safety reasons, as it helps to protect the splices from damage and prevents electrical fires.In the case of a temporary service, the NEC requires that the service be installed in accordance with Article 590 of the NEC. Article 590 requires that all splices in temporary wiring be made in an approved electrical box.Therefore, it is not permissible to splice a piece of SER run from a temp service, sleeved through a piece of 2" PVC, just below the job trailer to another piece of SER and into the panel without a box. Flag for review

Previous Question Next Question