Topic: Bidding Post Light Changeouts

User: mkgrady, Location: Massachusetts

Asked on: Wednesday, February 9, 2011 at 1:41 pm EST
Answered on: Tuesday, May 14, 2024 at 1:22 am EDT

Question: I'll be pricing a job at a condominium where they have about 55 post lights. The posts and lights are 22 years old. Posts are cedar with no concrete, just dirt. About 15 of them are 10 feet above grade along a road. The rest are in courtyards off the road and closer to the buildings. All are being replaced.It's a tough tome of year to price this work because of all the snow but they want to get started on a budget before the snow melts and the ground thaws. I'm told the post lights are fed with UF cable direct buried from 4-5 buildings.So I'm picturing, when I dig up a post I will mostly find two UF cables running up the inside of each post. I hope they left a little slack at the bottom. I will need to remove the UF and send it up a new post. The new posts are going to be vinyl. The taller ones will have a galvy pipe in the center and will need to be backfilled with concrete. The shorter ones can be backfilled with just dirt. In both cases the new post will be an inch or two wider than the existing which are all 4-1/2 inches wide.My question is about labor and ideas. Can anybody help with manhours per post? The area has a lot of rock so the digging will likely be difficult at times. I will take exception to having to cut into any ledge (don't know if there is any) but I expect to find some rocks in the backfill. Any ideas that could make the job easier? One idea I had was to protect the old UF with a pvc sleeve while the digging is going on but that can't happen until I get the old post out of the way.Thanks in advance, Mike

Man-Hours per Post

The labor required for each post will vary depending on the specific conditions encountered, but here is a general estimate: Removal of existing post

0.5-1 hour


Installation of new post

1-1.5 hours

Backfilling and cleanup

0.5-1 hour

Total

2-3.5 hours per post

Ideas for Easier Installation
Use a post puller

This tool can significantly reduce the time and effort required to remove existing posts.

Drill pilot holes for the new posts

This will make digging easier, especially in rocky soil.


Use a level

Ensure that the new posts are installed vertically for a professional appearance.

Compact the backfill

This will prevent the posts from settling or leaning over time.


Use a concrete mix with rock-resistant additives

This will help prevent damage to the concrete by rocks in the backfill.

UF Cable Protection


While it is not possible to completely protect the old UF cable during digging, there are a few precautions you can take: Dig carefully

Use a sharp shovel and avoid hitting the cable with the blade.


Use a cable locator

This device can help you identify the location of the cable before digging.

Notify the utility company

They may have additional recommendations for protecting the cable during excavation.

Additional Considerations
Underground service lines

Be aware of any underground service lines, such as gas, water, or electrical lines, and proceed with caution.

Snow removal

If there is still snow on the ground, it may need to be cleared before excavation can begin.


Weather conditions:
Extreme cold or rain can make the work more challenging and may require additional precautions. Flag for review